ML20236B710
| ML20236B710 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 03/16/1989 |
| From: | Kelly L Office of Nuclear Reactor Regulation |
| To: | Sylvia B DETROIT EDISON CO. |
| References | |
| GL-88-01, GL-88-1, TAC-69135, NUDOCS 8903210241 | |
| Download: ML20236B710 (11) | |
Text
m' p-2 March 16, 1989
- e.,
n.g h
' Docket No. 50-341 Mr. B. Ralph Sylvia Group Vice President i
Nuclear Operations Detroit Edison Company.
6400. North Dixie Highway
- . Newport, Michigan ' 48166-
Dear Mr. Sylvia:
SUBJECT:
FERMI NUCLEAR POWER PLANT,' UNIT 2, GENERIC LETTER 88-01 RESPONSE:-
REQUEST FOR ADDITIONAL INFORMATION (RAI) (TAC NO. 69135)
Your submittal dated August 5, 1988, provided information concerning the Fermi-2 response to Generic Letter 88-01. The information provided in this-submittal, however,-is not sufficient to complete our review and determine compliance with the guidance of the Generic Letter.
In order to complete our review, please respond to the enclosed request for.
i additional information on Generic Letter 88-01 by May 12, 1989.
In addition,-
i in order to expedite the review process, please send a copy of your RAI response.to the NRC contractor, Viking Systems International, at the following address:
Dr. Armand A. Lakner Director, Safety and Reliability Viking Systems International 101 Chestnut Street Gaithersburg, Maryland 20817 Thank you for your assistance.
Sincerely, Ly Kelly, Pro et Manager Project Directorate III-1 Division of Reactor Projects - III, IV, V
& Special Projects
Enclosure:
As stated DISTRIBUTION I
DUCKET;- EILEr MVIRGILIO EJORDAN NRC & LOCAL PDRs PSHUTTLEWORTH BGRIMES PD31 GRAY FILE LKELLY ACRS(10)
GH0LAHAN OGC LA/PD31:DRSPTA PM/PD31:DRSP (A)D/PD31:DRSP J
PSHUTTLEWORTH <
LKELLY:cr.
TQUAY W L[0]'
3/16/89$g 3/16/89 3/16/89 8 I 8903210241 890316 POR ADOCK 05000341 h's P
y;;
O
'8 i
NUCLEAR REGULATORY COMMISSION
(
G E
WASHINGTON, D. C. 20555
. March 16, 1989.
Docket No. 50-341:
Mr. B. Ralph-Sylvia'
. Group:Vice President l
' Nuclear' Operations 4
Detroit Edison Company
- 6400 North Dixie Highway-Newport, Michigan.48166
Dear Mr. Sylvia:
SUBJECT:
FERMI NUCLEAR POWER PLANT, UNIT 2, GENERIC LETTER 88-01 RESPONSE -
'REQUESTFORADDITIONAL'INFORMATION(RAI)(TACN0.69135)
Your submittal dated August 5,1988, provided information concerning the.
Fermi-2 response.to Generic Letter 88-01. The information provided in this i
submittal, however, is not sufficient to complete our review and determine l
' compliance with the guidance of the Generic Letter.
.i In order to complete our review, please respond to the enclosed request for 1
additional information on Generic Letter 88-01 by May 12,1989.
In addition, i
'in order to expedite the review process, please~ send a copy of your RAI l
response to'the NRC contractor, Viking Systems International, at the. following l
~ address:
l Dr. Armand A. Lakner Director, Safety and Reliability l
Viking' Systems International I
101 Chestnut Street Gaithersburg,fiaryland 20817 l
Thank you for your assistance.
Sincerely,
/
n Ly n Kelly, Pro ect Manager Project Directorate III-1 Division of Reactor Projects - III, IV, V 8 Special Projects i
i
Enclosure:
As stated l
g i
m
...z, q
.a
-sa 1,
1
. Mr. B. Ralph Sylvia Fermi-2 Facility.
y]
Detroit Edison Company.
l cc:
Mr. Ronald C. Callen Ms. Lynn Goodman i
!Adv. Planning Review Section Supervisor -- Licensing.
