Monthly Operating Repts for Feb 1989 for Hatch Units 1 & 2
ML20236B013
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 02/28/1989
From: Beard R, Hairston W
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
0550I, 550I, HL-351, NUDOCS 8903200281
Download: ML20236B013 (12)


Text

_ _ - _ _ _ _ - _ -

i3-

)

i ENCLOSURE 1

' TABLE OF CONTENTS ~

PLANT HATCH - UNIT 1-NRC DOCKET 50-321~

MONTHLY OPERATING REPORT

-FEBRUARY 1989-NARRATIVE REPORT-Page'El-1 OPERATING DATA REPORT Page.El AVERAGE DAILY P0HER LEVEL-Page El-3 UNIT SHUTDOHNS AND POWER REDUCTIONS Page El..

l

'i l

i I

Of L 8903:200281 890228 R"

.PDR':ADOCK 05000321 h

/}'

R

~

PDC-y

\\h-

]

L

.c I

n i;

i a

NARRATIVE REPORT DOCKET N0. 50-321 UNIT 1

.DATE: MARCH 2, 1989 COMPLETED BY:

R. M. BEARD TELEPHONE: -(912) 367-7781 x2878 FEBRUARY 1 0000 On line maintaining rated thermal power.

FEBRUARY ?

2348

. Reducing load to'735 GMWe for Weekly Turbine Valve and Auxiliaries Testing and CR0 Exercise.

FEBRUARY 11 0010 Reducing load to 740 GMWe for Turbine Stop Valve Testing, i

Weekly Turbine Valve and Auxiliaries Testing and CRD -

Exercise.

FEBRUARY 18 2110 Reducing load to 710 GMWe for Turbine Bypass Valve' Testing,.

Weekly Turbine Valve and Auxiliaries Testing and CRD Exercise.

i FEBRUARY 19 1645 Reducing Core Thermal Power to 2425 CMWt due to unavailability of the process computer.

FEBRUARY 25 2104 Reducing load to 215 GMWe for repair of the Reactor Recirculation System's Motor / Generator Sets, cleaning of the i

Circulating Water Pump Screens, Weekly Turbine Valve and Auxiliaries Testing and CR0 Exercise.

FEBRUARY 28 2400 On line maintaining rated thermal power.

l El-1

OPERATING DATA REPORT DOCKET NO. 50-321-DATE:

MARCH 2, 1989 COMPLETED BY:

R. M. BEARD 0PERATING STATUS

1. UNIT NAME:

E. I. HATCH UNIT 1

2. REPORT PERIOD:

FEBRUARY, 1989

3. LICENSED THERMAL POWER (MWt :

2436

4. NAMEPLATE RATING (GROSS MWe :

850

5. DESIGN ELECTRICAL RATING N T MWe :

776.3

6. MAXIMUM DEPENDABLE CAPACI Y GROS MWe):

789.6

7. HAXIMUM DEPENDABLE CAPACITY NET MWe 756.6
8. IF CHANGES OCCUR IN CAPACITY RATINGS):

(ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS: NO CHANGES

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):

NO RESTRICTIONS

10. REASONS FOR RESTRICTION, IF ANY:

N/A THIS MONTH YR. TO DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD:

672.00 1416 115391

12. NUMBER OF HOURS REACTOR WAS CRITICAL:

672.0 1416.0 82263.9

13. REACTOR RESERVE SHUTDOWN HOURS:

0.0 0.0 0.0

'14. HOURS GENERATOR ON-LINE:

672.0 1416.0 77992.1

15. UNIT RESERVE SHUTDOWN HOURS:

0.0 0.0 0.0

16. GROSS THERMAL ENERGY GENERATED (MWH):

1613568 3417360 169898046

17. GROSS ELEC. ENERGY GENERATED H):

524770 1114040 54827970

18. NET ELEC. ENERGY GENERATED (M 502661 1067393 52094026
19. 'JNIT SERVICE FACTOR:

100.0%

100.0%

67.6%

20. UNIT AVAILABILITY FACTOR:

100.0%

100.0%

67.6%

21. UNIT CAPACITY FACTOR USING MDC NET :

98.9%

99.6%

60.2%

22. UNIT CAPACITY FACTOR USING DER NET :

96.4%

97.1%

57.7%

23. UNIT FORCED OUTAGE RA E:

0.0%

0.0%

'15.0%

24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH): N/A
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

N/A

26. UNITS IN TEST STATUS ( PRIOR TO COMMERCIAL OPERATION):

N/A El-2 L-________-__--___

.?

