ML20246L247

From kanterella
Jump to navigation Jump to search
Advises That Mod Re Reactor Coolant Standpipe Installation Will Not Be Completed During 1989 Refueling Outage as Committed to in 880429 Response to Insp Rept 50-338/88-01 & 890106 & 0203 Responses to Generic Ltr 88-17
ML20246L247
Person / Time
Site: North Anna Dominion icon.png
Issue date: 07/14/1989
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
89-497, GL-88-17, NUDOCS 8907180376
Download: ML20246L247 (2)


Text

--

L l

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261

. W, L. STEWA RT SENIOR VICE PRESIDENT power July 14, 1989 U. S. Nuclear Regulatory Commission SerialNo 89-497 Attn: Document Control Desk NAPS /PAK:bgp Washington, D, C. 20555 Docket No. 50-338 License No. NPF-4 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNIT 1 REACTOR COOLANT STANDPIPE INSTALLATION Generic Letter 88-17, Loss of Decav Heat Removal. required programmed enhancements consisting of hardware installations and/or modification implementation by the end of the first refueling outage that is -

initiated 18 months or later following receipt of the letter, or by the end of the second refueling outage following receipt of the letter, whichever occurred first. The Virginia Electric and Power Company response to NRC Inspection Report 88-01 dated April 29,1988, and responses to Generic Letter 88-17 dated January 6,1989 and February 3,1989 committed to the installation of a permanent reactor vessel standpipe arrangement during the 1989 refueling outage.

Design Change Package (DCP) 88-11 was developed and implemented to direct the installation activities for the new standpipe as previously committed. However, the modification will not be completed during the 1989 refueling outage. Mechanical and electrical work for DCP 88-11 was completed during the 1989 refueling outage except for 1) installation of the spool pieces to connect the standpipe to the Reactor Coolant System,2) installation of a metal gasket at the transmitter rernote seal,3) hydrostatic testing and

4) calibration of the transmitter and remote indicator.

To ensure the safety ot other containment systems remains unaffected during a seismic event, the standpipe was left in the following condition:

1.

All portions of the standpipe modification are seismically secure and verified by a stress calculation based on the as-built configuration.

2.

Flushing of the new piping is complete.

8907180376 890714

~

g d((

A PDR ADDCK 05000338 p

PNU

'] 0

. ' :.4

.r.

3.

All wiring is complete. This includes wiring from the Rosemount transmitter to the 7300 racks and wiring from the racks to the control room indicator and annunciator. All portions of the modification will be left de-energized.

l' 4.

The new syrstem is tied in to existing piping only at the interface with the instrumentation biowdown header.

~

L 5.

The RCS boundary will be restored with blind flanges per the existing unmodified' design.

' Appropriate measures have been taken to ensure the new levelindication system will be operable prior to the next entry into a reduced inventory condition (i.e., vessel level lower than three feet below the reactor vessel flange) and therefore, will not impact overall plant safety.

If you have further questions or require additionalinformation, please contact us.

Very truly yours, N

W. L. STEWART cc:

U. S. Nuclear Regulatory Commission 101 Marietta Street, N.W.

Suite 2900 Atlanta, GA 30323 Mr. J. L. Caldwell NRC Senior Resident inspector North Anna Power Station

,