Forwards Safety Evaluation Re Request for Relief for First 10-year Interval Inservice Insp Nondestructive Exam Program
ML20237E111
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 08/25/1998
From: Carpenter C
NRC (Affiliation Not Assigned)
To: Gipson D
DETROIT EDISON CO.
Shared Package
ML20237E113 List:
References
TAC-MA1570, NUDOCS 9808280256
Download: ML20237E111 (4)


Text

t ,

Mr. Douglis R. Gipson August 25, 1998 Srnior Vice Prcsid:nt Nuclear Generation Detroit Edison Company 8400 North Dixie Highway i

Newport, MI 48166

SUBJECT:

FERMI 2 - RELIEF REQUESTS FOR THE FIRST 10-YEAR INTERVAL' INSERVICE INSPECTION (ISI) NONDESTRUCTIVE EXAMINATION (NDE) 1 PROGRAM (TAC NO. MA1570)

Dear Mr. Gipson:

' By letter dated April 16,1998, as supplemented by letters dated June 19 and July 27,1998, the Detroit Edison Company (DECO) requested relief from certain ISI requirements of the American

' Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, for the Fermi 2 plant. The ten requests for relief are related to inspections under the ISI NDE program for the first 10-year interval. By letter dated May 28,1998, the NRC staff requested additional information concerning the requests for relief. DECO responded to this request in the June 19, 1998, letter. After further discussions with the NRC staff, DECO submitted the July 27,1998, 3 letter, providing further information and withdrawing request for relief RR-A1. I l'he_ staff, with technical assistance from its contractor, the Idaho National Engineering and Environmental Laboratory, has completed its review for five of the requests for relief (RR-A17, l

A19, A20, A21, and A22). For RR-A17, A21, and A22, the staff determined that the proposed alternatives will provide an acceptable level of quality and safety; therefore, these alternatives ,

are authorized pursuant to 10 CFR 50.55a(a)(3)(i) for the first 10-year ISI interval. For RR-A19 and A20, the staff determined that imposing the requirements at issue would result in hardship J without a compensating increase in the level of quality and safety at Fermi 2; therefore, the I alternative examinations are authorized pursuant to 10 CFR 50.55a(a)(3)(ii) for the first 10-year ISI interval. The alterative contained in request for relief RR-A20 (the use of Code Case N-498-1) is authorized for the current interval or until such time as the Code Case is published in l a future revision of Regulatory Guide (RG) 1.147. At that time, if DECO intends to continue to implement this Code Case, you should follow all provisions in Code Case N-498-1 with the i limitations issued in RG 1.147, if any. A copy of the staff's safety evaluation and the associated contractor's technicalletter report are enclosed. The remaining requests for relief will be addressed in future correspondence.

Sincerely, l

Original signed by:

l Cynthia A. Carpenter, Project Director l Project Directorate lll-1 L

Division of Reactor Projects - Ill/IV Office of Nuclear Reactor Regulation

? i,) &m '

l Docket No. 50-341 e -? .y

Enclosures:

As stated - gn%pyyw W 6LL &asR-_ Yi cc w/ encl: See next page QlSTRIBUTIOR Docket File PUBLIC PD31 Reading E. Adensam (EGA1)

SEDB (TLH3) OGC. Gc Hill (2) T. McLellan M. Banerjee B. Burgess, Rill ACRS .

DOCUMENT NAME: G \WPDOCS\ FERMI e box: "C" \FE-A1570.RL

= Copy without attachmeJ' no g To receive a cop ' of th6s document. Indicati in tt "E" = Cooy wi'h attachment / enclosure "N" = No copy OFFICE PM:PD31 ,o E LA:PD31 (E C;%e@lf l OGQM $ lE D:PD31 l E.-

NAME AKugler:db W CJamerson G7 JsBadchi 4 2/ m y, CACarpenterb >

DATE 08/ (, /98 " 08/ la /98 // ~ 08/ (, /98 08/ [f /98' 08/og /98 OFFICIKL RECORD COPY 4(

9909290256 990825 PDR ADOCK 05000341 P PDR

> , l Mr. Dougiss R. Gipson August 25, 1998 I 3

Ssnior Vic] Pr;;sidant l Nucisar G2ntration

- Detroit Edison Company 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

FERMI 2 - RELIEF REQUESTS FOR THE FIRST 10-YEAR INTERVAL l INSERVICE INSPECTION (ISI) NONDESTRUCTIVE EXAMINATION (NDE)

PROGRAM (TAC NO. MA1570)

Dear Mr. Gipson:

By letter dated April 16,1998, as supplemented by letters dated June 19 and July 27,1998, the Detroit Edison Company (DECO) requested relief from certain ISI requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, for the Fermi 2 plant. The ten requests for relief are related to inspections under the ISI NDE program for the first 10-year interval. By letter dated May 28,1998, the NRC staff requested additional information concerning the requests for relief. DECO responded to this request in the June 19, 1998, letter. After further discussions with the NRC staff, DECO submitted the July 27,1998, letter, providing further information and withdrawing request for relief RR-A1.