,v

' UNIT 1 DOCKET NO. 50-321 AVERAGE DAILY DATE:

MARCH 2, 1989 POWER LEVEL COMPLETED BY: R. M. BEARD FEBRUARY, 1989 TELEPHONE:-(912) 367-7781 x2878 1

I

. DAY Net MW 1.........

1756 2..........

753 3.........-

754

-l 4.........

756 5.........-

757 1

6.........

756' 7.........

757 8.........

764 9.........

767 10.........

766 11.........

765 12.........

764 13.........

760 i

14.........

756 15.........

755 i

16.........

755 17.........

760 18.........

'758 19......;..

762-20.........

759-21.........

755 22.........

761 23.........

763 24.........

763 25.........

726 26........'.

483 27.........

757 28.........

757 i

i i

1 i

El-3

L

~

3 b

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-321 DATE: MARCH 2, 1989-UNIT NAME:

E.I. HATCH 1 COMPLETED BY:

R. M. BEARD TELEPHONE:

(912) 367-7781 x2878 l

REPORT MONTH FEBRUARY, 1989 I

'l

.R M

5 E

E Y

T A

T LICENSEE SC Y

S H

EVENT T0 COMPONENT CAUSE & CORRECTIVE P

DURATION 0

0 REPORT ED CODE ACTION TO N0.

DATE E

(HOURS)

N D

NUMBER HE' (SUBCODE)

PREVENT RECURRENCE 89-001 890225 S

0 B

5 N/A CB GENERA Reduced load in order to',

(X) repair the Reactor q

Recirculation System's i

Motor / Generator Sets.

1 See narrative for other 1

activities performed l

concurrently.

l l

F: FORCED REASON:

METHOD:

EVENTS REPORTED INVOLVE 1 - MANUAL-A GREATER THAN 20%

A-EQUIPMENT FAILURE (EXPLAIN) 2 - MANUAL SCRAM S: SCHEDULED B-MAINTENANCE OR TEST REDUCTION IN AVERAGE C-REFUELING 3 - AUTO. SCRAM DAILY POWER LEVEL FOR i

D-REGULATORY RESTRICTION 4 - CONTINUATIONS THE PRECEEDING 24 HOURS.

i E-0PERATOR TRAINING & LICENSE 5 - LOAD REDUCTION i

F-ADMINISTRATIVE 9 - OTHER (EXPLAIN)

G-0PERATIONAL ERROR (EXPLAIN)

H-0THER (EXPLAIN) 1 i

El-4

l

~

ENCLOSURE 2 TABLE OF CONTENTS PLANT HATCH - UNIT 2 l

NRC DOCKET 50-366 l

MONTilLY OPERATING REPORT l

ffBRUARY 1989 l

8.

NARRATIVE REPORT Page E2-1 OPERATING DATA REPORT Page E2-2 AVERAGE DAILY POWER LEVEL Page E2-3 UNIT SHUTDOWNS AND POWER REDUCTIONS Page E2-4

.a x

s 4

i NARRATIVE ~ REPORT' DOCKET NO. 50-366 UNIT'2 DATE: MARCH'2, 1989 COMPLETED BY:' Re M. BEARD TELEPHONE:- (912) 367-7781 x2878 FEBRUARY 1 0000-On line' maintaining. rated thermal power.

FEBRUARY 4' 2300 Reducing load,to 720 GMWe for Weekly Turbine Valve and Auxiliaries Testing and CR0 Exercise.

