ML20235G135
Jump to navigation
Jump to search
| ML20235G135 | |
| Person / Time | |
|---|---|
| Site: | Calvert Cliffs |
| Issue date: | 08/31/1986 |
| From: | Behnke C BALTIMORE GAS & ELECTRIC CO. |
| To: | |
| Shared Package | |
| ML20235G063 | List: |
| References | |
| NUDOCS 8709290457 | |
| Download: ML20235G135 (1) | |
Text
--
I l
UNIT 2 ANNUAL OPERATING DATA REPORT Docket No. 50-318 Date: September 14, 1987 Prepared by C.
Behnke Tel. (301) 260-4871
- 1. UNIT NAME Calvert Cliffs Unit 2 1
- 2. REPORTING PERIOD AUGUST (Rev 1) 1986
- 3. LICENSED THERMAL POWER (MWT) 2700
- 4. NAMEPLATE RATING (GROSS MWe) 918 5.
DESIGN ELECTRICAL RATING (NET MWe) 845
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS M 860
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWe 825 8.
CHANGE IN CAPACITY RATINGS none 9.
POWER LEVEL TO WHICH RESTRICTED n/a
- 10. REASONS FOR RESTRICTIONS n/a 1986 August Year-to-Date Cumulative
- 11. HOURS IN REPORTING PERIOD 744 5,831 82,559
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 739.0 5,592.2 69,035.2
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 24.3 1,285.0
- 14. HOURS GENERATOR ON LINE 723.6 5,565.3 67,976.6
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,929,569 14,379,407 170,861,443
- 17. GROSS ELECTRICAL ENERGY GENERATED (M 623,320 4,825,820 56,347,344
- 18. NET ELECTRICAL ENERGY GENERATED (MWH 596,547 4,622,579 53,772,836
- 19. UNIT SERVICE FACTOR 97.3 95.4 82.3
- 20. UNIT AVAILABILITY FACTOR 97.3 95.4 82.3
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 97.2_
96.1 78.9
- 22. UNIT CAPACITY FACTOR (USING DER NET)
_94.9 93.8 77.1
- 23. UNIT FORCED OUTAGE RATE 2.7 4.1 6.0
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):
Refueling Shutdown:
March 14, 1987 to May 22, 1987 (69 days)
- 25. IF SHUTDOWN AT END OF STARTUP PERIOD, ESTIMATED DATE OF STARTUP:
n/a i,
R
-