Michigan,Public. Service Commission Detroit Edison Company 6,545 Mercantile Way Fermi Unit 2 P. 0. Box 30221 6400. North Dixie Highway eLansing,. Michigan!:48909 Newport,' Michigan -48166
? John Flynn, Esq.
Senior Attorney Detroit Edison Company 2000 Second Avenue Detroit, Michigan-48226 1
Nuclear Facilities and Environmental Monitoring Section Office
. Division of Radiological Health P. O. Box 30035' i
Lansing, Michigano48909 i
Mr. Walt Rogers U.S. Nuclear: Regulatory Commission Resident Inspector's Office 6450.W. Dixie Highway i
Newport,. Michigan 1 48166
> Monroe County Office of Civil.
Preparedness 953 South-Raisinville Monroe, Michigan 48161-
' Regional Administrator, Region III U.S. Nuclear Regulatory Commission-
- 799 Roosevelt Road
. Glen Ellyn, Illinois 60137 l
I
i
~
1 ATIACHMENT A l
GENERAL QUESTIONS / REQUESTS l
Reviews of several licensee submittals has shown that most (although not all) of the submittals commonly lack certain information that is needed for evaluation of the submittals. Thus, this general list of questions and,
L requests has been prepared for submission to each of the licensees. For, those portions of this attachment for which the requested information was supplied (in the detail requested herein) in the original submittal, the utilities may reference the relevant pages or tables in the original submittal and supply only the requested information that was not provided. However, if the information requested concerning any of the items herein was not provided in the original licensee submittal, an omission of that information from the response to this RAI will be construed as an endorsement of the
. applicable NRC Staff position.
Item 1. Position on NRC Staff Positions Generic I4tter 88-01 states on page 3:
" Pursuant to 10 CFR 50.54(f), you, as a BWR operating reactor licensee or construction permit holder, are requested to furnish, under oath or affirmation, your current plans relating to piping replacement, inspection, repair, and leakage detection.
Your response should indicate whether you intend to follow the staff
)
positions included in this letter, or propose alternative measures."
The staff positions outlined in Generic Letter 88-01 include positions on: (1) Materials.
(2) Processes.
(3) Water Chemistry. (4) Weld Overlay. (5) Partial Replacement.
(6) Stress Improvement of Cracked i
(7) Clamping Devices.
(8) Cra.ck Evaluation and Repair Criteria. (9) Inspection Method and Personnel. (10) Inspection Schedules. (11) Sample Expansion. (12) Leak Detection. (13)
Reporting Requirements.
Please supply information concerning whether the licensee: (1) endorses these positions, (2) proposes alternate positions, exceptions, or provisions, and (3) is c'onsidering or planning to apply them in the future. Please describe any alternate positions, exceptions, or provisions that are proposed.
l Please supply this information using a table such as that illustrated in the example shown in Table 1.
l A-1 o
e
~
e Table 1
. Responses to NRC Staff Positions Licensee Response
- Licensee Has/Will**
Accept Requests
.t with Alternate Applied Consider for i
Staff Position Accept Provisions Position in Past-Future Use
- 1. Materials
- 2. Processes
- 3. Water Chemistry
- 4. Weld Overlay 1
- 5. Partial Replacement
- 6. Stress Improvement of Cracked Weldments
- 7. Clamping Devices t
- 8. Crack Evaluation and Repair Criteria
- 9. Inspection Method and Personnel i
- 10. Inspection Schedules
- 11. Sample Expansion I
- 12. Leak Detection
- 13. Reporting Requirements Answer with "yes", " check mark" or "X" in appropriate column for each of the 13 NRC Staff Positions. List and explain each provision and/or alternate position (or reference original submittal if it contains the listing and explanation). Use separate page(s) if needed.
- Answer with "yes" or "no", as appropriate, in each column for each of 13 NRC Staff Positions.
l A-2 o
p L
<v j
1
- 1. -
ATTACHKENT A (continued)-
Item 2. Inservice Inspection Pronram Generic Letter 88-01 requests on page 3:
' "Your current plans regarding pipe replacement and/or other measures taken or to be taken to mitigate IGSCC and provide assurance of continued long-term integrity and reliability."
