August 28, 1989' t
k
. Docket No. 50-458 --
Gulf States Utilities.
ATTN:: Mr.:. James C.: Deddens
..SeniorVicePresident(RBNG).
l' Post Office Box.220 1St. Francisville, Louisiana 70775
Dear Mr. Deddens:
SUBJECT:
ACCEPTANCE 0F OFFSITE DOSE CALCULATION MANUAL, REVISION 3-RIVER. BEND STATION, UNIT N0. 1 t
9.-
Referen'ces:
(a) - February 29,'1988 letter from W. A. Paulson to J.'C. Deddens.
(b) April 24, 1989 letter from 'J. E. Booker to NRC Document Control. Desk.
(c) June 15,1989. letter from D. W. Akers to W. Meinke.
. Reference (a)-documented NRC staff acceptance, with certain caveats, of
^ Revision 1 of the Offsite Dose Calculation Manual (0DCM) for River Bend Station, Unit No. I'.
Gulf States Utilities submitted Revision-3 to the ODCM with reference (b)'
that addressed the concerns expressed in reference (a).
Revision 3 of the ODCM for River Bend Station has been reviewed in its entirety by our contracter, EG&G, Idaho, Inc.. Their discussion and comments are contained in their letter' evaluation DWA-33-89 accompanying reference (c) (enclosed).
The NRC staff concludes that the ODCM, Revision 3, meets the guidance in
'NUREG-0133.and the requirements of the River Bend Station Technical Specifications.
.Therefore, the staff finds-Revision 3 of the ODCM to be an acceptable reference.
Some questions remain, however, regarding Revision 3 and these have been detailed in reference (c). The points raised in reference (c) should be considered in the next revision of the' River Bend ODCM.
Sincerely, Walter A. Paulson, Project Manager Project Directorate IV Division of Reactor Projects - III, y
IV, V and Special Projects Office of Nuclear Reactor Regulation f'
Enclosure:
a; -
As stated cc w/ enclosure:
g See next page-DISTRIBUTION
' Ed L E ocket411ed NRC PDR Local PDR PD4 Reading D
'58 G. Holahan ADR4 F. Hebdon P. Noonan mI W. Paulson 0GC-Rockville E. Jordan B. Grimes I
ACRS(10) 4 Plant File n-
.PD4/L
)
/
PD4/D FHebdonh PNoona aulson:sr 08p/89 08/h/89 08/ 3/89 f
, I 7
Y
[a g.
UNITED STATES
.m Y
- NUCLEAR REGULATORY. COMMISSION -
- 6 8,
WASHINGTON, D. C. 20655 koe**
August 28, 1989 A LDocket'No. 50-458 Gulf States Utilities
' ATTN:- Mr. James.C. Deddens SeniorVicePresident(RBNG)-
s
' Post Office Box-220 '
St. Francisville,. Louisiana 70775
=
Dear Mr.-Deddens:
SUBJECT:
ACCEPTANCE OF 0FFSITE DOSE CALCULATION MANUAL, REVISION 3-RIVER BEND STATION, UNIT NO. 1-
References:
.(a) February 29, 1988 letter from W. A. Paulson'to J. C. Deddens.
(b) April-24, 1989 letter from J. E. Booker to NRC Document' Control Desk.
(c) June 15, 1989 letter from D. W. Akers to W. Meinke.
Reference (a). documented NRC staff acceptance, with certain caveats, of Revision 1 of the Offsite Dose Calculation Manual (0DCM) for River Bend Station, Unit No. 1.
Gulf-States Utilities submitted Revision 3 to the ODCM with
~ reference (b) that addressed the concerns expressed in reference (a).
' Revision 3 of'the ODCM'for River Bend Station has been reviewed in its' entirety by our contractor, EG&G, Idaho, Inc. Their discussion and comments are contained in their. letter. evaluation DWA-33-89 accompanying reference (c) (enclosed).
.The.NRC staff concludes that the ODCM, Revision 3, meets the guidance in NUREG-0133 and the' requirements of the River-Bend Station Technical Specifications.
Therefore, the staff finds Revision'3 of the ODCM to be an acceptable reference.
Some questions remain, however, regarding Revision 3 and these have been detailed in reference ~(c). The points raised in reference (c) should be considered in the next revision of the River Bend ODCM.
Sincerely, kM, Walter A. Paulson, Project Manager Project Directorate IV Division of Reactor Projects - III, IV, Y and Special Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated cc wienclosure:
See next page o
- e ;.
Mr. James.C. Deddens
.' Gulf States Utilities Company River Bend Nuclear Plant CC:
- Troy 3. Conner, Jr., Esq.
Mr. J. E. Booker Conner and Wetterhahn Manager-River Bend Oversight
'1747 Pennsylvania Avenue, NW.
P. O. Box 2951
~ Washington, D.C. '20006 Beaumont, TX 77704 Mr. Les England Mr. William H. Spell, Administrator-Director.- Nuclear Licensing-Nuclear Energy Division.
. Gulf States Utilities Company Office of Environmental Affairs l
P. 0. Box 220 P. O. Box 14690-St. Francisville, LA 70775 Baton Rouge, Louisiana 70898-Richard M. Troy, Jr., Esq.
Assistant Attorney General in Charge Mr. J. David McNeill, III State of Louisiana Department'of Justice William G. Davis, Esq.
234 Loyola Avenue Department of Justice New Orleans, Louisiana 70112 Attorney General's Office j
P. O. Box 94095 Resident Inspector Baton Rouge, Louisiana 70804-9095 P. O.. Box 1051 l
St. Francisville, Louisiana 70775 H. Anne P1ettinger 3456 Villa Rose Drive President of West Feliciana Baton Rouge, Louisiana 70806 Police Jury P. 0. Box 1921 St. Francisv111e,' Louisiana 70775 Philip G. Harris Cajun Electric Power Coop. Inc.
Regional. Administrator, Region IV 10719 Airline Highway.
U.S. Nuclear Regulatory Commission P. O. Box 15540 Office of Executive Director Baton Rouge, LA 70895 for-Operations 611 Ryan Plaza Drive, Suite 1000 1
Arl hgton, Texas 76011 l
d g