The staff, with technical assistance from its contractor, the Idaho National Engineering and Environmental Laboratory, has completed its review for five of the requests for relief (RR-A17, A19, A20, A21, and A22). For RR-A17, A21, and A22, the staff determined that the proposed i alternatives will provide an acceptable level of quality and safety; therefore, these attematives I are authorized pursuant to 10 CFR 50.55a(a)(3)(i) for the first 10-year ISI interval. For RR-A19 l and A20, the staff determined that imposing the requirements at issue would result in hardship I without a compensating increase in the level of quality and safety at Fermi 2; therefore, the attemative examinations are authorized pursuant to 10 CFR 50.55a(a)(3)(ii) for the first 10-year ISI interval. The alterative contained in request for relief RR-A20 (the use of Code Case N-498-1) is authorized for the current interval or until such time as the Code Case is published in a future revision of Regulatory Guide (RG) 1.147. At that time, if DECO intends to continue to ,

implement this Code Case, you should follow all provisions in Code Case N-498-1 with the  !

limitations issued in RG 1.147, if any. A copy of the staff's safety evaluation and the associated I contractor's technical letter report are enclosed. The remaining requests for relief will be addressed in future correspondence. i

)

Sincerely, I

Original signed by:

Cynthia A. Carpenter, Project Director Project Directorate ill-1 Division of Reactor Projects - Ill/IV Office of Nuclear Reactor Regulation l

Docket No. 50-341 1

[

Enclosures:

As stated l cc w/ encl: See next page DISTRIBUTION: Docket Fi!e PUBLIC PD31 Reading E. Adensam (EGA1)

SEDB (TLH3) OGC G. Hill (2) T. McLellan M. Banerjee i B. Burgess, Rlli ACRS DOCUMENT to rec.ev. . eorNAME: G:\WPDOCS\

of thi. oocum.nt indic.t.FERMI \FE-A1570.RL in in. box: c cooy tneue . taenm.Jne g.e, s con we ennenment encioive v No copy j i OFFICE PM:PD31 , , , E LA:PD31 (E. C% sis OGQJ W 84 E D:PD31 lL NAME AKugler:db W CJamerson C/ ~

fsBadchi M 2/ m y, CACarpenterth >

DATE 08/ (, /98 " 08/ 4. /98 /) 08/ (s /98 08/ /f /98' 08/QQ /98 OFFICIAL RECORD COPY 4 t Ug

)- , )

'g UNITED STATES

[ S NUCLEAR REGULATORY COMMISSION

!'* E.8  !

WASHINGTON, D.C. 30seH001 4

4 ,,, p August 25, 1998 Mr. Douglas R. Gipson

' Senior Vice President Nuclear Generation Detroit Edison Company 6400 North Dixie Highway l Newport, MI 48166

SUBJECT:

FERMI 2 - RELIEF REQUESTS FOR THE FIRST 10-YEAR INTERVAL

INSERVICE INSPECTION (ISI) NONDESTRUCTIVE EXAMINATION (NDE)

PROGRAM (TAC NO. MA1570)

Dear Mr. Gipson:

By letter dated April 16,1998, as supplemented by letters dated June 19 and July 27,1998, the

, Detroit Edison Company (DECO) requested relief from certain ISI requirements of the American Society.of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, for the Fermi 2 plant. The ten requests for relief are related to inspections under the ISI NDE program for the first 10-year interval. By letter dated May 28,1998, the NRC staff requested additional information conceming the requests for relief. DECO responded to this request in the June 19, 1998, letter. After further discussions with the NRC staff, DECO submitted the July 27,1998, letter, providing further information and withdrawing request for relief RR-A1.

The staff, with technical assistance from its contractor, the Idaho National Engineering and Environmental Laboratory, has completed its review for five of the requests for relief (RR-A17, A19, A20, A21, and A22). For RR-A17, A21, and A22, the staff determined that the proposed alternatives will provide an acceptable level of quality and safety; therefore, these alternatives ]

are authorized pursuant to 10 CFR 50.55a(a)(3)(i) for the first 10-year ISI interval. For RR-A19 and A20, the staff determined that imposing the requirements at issue would result in hardship without a compensating increase in the level of quality and safety at Fermi 2; therefore, the attemative examinations are authorized pursuant to 10 CFR 50.55a(a)(3)(ii) for the first 10-year l ISI interval. The alterative contained in request for relief RR-A20 (the use of Code Case

- N-498-1) is authorized for the current interval or until such time as the Code Case is published in a future revision of Regulatory Guide (RG) 1.147. At that time, if DECO intends to continue to implement this Code Case, you should follow all provisions in Code Case N-498-1 with the ,

limitations issued in RG 1.147, if any. A copy of the staff's safety evaluation and the associated contractor's technical letter report are enclosed. The remaining requests for relief will be addressed in future correspondence.

]

1 Sincerely, )

OA

l. C thia A. Carpenter, project Director Project Directorate lil-1 Division of Reactor Projects - lil/IV Office of Nuclear Reactor Regulation Docket No. 50-341

Enclosures:

As stated cc w/ encl: See next page l

Mr. Douglas R. Gipson Fermi 2 Detroit Edison Company cc:

John Flynn, Esquire Senior Attorney Detroit Edison Company 2000 Second Avenue Detroit, Michigan 48226 Drinking Water ar,d Radiological Protection Division Michigan Department of Environmental Quality 3423 N. Martin Luther King Jr Blvd P. O. Box 30630 CPH Mailroom Lansing, Michigan 48909-8130 U.S. Nuclear Regulatory Commission Resident inspector's Office 6450 W. Dixie Highway Newport, Michigan 48166 Monroe County Emergency Management Division 963 South Raisinville Monroe, Michigan 48161 Regional Administrator, Region Ill U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, Illinois 60532-4351 Norman K. Peterson Director, Nuc! ear Licensing Detroit Edison Company Fermi 2 - 280 TAC -

6400 North Dixie Highway Newport, Michigan 48166 I

(

August 1997