ML20236V491
| ML20236V491 | |
| Person / Time | |
|---|---|
| Site: | Wolf Creek |
| Issue date: | 12/01/1987 |
| From: | Callan L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Withers B WOLF CREEK NUCLEAR OPERATING CORP. |
| References | |
| NUDOCS 8712040336 | |
| Download: ML20236V491 (2) | |
See also: IR 05000482/1987020
Text
-
%.
. . .
.
In Reply' Refer To:
Docket:
STN 50-482/87-20
. IIE
Wolf Creek Nuclear Operating Corporation
ATTN:
Bart D. Withers
President and Chief Executive Officer
P.O. Box 411
Burlington, Kansas
66839'
Gentlemen:
' Thank you for your letter of October 28, 1987, in response to our letter
and Notice of Violation dated September 30, 1987.
We have reviewed your reply
i
l
l
and find it responsive to the concerns raised'in our Notice of Violation.
We
will review the implementation of your corrective actions during a future
inspection to determine that full compliance has been achieved and will be
l
maintained.
Sincerely,
Original Signed By
L. J. Callan
l
L. J. Callan, Director
Division of Reactor Projects
cc:
Wolf Creek Nuclear Operating Corporation
ATTN: Otto Maynard, Manager
of Licensing
P.O. Box 411
Burlington, Kansas
66839
Wolf Creek Nuclear Operating Corporation
ATTN: Gary Boyer, Plant Manager
P.O. Box 411
Burlington, Kansas
66839
Kansas Corporation Commission
ATTN:
Mr. Robert D. Elliott, Chief Engineer
Fourth Floor, Docking State Office Building
Topeka, Kansas
66612-1571
Ka 'a Radiation Controlf f gram Director
. RP/PSA
P$
f/Ji:Tapia;df
JP au' don
LJCallan
-
\\l/bb/87
l( /9]]87
I?/ q/87
/ C6 /
9712040336 871201
)
ADOCK 05000482
G
- _ _ - -
]
2
,
!
Wolf Creek Nuclear Operating
-2-
Corporation
bec to DMB'(IE01)
bec'distrib. by RIV:
Myron Karman, ELD, MNBB (1)
- RRI
R. D. Martin, RA
- Section Chief (DRP/A)
- DRP.
RPSB-DRSS
W. L. Forney, RIII
- RIV File
Resident Inspector, RIII
- MIS System
- RSTS Operator
- Project Engineer, DRP/A
- R. Hall
- Lisa Shea, RM/ALF
- P. O'Connor, NRR Project Manager
- DRS
- TSS
- w/766
i
1
i
1
_ _ _ _ _ - _ -
,
.
.
~.-
.
.
W4) NUCLEAR OPERATING
,
.
.
Bart D. Withers
b i'i -/
e,L ' (
Present end
4
i
O ,i
October 28,i1987 7-
p
Chief ExecuWe Omcor -
,
e,t 1
/
U. S. Nuclear Regulatory Commission
!
ATTN:
Document Control Desk
j
Washington, D. C. 20555
'
Reference:
Letter dated 9/30/87, from J. E. Gagliardo, NRC, to
B. D. Withers, WCNOC
Subj ect:
Docket No. 50-482:
Response to Violation 482/8720-01
l
Gentlemen:
'
Attached is a detailed response to violation 482/8720-01 which
was
documented" in the Reference.
Violation 482/8720-01 concerns a failure to
enter Technical Specification 3.0.3 when both trains of the control room
)
emergency ventilation system were inoperable when a door was blocked open.
4
If you have any questions concerning this matter, please contact ne or Mr.
O. L. Maynard of my staff.
Very truly yours,
4
Bart D. Withers
President and
Chief Executive Officer
BDW/jad
Attachment
ec:
P. W. O'Connor (2)
R. D. Martin
J. E. Cuttnins
.
C. A. Hackney
-gM-6
$
A4
e
.
RO. Box 411/ Burlington, KS 66839 / Phone: (316) 364-8831
An Equal Opportunny Ernployer uf/HC/ VET
- _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - - - - _ _ - _ - - - -
--
-
- - -- A
_
_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
'.
-
'
~
.
.
Attachment to WM 87-0289
Page 1 of 2
October 2& 1987
Violation (482/8720-01): Failure To Enter Technical Specification
(TS)_3.0.3
Finding:
Technical Specification 3.0.3 requires, in part,
"When a limiting condition
for operation is not met,
except as provided in the associated action
requirements, within 1-hour action shall be initiated to place the unit in a
mode in which the specification does not apply..."
TS 3.7.6 requires,
"Two independent control room emergency ventilation
systems shall be operable."
Contrary to the above, on August 20,
1987, the NRC inspector observed both
trains of the control room emergency ventilation system inoperable when Door
36171 was blocked open preventing the control room from being pressurized to
greater than or equal .25 inches of water.
Reason For Violation:
,
On August 20,
1987,
at approximately 1330 CDT, the NRC Resident Inspector
found Door 36171, which separates the Control Room from an electrical chase
area, propped open for rework of penetrations by Facilities and Modification
(F&M) personnel.
The Shift Supervisor was aware of the rework activity, but
was unaware that it required the door to be propped open.
With this door
open, it was concluded that positive pressure could not be maintained in the
l
Control
Room which is contrary to Technical Specifications (TS) and should
i
have resulted in TS 3.0.3 entry.
'
This violation has been attributed to a failure to effectively communicate
between the Shift Supervisor involved and the F&M personnel performing the
work activity.
This Technical Specification violation was reported to the
NRC in LER 87-034-00.
Corrective Ste_ps Which Have Been Taken and Results Achieved:
The Shift Supervisor promptly took cotapensatory measures upon notification
that the door was propped open to restore the operability of both Control
l
Room Emergency Ventilation Systems.
Corrective Steps Which Will_ Be Taken To Avoid Further Violations:
In order to prevent the recurrence of this event,
the following corrective
actions have been implemented:
(1)-
Permanent signs have been posted on Door 36171 and two other similar
doors informing personnel that the doors are part of the Control Room
pressure boundary and the Control Room must be contacted prior to
initiating any work that would require propping the doors open.
,
i
l
,s
X L%
+,
o
_ - _ _ _ _ _ . .
.
,
--
,
,
. / ., ^.
'
'
Attachment'to.WM 87-0289
]
.Page 2 of 2
October 28, 1987
]
(2)
F&M Engineers have been instructed to' include precautionary statements'
into their work packages to emphasize pressure boundary. considerations;
prior to starting work.
(3)
F&M personnel, including Contractors, have been instructed to contact
Control Room personnel when work could affect a pressure boundary.;.
(4)
A change has been made to .the Control Room- Ventilation Isolation
Signal alarm response procedure to close the doors if open.
~
(5)
LER 87-034-00 has been added to Operations' Required Reading.to remind.
licensed personnel of- the importance of considering potential effects
on pressure boundaries when authorizing work activities.
Date When Full Compliance Will Be Achieved: .
Full compliance has been achieved.
1
l
i
,
j
4
1
,
!
1
!
..
O
P
4.
.I
- h_