Notice of Violation from Insp on 870803-07.Violation Noted:On Five Occasions During Month of June 1987, Individuals Worked Overtime in Excess of Tech Spec Limit of 72 H in 7-day Period W/O Required Approval
ML20238F565
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 09/10/1987
From: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20238F548 List:
References
50-369-87-26, 50-370-87-26, NUDOCS 8709160225
Download: ML20238F565 (2)


Text

_ _ _ _- _ _

p, -

l ENCLOSURE 1 NOTICE OF VIOLATION DbkePowerCompany' Docket Nos. 50-369 and 50-370

.McGuire. Units 1 and'2 License Nos. NPF-9 and NPF-7 During' the ' Nuclear Regulatory Commission (NRC) inspection conducted 'on August 3-7, 1987,- a violation of NRC requirements was identified. The violation : involved a . failure to comply c ith Technical Specifications and procedures 1 governing the use of overtime.for persons performing safety-related

. functions. In accordance with the " General Statement of Policy and Procedure

! for NRC Enforcement Actions " 10 CFR Part 2, Appendix C (1987), the violation is listed below:

Technical Specification 6.2.2.f requires that adequate shift coverage shall be maintained without routine heavy use'of overtime and states

' that under certain' circumstances when substantial amounts of overtime are required, an individual should not be permitted to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> in any 24-hour period nor more than-72 hours in any 7-day period, excluding shift turnover time. Technical Specification 6.2.2.f requires that any deviation from the above guideline shall be authorized by the Station Manager or his deputy, or higher levels of management,

in accordance with established procedures and with documentation of the basis for granting the deviation. Station' Directive 2.0.10, Overtime Authorization for Personnel Performing Safety Related~ Functions, Revision 2, which implements ' Technical Specification 6.2.2.f, requires that excessive

' overtime be authorized in advance and documented on a Request for Work Hour Extension form.

Contrary to the above, on five occasions during the month of June 1987, individuals worked overtime in excess of the Technical Specification limit of 72. hours in a 7-day period without the required management approval, and on numerous occasions during the months of September and October 1986, March 1987, and May through July 1987, Request for Work Hour Extension forms were approved after the. excessive overtime had been worked.

Station Directive 2.0.10 allows the Shift Engineer on duty to approve work hour extensions, although Technical Specification 6.2.P.f requires this function to be performed by the Station Manager, his deputy, or higher levels of management.

s This is a Severity Level IV violation (Supplement I).

Pursuant to the provisions of 10 CFR 2.201, Duke Power Company is hereby required to submit to this Office within 30 days of tre date of the letter transmitting this Notice a written statement or explanation in reply including:

8709160225 870910 gDR ADOCK 05000369 PDR ,

1 Duke Power Company 2 Docket Nos. 50-369 and 50-370 McGuire Units 1 and 2 License Nos. NPF-9 and NPF-7 i

i

_(1) admission' or denial'of the violation, (2) the reason for the violation if l admitted, (3) the corrective steps which have been taken and the results  !

achieved. (4) the corrective steps which will be taken to . avoid further {

violations, and (5) the date when full compliance will be achieved. Where good j cause is shown, consideration will be given to extending the response time.

FOR THE NUCLEAR REGULATORY COMMISSION ,

J. Ne son Grace

-[ '

- Regional Administrator Dated at Atlanta, Georgia, I this 10th day of September 1987 I