"An Inservice Inspection Program to be implemented at. the next refueling outage for austenitic stainless steel piping covered under the scope of this letter that conforms to the staff positions on inspection schedules methods and personnel, and sample expansion included in this letter."-
)
The information pertaining to the pipe repiscesent and other
' mitigating actions as well as the Inservice Inspection Program provided in most of the licensee submittals were either incomplete or did not provide the background data that is needed to evaluate the ISI Program such as (1) reasons / justification for IGSCC classification of welds, (2) methods,. personnel qualification, schedules and identities of welds inspected, and (3) results of previous inspections, and/or identities of welds to be inspected during future inspections.
Thus, the'following information is requeeted:
i
- 1. A listing of all welds by system, pipe size, configuration i
(e.g., pipe to elbow, pipe to valve, etc.), drawing number (piping ISO with weld I.D.), location (i.e., inside or
{
outside of containment, etc.), weld I.D. number, and IGSCC classification (i.e.
IGSCC Category A, B, C, D, E, F and G).
- 2. Reason / justification for the classification of each weld, using such information as (a) weld history such as heat sink i
welding (HSW), (b) pipe and weld metal compositions or material identities to show either conforming material or non-conforming i
material, (c) mitigating treatment (s) applied such as solution heat treating (SHT), stress improvement (IHSI or MSIP).
- 3. Identity of welds to be inspected during past and future refueling outage. Include (a) dates and results of previous i
inspections, (b) flaw characterierte. including orientation (axial or circumferential), maximum length, maximum depth, repairs and/or mitigating treatments applied.
Please supply this information in tabular form using formats such as that illustrated in Tables 2 and 3.
A-3 0
i l
i-e
- i Table 2 History,of Welds and Prior Mitigating Actions / Treatments
- Material **
1 ICSCC Weld Dia.
Casting Treatment ***
i Caten. System Number Configuration Inch Fornina. Pipe Weld SHT NWS CRC E 0.L.
l 4
I l
Notes:
List each weld separately, using one or more lines as required.
- For material: identify as non-conforming or conforming as appropriate concerning whether.it conforms with the NRC Staff position on resistant materials. If conforming, identify the i
material type (e.g., Type 316 NG).
i
- For treatment: list "X" under appropriate column (s) if weld was i
treated using indicated technique, i.e., solution heat treated (SHT), heat sink welded (HSW), corrosion resistant clad (CRC),
j stress improved (SI), or overlayed (0.1..-).
For SI, add explanation of method used, i.e., whether by induction heating or mechanical, whether pre and/or post treatment inspection was applied using methods and personnel qualified under NRC/EPRI/BWROG coordination plan', and whether treatment was applied within two years of service date. Also add explanation and justification of any overlays that were not' atandard (per NRC Staff position).
l e
i 4
A-4
.v l
l l
c l
Table 3 Inspection Schedules l
ICSCC Inspected /To Be Inspected / Flaws Found j
Weld Dia.
Past Future-Caten System No.
Inch. Configuration R.O.#X-2 R.O.fX-1 Flaw R.O.fX R.O.fX+1 1
j d
Instructions:
- 1. Under the heading, " Inspected /To BE Inspected," use as many columns as required to describe the followings i
(a) All previous inspections that were conducted (per NUREG 0313, Revision 2, page 5.2) using methods and personnel qualified under NRC/EPRI/BWROG coordination plan as upgraded in September,1985.
plus (b) A sufficient number of. future inspections to demonstrate that the schedules will follow the NRC Staff positions as given in Table 1 in Generic letter 88-01.
l
- 2. Replace R.O.i (X-2, X-1, X, X+1) with actual refueling outage numbers. Indicate dates inspections were/will be performed.
- 3. List each weld within the scope of Generic Letter 88-01.
- 4. Place an "X" or other appropriate symbol under the appropriate column for each refueling outage for which that weld was inspected or will be inspected.
- 5. Indicate with "yes" under dolumn marked " flaw" if a flaw indication was found. Attach a statement for each flawed weld giving the orientation (axial or circumferential), the dimensions (maximum length and depth), and describing any repairs made.
