Approves Listed Recommendations Re Comanche Peak Repts,Per Recipient 870414 Memo
ML20236J331
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/12/1987
From: Zech L
NRC COMMISSION (OCM)
To: Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
Shared Package
ML20236J334 List:
References
FOIA-87-596 COMLZ-87-25, NUDOCS 8711060003
Download: ML20236J331 (2)


Text

/7 A>

Action: OSP/NRR/ ARM /RIV/

l

[xu\\c%

UNITED STATES ED0/0GC NUCLEAR PcGULATORY COMMISSION s

5 4

,s

>+(

Cys:

Stello

% g,y Peu "

wAssiscion.o.c.rosss -

~

LIMITED DISTRIBUTION Connelly CHAIRMAN COMLZ-87-25 May 12, 1987

[

MEMORANDUM FOR:

Victor Stello, Jr., Executive Director for Operations FROM:

Lando W.

Zech, Jr.

dM C b.

l

SUBJECT:

RECOMMENDATIONS PURSUANT TO THE COMANCHE PEAK REPORTS Your memorandum of April 14, 1987 contained your recommenda-tions pursuant to the OIA and Comanche Peak Review Group reports.

The Commission has approved the following:

c Please extract from the Comanche Peak Report Review Group's (CPRRG) report and its appendices

'^0ffices noted take all explicit recommendations and categorize each r quired act in one of three different categories.

Assign all P 9 3

Category I recommendations to the Office of further action to Special Projects (OSP) for action.

Category II ED0 by 6-5-87.

and III recommendations should be assigned to the Complete action &

Office of Nuclear Reactor Pegulation (NRR) with advise EDO by the assistance of the Office of Administration and 7-1-87.

Resources Management (ARM).

(OSP/NRR/ ARM)

D'

  • 2.

OSP, NRR and ARM should further review the report to determine whether there are any additional actions to be taken based on other statements, implicit recommendations, or " lessons learned" contained therein. (OSP/NRR/ ARM)

    • 3.

NRR should examine, in more detail, the inspection o: Plan / schedule records for a facility within Region IV which did to EDO by not receive as much attention from either NRC or 6-5-87.

utility conducted efforts.

If the results of such review require, further staff reviews of other plants should be performed.

(HRR) - Verbal guidance issued by J. Taylor.

4.a. Your letters to the principal individuals involved should be modified as discussed at the management meeting, and submitted for Commission review and approval.

(E00 - complete 5-14-87)

Re:'d Off. EDO Date d ' / 3 ' F ~2

/

f,

((

II~re

  • 'O h

~gp l

/'

< {l, s]'. ) ' j ' -

/

/

/

LDO -- UO2 k11

)

y

..... ~.

d O

. b. You should meet with each of the principals to inform them of decisions for resolving the remain-ing-issues and to discuss with them their respective roles as representatives of the Agency.

These discussions should be consistent with the Commission approved letters referenced in item

~~5..'sM /

4.a.

(EDO) 7pg f./. r7 4'

c.JThe Chairman will meet with Region IV and site personnel to stress the importance to be attached to professionalism, teamwork, and the need to be j

sensitive to the views of others which may not coincide with one's own, within the framework of the inspection process as well as within the agency as a whole.

(Chairman)

d. The principal individuals involved, both inspector and management, should be given specific training to improve their interpersonal and communication skills as appropriate to the individual.

(RIV)

e. The Region-wide training program and guidance initiated by the Regional Administrator, as described in his December 17, 1986 memorandum to the EDO, may be continued for all Region IV inspection personnel.

(RIV) r..

(5.)

The CPRRG report and its appendices and your April 14, 1987 memorandum, except for Enclosure 3-6, should be released to the public, consistent with any limitations determined appropriate by the Commission regarding the release of the OIA report, following the meetings cited in 4.b. and c., above.

(EDO)

(OGC provide liaison with OIA on DOJ & keep EDO advised.)

6.

You should provide suggestions to improve the early identification of, and methods for dealing with, future similar management-type issues.

(EDO) 7.

Your communications on this matter should not convey the impression that these actions necessarily constitute final Commission disposition of the issues.

(ED0/RIV)

{

Copies:

d commissioner Asselstine Commissioner Bernthal Commissioner Carr vuv SECY