FEBRUARY-8 0430' Reducing Core Thermal' Power to less than 2432 CMWt 'due to unavailability of the Core Thermal Power Program in the process computer.:

FEBRUARY 12-0020 Reducing load to' 720 GMWe for Weekly Turbine Valve and Auxiliaries Testing, Rod Pattern Adjustment and CRD Exercise.

<(

' FEBRUARY 16 1632 Reducing Core-Thermal Power to 2425 CMWt due to

~ ;

unavailability of the process computer.

l FEBRUARY.18 2130 Reducing load to 720 GMWe for Weekly Turbine Valve and Auxiliaries Testing, Rod Pattern Adjustment and CRD. Exercise.

)

FEBRUARY 26

.1436

. Reducing' load to 720 GMWe for Monthly-and Weekly Turbine Valve and Auxiliaries Testing, Rod Pattern Adjustment and CRD Exercise FEBRUARY'28 2400 On line maintaining rated thermal power.-

1

r i

i i

E2-1 t

i

)

L.

(,

h OPERATING DATA REPORT DOCKET N0. 50-366 DATE: MARCH 2, 1989 COMPLETED BY:

R. M. BEARD TELEPHONE:

(912) 367-.7781 x2878 OPERATING STATUS:

I

1. UNIT NAME:

E. I. HATCH UNIT-2

. 2. REPORTING PERIOD:

FEBRUARY, 1989 i

.3.

LICENSED THERMAL POWER (MWt :

2436

]

4. NAMEPLATE RATING (GROSS MWe :

850 i

6. UESIGN ELECTRICAL RAflNG (N T MWe):

784

'j

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):

800.7 4

7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):

767.7 l

8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NO CHANGES

9. POWER LEVEL TO WHICH RESRTICTED, IF ANY (NET MWe):

NO RESTRICTIONS

.10. REASONS FOR RESTRICTION, IF ANY:

N/A.

i THIS MONTH YR-TO-DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD:

672.00 1416 83017

12. NUMBER OF HOURS REACTOR WAS CRITICAL:

672.0 1416.0 60318.3.

13. REACTOR RESERVE SHUTDOWN HOURS:

0.0 0.0 0.0

14. HOURS GENERATOR ON LINE:

672.0 1416.0 57772.0

15. UNIT RESERVE SHUTD0WN HOURS:

0.0 0.0 0.0

16. GROSS THERMAL ENERGY GENERATED MWH):

1630704 3422256 125459681

17. GROSS ELEC. ENERGY GENERATED (M H):

535310 1125130 41218120

18. NET-ELEC. ENERGY GENERATED (MWH :

513102 1078435 39235620

19. UNIT SERVICE FACTOR:

100.0%

100.0%

69.6%

20.' UNIT AVAILABILITY FACTOR:

100.0%

100.0%

69.6%

21. UNIT CAPACITY FACTOR USING MDC NET):

99.5%

99.2%

61.8%

22. UNIT-CAPACITY FACTOR USING DER NET):

97.4%

97.1%

60.3%

23. UNIT FORCED OUTAGE RA E:

0.0%

0.0%

9.1%

24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE, AND DURATION OF EACH):

Maintenance Outage:

tentatively scheduled for April 22, 1989; 7 Days 25.'IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

N/A

26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

N/A i

E2-2 l

r-v

?

l l" i' UNIT 2 DOCKET NO. 50-366 AVERAGE DAILY.

DATE: MARCH 2, 1989 POWER LEVEL COMPLETED BY:

'R.

M. BEARD

' FEBRUARY, 1989 TELEPHONE:

(912) 367-7781 x2878_

.i DAY Net'MW l

)

-1.........

764 2.........

760 3.........

760 4.........

759 5..........

758 6.........

759 7.........

761

'8.........

767 9.........

769 10.........

770 11.........

773 12.........

766 i

13.........

767 14.........

759 15.........

759 I

16.........

759 17.........

765 18.........

'765 19.........

770 20.........

