ML20247P643
| ML20247P643 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 09/18/1989 |
| From: | Swenson W Office of Nuclear Reactor Regulation |
| To: | Fay C WISCONSIN ELECTRIC POWER CO. |
| Shared Package | |
| ML20247P648 | List: |
| References | |
| TAC-63152, TAC-63153, NUDOCS 8909270236 | |
| Download: ML20247P643 (2) | |
Text
7__
%y
--[
September 18, 1989:
[
c-i y '
Docket; Nos. 50-266 DISTRIBUTION:
and 50-301 Jocte n w ess NRC & Local PDRs PDIII-3 r/f MVirgilio JHannon WSwenson PKreutzer OGC-WF1 Mr. C. -W. Fay,= Vice President EJordan BGrimes T
Nuclear Power Department ACRS(10)
PDIII-3 Gray F
Wisconsin Electric Power Company Schan GBagchi 231 W. Michigan Street, Room 308 Milwaukee,' Wisconsin 53201
Dear Mr. Fay:
SUBJECT:
CONTAINMENT LINER LEAK CHASE CHANNEL VENTING (TAC NOS. 63152 AND 63153)
On July.24, 1986, Wisconsin Electric Power Company (WEPC0) submitted a request to qualify the containment liner leak chase. channels as an integral part of the containment liner plate. The staff has reviewed your request along with the additional information submitted on May 9, 1989 in response to a request for additional information.
Based on our review of the information submitted, the staff has concluded that the containment liner leak chase channels, as built, meet the intent.of the ASME B&PV Code,Section III. Therefore, the staff concurs'with WEPC0 that it is not necessary for the Point Beach Nuclear Plant to vent the containment liner weld leak chase channels during a containment integrated leak rate test. ' Visual inspections required by 10 CFR Part 50, Appendix J, Section V.A prior to any Type A test will
)
include those readily accessible portions of the containment liner leak chase channels.as well.
Sincerely, Warren H. Swenson, Project Manager Project Directorate III-3 Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated I
cc: See next page
\\
l DOCUMENT NAM - TACS 63152/53 j
Office:
III-3 FM/PDIII-3 PD PDIII-3 SurnarefKreutzer WSwenson/tg JHannon l
y/jf/89 1/J g/89 G/89 Date:
0+
4 89092W.C36 890M S
'PDR ADOW 0500 P
C-_--______--_-_____-_-_.
y
- l. '.
i Mr. C. W. Fay Point Beach Nuclear Plant i
J N
Wisconsin. Electric Power Company Units 1 and 2 l
cc:
Mr. Bruce Churchill, Esq.
Shaw,' Pittman, Potts and Trowbridge 2300 N Street, N.W.
Washington,.DC -20037 Mr. James J. Zach, Manager o
Point Beach Nuclear Plant Wisconsin. Electric Power Company i
6610 Nuclear Road Two Rivers, Wisconsin 54241 Town Chairman Town of Two Creeks Route 3 Two Rivers, Wisconsin 54241 Chairman Public Service-Commission of Wisconsin Hills Farms State Office Building Madison, Wisconsin 53702 Regiona1' Administrator, Region III U.S. Nuclear Regulatory Commission Office of Executive Director 1for Operations-799 Roosevelt Road Glen Ellyn, Illinois 60137 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, Wisconsin 54241 1
i
>