PARSONS Daniel L. Curry, vico Presdent. Nacicar serv <-es Parsons Energy & Chemicals Group loc.
2675 Morgantown Road + Reading, Ponosylvania 19607 + (610) 855-2366 + Fat (610) 855-2602 April 20,1998 Docket No. 50-336 Parsons NUM2-PPNR-1381-L U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Millstone Nuclear Power Station Unit No. 2 Independent Corrective Action Verification Program (ICAVP)
Gentlemen:
Pursuant to your recent request, attached please find the Millstone Unit 2 ICAVP Bi-Weekly Report for week ending April 17,1998.
Please call me at (610) 855-2366 if you have any questions.
Sincerely, Daniel L. Curry Parsons ICAVP Project Director DLC:cvb Attachments 1.
Bi-Weekly Report cc:
E. Imbro (2) - USNRC H. Eichenholz - USNRC R. Laudenat - NNECo J. Fougere - NNECo
.s Rep. Terry Concannon - NEAC Project Files 9804270108 980420 PDR ADOCK 05000336 i
P PDR
' e)
PAGE1 Encompass
~'U P
PPNR1381. doc
PAR $ IONS Daniel L Curry, %ce Pres. cent Nuclear Geoces Parsons Energy & Cherracats Group Inc.
2675 Morgantown Road a Reading. Pennsylvania 19607 * (610) 855-2366
- Fax: (610) 855-2602 April 20,1998 Doc. ID: NUM2-PPNU-1380-L Mr. Richard Laudenat Northeast Nuclear Energy Company Millstone Nuclear Power Station Unit 2 P. O. Box 128 Waterford, CT 06385 Re:
Millstone Unit 2 ICAVP Bi-Weekly Progress Report
Dear Mr. Laudenat:
The following represents a bi-weekly progress report for work completed on Millstone Unit 2 ICAVP for the week ending April 17,1998.
Project Schedule: Forecasted discovery completion dates noted in Tier summaries presented below.
Tier 1 - System Vertical Slice Reviews HPSI system discovery complete. Corrective Action Review and DR close-out is still pending.
AFW system review continuing. Discovery forecast remains June 15,1998, exclusive of accident
=
reanalyses, HELB/EQ and SBO efforts discussed below.
RRC system review in progress. Discovery forecast remains June 5,1998, exclusive of accident reanalyses, HELB/EQ and SB0 discussed below. Revised response on DR-0027 is needed in order to better understand the revised design criteria for the EBFS system.
EDG system review in progress. Discovery complete forecast remains June 12,1998, exclusive of accident reanalysis, HELB/EQ and SBO, discussed below.
Programs -
=> SB0 was not received from NNECo on target date of April 7,1998. New date appears to be in May. Schedule for completion of SB0 is 8 weeks following receipt of all information
=> HELB/EQ - limited information expected to be received in mid-May from NNECo. Final information expected per NNECo by 15 September.
=> Completion of Tier 1 systems review is dependent on NNECo accident reanalyses impact on selected systems.
Tier 2 - Accident Mitigation System Review Closure of preliminary DRs, UIRs and RAls is required to complete Tier-2 review. See Attachment B for details.
Design inputs have been received for 8 of the 12 DBEv being reanalyzed by NNECo. Design inputs for the remaining 4 DBEv were scheduled to be transmitted to Parsons by April 15,1998.
Short tenn (April) stafling reductions initiated based upon slippage of projected reanalysis completion dates.
Tier 2 schedule revised based on NNECo " Accept Analysis" date of April 30,1998. Tier 2 discovery gomplete approximately 8 weeks following receipt of revised analyses.
I
a Mr. Richard Laudenat
+
Northeast Nuclear Energy Company NUM2-PPNU-1380-L April 20,1998 ~
Analysis review - 29 Design Basis Events (DBEv) 13 DBEv Discovery Complete I
8 DBEv Validations in Progress 8 DBEv Awaiting Revised Analyses I
Tier 3 - Process Review Tier 3 discovery complete date changed to April 27,1998 (due to outstanding Tier 3 RAls.). This does e
not include vendor technical manual resiews. In addition, through response to RAI-1313, the sample population of setpoint change requests has been found to be larger than originally stated by NNECo. The effects of this on present sample plan are being evaluated.
Report preparation in progress for completed sample areas.
Reviews in progress for specification revision, drawing revision, NCRs and ASME Section XI Repairs.
Vendor manual review on hold until NNECo can identify the population of Unit 2 manuals to be updated and the NNECo schedule for updates and validation of procedures.
Other Activities:
Phone conferences completed on April 14 and 16,1998.