766 i

21.........

761 22.........

767 23.........

771 24.........

770 25.........

772 1

26.........

732 27.........

766 28.........

765 i

i l

I E2-3 i

j

~

h, UNIT SHUTDOWNS AND POWER' REDUCTIONS DOCKET NO.-50-366 CAIC: MARC 9 2, 1989' UNIT NAME:

E.I. HATCH 2 COMPLETED BY:

R. M. BEARD TELEPHONE:

(912) 367-7781 x2878 REPORT MONTH FEBRUARY, 1989 R

M 5

E E

Y T

A T

LICENSEE SC Y

S H

EVENT T0 COMPONENT CAUSE & CORRECTIVE P

DURATION 0

0 REPORT ED CODE ACTION TO N0.

DATE E

(HOURS)

N D

NUMBER HE (SUBCODE)

PREVENT RECURRENCE No significant power reductions this month.

4 l

i i

I l

F: FORCED REASON:

METR:0D:

EVENTS REPORTED INVOLVE 1 - MANUAL A GREATER THAN 20%

A-EQUIPMENT FAILURE (EXPLAIN) 2 - MANUAL SCRAM S: SCHEDULED B-MAINTENANCE OR TEST REDUCTION IN AVERAGE ~

l C-REFUELING 3 - AUTO. SCRAM DAILY POWER LEVEL FOR D-REGULATORY RESTRICTION 4 - CONTINUATIONS THE PRECEEDING 24 HOURS.

E-0PERATOR TRAINING & LICENSE 5 - LOAD REDUCTION F-ADMINISTRATIVE 9 - OTHER (EXPLAIN)

G-0PERATIONAL ERROR (EXPLAIN) 4 H-0THER (EXPLAIN) l i

t E2-4 I

i

. = _.._,

' _-lGhyga 1%ipiCornpiny,

3,,

9

-.i333 Pmdmont Avena %

Nf1.., g Attenti(korgia 30303--

Thiephxo 404 6263195 t

fMa!!sg Address,

40 Invercer,s Center fw.sw

. Post ofh:o Ocx 1295

-Lrnh;; ham, Na%rna 35201 ~

Tetest'one 20S 868 5581 L

>1 3 Y/! v.iv_'t 4 sydy$

e-4,

' W. G. Hairston,111 l

Senior V4:e Presicent. -

Nucwu coma:es HL-351' i

0550I-

- X7GJ17-H510

.l March 7, 1989 U. S. Nuclear Regulatory Commission ATTW: Document Control Desk i'

Hashington, D. C.

20555 PLANT HATCH - UNITS 1, 2 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 l

MONTHLY OPERATING REPORTS 1

Gentlemen:

a i

Enclosed ~ are the Monthly Operating Reports. for Plant Hatch Unit 1,

' Docket Number -.50-321, and for Plant Hatch Unit ' 2, Docket Number 50-366.

These ' reports.' are submitted in accordance with the requirements of Technical Specifications Section 6.9.1.10.

Sincerely, W.J./

H. G. Hairston, III SJB/ls

Enclosures:

1.

Monthly Operating Report for Hatch-1 i

2.

Monthly Operating Report for Hatch-2 l

I c:

(See next page.)

i l

t b

i I \\

3 a

.t

['.

i r

1 U. S. Nuclear. Regulatory _ Commission

(

~ March 7, 1989

'l

- Page Two-c: Georaia Power Comoany Mr. H.: C. Nix, General Manager - Plant Hatch' Mr. L. T.,Gucwa, Manager Nuclear Engineering and Licensing l

GO-NORMS

')

U. S. Nuclear Regulatory Commission. Washinaton. D. C.

Mr. L. P. Crocker, Licensing Project Manager - Hatch ll U. S. Nuclear Reaulatory Commission. Reaion II i

Mr. S. D. Ebeneter, Regional Administrator l

Mr. J. E. Menning, Senior Resident Inspector - Hatch

.1 l

l i-

'I i

l f

i i

i i

h 0550I

.