O A-5
.v f
i
c i
l
~
I i
ATTACHMENT A (continued)
Item 3. Welds Covered in Licensee-Submittel Generic latter 88-01 (on page 2) states:
i "This Generic Letter applies to all BWR piping made cf sustenitic l
stainless steel that is four inches or larger in nominal diameter and contains reactor coolant at a tempe'rature above 200*F during power operation regardless of Code classification. It also applies to reactor vessel attachments and appurtenances such as; jet pump instrumentation penetration assemblies and head spray and vent components."
Were any welds that fall within this defined scope excluded from the licensee submittal (for example, welds in the RWCU outboard of i
the isolation valves)? If previously excluded, please list identity of such welds and plans for mitigation and inspections in Tables 2 and 3 or provide alternative proposal. If IGSCC susceptible welds were excluded from the licensee subeittal based on temperature considerations please identify the welds and describe in detail the method of. temperature measurements.
l t
Item 4. Welds that Are Not UT Inspectable Generic Letter 88-01 (in Table 1) states " Welds that are not UT l
inspectable should be replaced, " sleeved", or local leak detection applied. RT examination or visual inspection for leakage may also be considered."
Does the licens,ee submittal include discussions and plans for:
(a) All welds that are inaccessible for UT inspections?
(b) All welds that are only partially accessible for UT 3
inspections?
1 (c) Welds that cannot be Uf inspected because of geometrical constraints or other reasons.
If not, please list these welds and plans for mitigation / inspection.
Item 5. Leakage Detection Generic Letter 88-01 states on page 3:
" Confirmation of you plans to ensure that the Technical A-6
.w
J s.
s-ee r..
ATTACHMENT A (continued)
Specification related to leakage detection will be in'conformance with'the staff position on leak detection included in this letter."-
The staff position is outlined on pages 5 and.6 of Generic Letter j
g 88-01 and include the following items:
l
- 1. Leakage detection should be in conformance with Position C I
of Regulatory Guide 1.45 " Reactor Coolant Pressure Boundary Leakage Detection Systems," or as otherwise approved by the NRC.
- 2. Plant shutdown should be initiated for corrective action when:
i I
(a) within any 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period any leakage detection system indicates an increase of unidentified leakage in excess of 2 sps or its equivalent, or
-(b) the total unidentified leakage attains a rate of 5 sps or equivalent.
- 3. Leakage shou?d be monitored (or determined from flow measurements
".! flow is continuously monitored) at'approximately four hour intervals or less.
- 4. Unidentified leakage should include all leakage other than (a) leakage Anto closed systems, or (b) leakage into the containment atmosphere from sources that are both specifically located and known either not to interfere with operations of monitoring systems or not to be from a throughwall crack.
- 5. For plants operating with any IGSCC~ Category D, E, F, or G welds, at least one of the leakage measurement' instruments associated with each sump shall be operable, and the outage time for inoperable instruments shall be limited to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or immediately initiate an orderly shutdown.
i Although most licensee submittals describe the intention of meeting some or all of these requirements or offer alternative measures, it is not always clear whether these requirements are contained in the Technical Specifications. Thus it is requested that this information should be provided by each licensee. For clarity and completeness, please use a checklist such as that illustrated in Table 4.
l A-7 l
l
.t'
- )
J a
Table 4 Licensee Positions on Leaksge Detection Already TS will be Alternate Contained Changed Position Position in TS to Include Proposed
- 1. Conforms with Position C of Regulatory Guide 1.45 1
- 2. Plant shutdown should be initiated when:
(a) within any period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or less, an increase is indicated in the rate of unidentified leakage in excess'of 2 spa, or (b) the total unidentified leakage attains a rate of'5 spa.
t
- 3. Leakage monitored at four hour intervals or less.
- 4. Unidentified leakage includes all except:
1 (a) leakage into closed systems, or (b) leakage into the containment atmosphere from sources that are located, do not interfere with monitoring systems, or l
not from throughwall crack.
~
- 5. Provisions for shutdown within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> due to inoperable measurement instruments in plants with Category D, E, F, or G welds.
I Instructions:
Place "I" or "yes" under appropriate column for each item. Provide description and justification for alternative positions if not already provided.
A-8
--