Discrepancy Reports See Attachment A for details RAI (Status)
Total issued 1415
=
27 greater than 2 weeks / total outstanding 148 e
HPSI - (RAI-0766, RAI-0921, RAI-1054, RAI-1320)
AFW - (RAI-0766, RAl-1087, RAI-1303, RAI-1306, RAI-1321)
RRC -(RAl-1125, RAI-1309) e EDG - (RAI-1223, RAI-1246, RAI-1266, RAI-1285, RAI-1293, RAI-1305)
Tier 2 Validation (RAI-l115, RAI-1257(p), RAI-1314)
=
Tier 3 (RAI-l 168, RAl-1323, RAI-1361, RAI-1350)
Should you have any questions on the contents of this progress report, do not hesitate to contact me at (610) 855-2366.
Sincerely, h
Daniel L. Curry Project Director DLC/cyb Attachment ec:
J. Fougere E. A. Blocher J. L. Caldwell W. L. Dobson J. F. Hilbish E. Imbro (USNRC)
M. J. Akins W. L. Dobson R. T. Glaviano Project Records 2 of 2 Encompass Letter PPNU1380. Doc
e Attachment A to April 17,1998 Bi-weekly Report Discrepancy Report Summary and Status 510 Preliminary DR Numbers issued by Parsons 437 Preliminary DRs approved of which 15 determined to be invalid 102 Responses received to date from NU 35 DRs CIOSED 56 DRs OPEN 11 DRs IN-PROGRESS (Awaiting revised response from NU on 3 DR's) i Of the 35 Valid and Closed Discrepancies resolutions 15 Confirmed Discrepancies 12 Previously Identified by NNECo 8 Non-discrepant Conditions Of the 15 Confirmed Discrepancies l
0 - Level 1 0 - Level 2 0 - Level 3 15 - Level 4 l
4 4
Attachment B: Tier-2 AMSR Validation Open items (Status as of 4/17/98)
This attachment lists information needed to complete validation of the Critical Design Characteristics associated with the FSAR Chapter 14 Accident Analyses.
Preliminary Discreoancy Reports - Provide completion schedule and closure package for the listed DRs.
DR-027 Enclosure Building Ventilation System DR-033 HPSI Flow DR-045 Deboration During Startup DR-202 MSSV Accumulation DR-205 Pressurizer Safety Valve Accumulation DR-313 RPS RC Low Flow Trip Setpoint DR-412 Containment Purge Supply Air Flow Delicit (New Item)
NNECo identified items - Provide completion schedule and closure package for the listed items.
Note: the listed items may have related UIRs, CRs, etc.
UIR-288 RCS Pressure Uncertainty UIR-929 Pressurizer Level UIR-2601 Containment Purge Flow Rate Used In Fuelllandling Accident Analysis (New Item)
UIR-3198 Containment Purge Isolation Time Assumed for Fuel Handling Accident (New Item)
Revised FS AR Chapter 14 Analyses - The below table lists events being reanalyzed by NNECo and identifies information needs to complete the Tier-2 validation. RAls will be submitted upon NNECo acceptance of the revised analyses.
Event _
Design inputs NNECo Accept Revised Analysis (ECD)
' Analysis -
14.1.3 Increase in Steam Flow 27 Feb 98 Rx 15 Apr 98 RAI (later) 14.1.5 Main Steam Line Break (RCS Analysis) 27 Feb 98 RS 15 Apr 98 RAI (later)
(14.2.11
- Loss of External Load :
-27 Feb 98 R -
Complete" 223 Mar 98 R4 14:2.4 2 s Closure of Main Steam Isolation Valve 27 Feb 98 R S Complete 3 23 Mar 98 R 14.2.7 Loss of Normal Feedwater Flow 27 Feb 98 R 4 30 Apr 98 RAI(later) 14 4.1 Startup Rod Withdrawal Accident 24 Mar 98 R 15 Apr 98 RAI(later) 14.4.6 CVCS Malfunction Causing RCS Deboration RAI-Ill5 30 Apr 98 RAI (later) 14.6.5.1 Large Break LOCA (RCS Analysis)
RAl-1115 30 Apr 98 RAI (later) 14.6.5.2 Small Break LOCA RAl 1115 15 Apr 98 RAI (later) 14.6.3 Steam Generator Tube Rupture RAl-1115 3! Mar 98 RAI(later)
!!4.8.2.11 2 Containment Analysis (MSLB) -
Received '
interim - '
6 Mar 98 R1 (14.8.2.1) Containment High Press Trip During MSLB RAl-1115 15 Apr 98 RAI (later) 114.8.2.2r < Containment Analysis (LOCA) -
Received' Complete" 6 Mar 98 R -
RC Pump Coastdown Curve
^24 Mar 98 R 15 Apr 98 RAI(later) j Note: R = Documents received by Parsons on indicated date Reauests for AdditionalInformation RAls: 1257 & 1314 (Revised item) l