ML20237G978

From kanterella
Jump to navigation Jump to search
Ack Receipt of Assuring NRC of Completion of short-term Commitments,Per Telcon Re Insp Repts 50-285/87-05 & 50-285/87-08
ML20237G978
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 08/11/1987
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Andrews R
OMAHA PUBLIC POWER DISTRICT
References
NUDOCS 8708170007
Download: ML20237G978 (1)


See also: IR 05000285/1987005

Text

- _ _

,

!

,:

,

,

. .

AUG 11'1387

!

,-

!

In Reply Refer To:

.

Docket: 50-285/87-05..

1

50-285/87-08)

!.

i

'

!,

-l

.

..

-]

Omaha Public Power District

.

4

ATTf4:

R. L..Andrews, Division Manager-

'

Nuclear Production

1623 Harney' Street-

,

'

Omaha, Nebraska

.68102:

Gentlemen:

,1

Thank.you for your letter of July.6,1987, in response to.our telephone

request for. assurance of completion of.short-term commitments. ,

d

i

Sincerely,

jj

. Orig!nct S1;;ned By :

p

. J. E. Gagilardo

l

J. E. Gagliardo.. Chief .

1

!

Reactor Projects' Branch

q

l

cc:

W. G. Gates, Manager

Fort Calhoun Station

,

.l

!

P. 0. Box 399

.

l

Fort Calhoun, Nebraska

68023

i

Harry H. Voigt, Esq.

LeBoeuf, Lamb, Leiby & MacRae

a

'

1333 New Hampshire Avenue, NW

]q

Washingtor,, D. C.

20036

l

Kansas Radiation Control Program Director

Nebraska Radiation Control Program Director

j

bectoDMB(IE01)

0

,

bec distrib. by RIV:

,

RPB

RRI

.R.D. Martin, RA-

'

RPSB

SectionChief(RPB/B)

MIS System

,

RIV File

DRSP

RSTS Operator

.]

RSB

Project Inspector, RPB

D. Weiss, RM/ALF

i

R. Hall

T. Bournia, NRR Project Manager

,

. . - - g

RIV: SRI

PI

CMB

C:RPB /

'

h 'PHHarrell/dfhRPMullikin

DRYunter

JEGagl it do

,

'

/ pj/87

q/q/87

4/cf/87

3 / 3/

()

]

/

3

B708170007 870811

'[

l

PDR

ADOCK 05000295

)

I

,

G

PDR

'

},

-

.

.,m

,

,.

-

. .

_

___.m.-.

..

_ r _ ___ _ .

,

,

.

,

.

.

_ _ - - _ - -

+

.~ -

~

.

.

Omaha Public Power District

i

1623 Harney Omaha. Nebraska 68102 2247

,

l

402/536 4000

9 ]@ [7- 'gg 'p'

,

@[

fi

'

July 6, 1987

, -

LIC-87-431

l#

1

.AA.-9S67

'I

L,

4

-

Mr. J. E. Gagliardo, Chief

~

Reactor Projects Branch

U. S. Nuclear Regulatory Commission

Region IV

611 Ryan Plaza Drive. Suite 1000

l

Arlington, TX 76011

Dear Mr. Gagliardo:

SUBJECT:

Inspection Reports 87-05/87-08, Completion of Short Term

Commitments

Reference:

(1) Docket No. 50-285

(2) Let'ar from 0 PPD (R. L. Andrews) to NRC (J. E. Gagliardo)

dated May 22, 1987 (LIC-87-347)

'

Pursuant to a telephone request from Mr. Hunter of your staff, this letter

serves to provide assurance that short term commitments made in Reference (2)

were completed.

Because of some ambiguity in the Reference (2) items,

clarification is provided where appropriate. The items and final disposition

are as follows:

1.

Modification MR-FC-81-180 was presented to the System Acceptance

Committee (SAC) on May 26, 1987, and was accepted.

OPPD is aware that

during the week of May 25-29, 1987, Mr. Les Gilbert again reviewed this

modification.

His findings, which are to be documented in Inspection

Report 87-13, were factored into a subsequent engineering review,

including third party approval.

2.

Repairs to the Emergency Feedwater Storage Tank were completed, results

of radiography performed were acceptable, sandblasting was conducted,

the painting was completed, and a hydrotest was conducted with

satisfactory results.

3.

Welding performed on Critical Quality Element equipment during the 1987

refueling outage was conducted using qualified welders using qualified

weld procedures. Additionally, the welder / weld qualification records

were researched back to 1973.

From our review it was determined that

there was one welder on one weld whose continuity of qualification could

,

not be established.

The weld is on a pipehanger on the CVCS.

The

records of inspection for this weld were reviewed and the weld was

determined to be adequate.

(The weld .fas established to have been made

eq/

in 1981.) +70 7 aa ootcr-

o/

ze

-

~=w--

_

-_

. - - - - - - - - - - - - - -

i

r

..

,

4

.

c ,

Mr. J. E. Gagliardo

Page Two

l

LIC-87-431

'

,

4.

The ten (10) Main Steam Safety Valves have been acceptably installed.

The concern in this area was overstressing of the studs juring

reinstallation because of the use of a slugging wrench f astead of torque

!

values. A new procedure was written to achieve preload rtress values

~

below code allowable via measurement of stud elongation.

The studs on

the 10 main steam. safeties were replaced. Additionally, the effort

i

required to tighten the new studs to the appropriate preload via

elongation measurements indicates that overtightening in the past is

extremely unlikely.

,

5.

Pressurizer Safety Valve Flange Stud torque values. The torque values

i

used were verified to provide below code allowable stress values.

'

6.

Lubricant in Limitorque operators that are included in the Fort Calhoun

l

Station Electrical Equipment Qualification program was changed or

'

verified to be Exxon Nebula EP-0.

!

7.

The containment vent fan motor and cables were meggered with

satisfactory results. The containment vent fan blade torque and blade

angle settings were verified. The correct values had been specified in

the procedure and were field verified.

,

I

8.

There were 181 Maintenance Ordens (M0's) specified in Reference (2).

Of

.

these, 41 did have torque values specified.

This information was

'

relayed to the Resident Inspector and to Region IV management. Of the

1

remaining 140 M0's, engineering evaluations were prepared and are being

'

maintained internally.

If you or your staff have additional questions concerning this matter, please

do not hesitate to contact us.

1

Sincerely,

4M

,

R. L. Andrews

Division Manager

Nuclear Production

RLA:rge

c:

LeBoeuf, Lamb, Leiby & MacRae

1333 New Hampshire Ave., N.W.

Washington, DC 20036

A. Bournia, NRC Project Manager

D. R. Hunter, NRC Region IV

P. H. Harrell, NRC Senior Resident Inspector

i

!

Y