Forwards List of License Conditions Re 980214 Amend Request to Allow Operation at Increased Reactor Core Power Level of 2775 Mwt,In Response to NRC 980323 Telcon
ML20217C132
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 04/17/1998
From: Dennis Morey
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9804230224
Download: ML20217C132 (5)


Text

I* Dave Morey Southern Nuclear )

, Vice President OperatingC mp ny {

fadey Project P.O. Box 1295 i

Birmingham. Alabama 35201 i

, Tel 205.992.5131 1

l SOUTHERN h April 17,1998 COMPANY l Energy to Serve YourWorld" Docket Nos.: 50-348 10 CFR 50.90 50-364 i

U. S. Nuclear Regulatory Commission ATTN.: Document Control Desk Washmgton,DC 20555 Joseph M. Farley Nuclear Plant License Conditions Related to Power Uprate Facility Ooeratina Licenses and Technical Soccifications Channe Reauest Ladies and Gentlemen:

By letter dated February 14,1997, Southern Nuclear Operating Company (SNC) proposed to amend the Facility Operatmg Licenses and Technical Specifications for Joseph M. Farley Nuclear Plant (FNP) Unit I and Unit 2 to allow operation at an increased reactor core power level of 2775 megawatts thermal (MWt). During a telephone conference call on March 23,1998, NRC and SNC representatives discussed the proposed operating license conditions currently under consideration by the NRC Staff. Each of these conditions is listed in Attachment I, " Additional Conditions Operating License No. NPF-2," and Attachment II, " Additional Conditions Operating License No. NPF-8."

SNC concurs with the first and second conditions for FNP Units 1 and 2, since SNC previously 1 committed to perform these training activities in SNC letter dated September 22,1997. SNC agrees i to the third condition for FNP Units 1 and 2.

Should you have any questions, please advise.

Respectfully submitted, Jk ll'H Dave Morey Sworn to and subscribed before me this/hy of 998 W/adla

              '~~

Notaryfubtf/ 6 9) w My Commission Expires: b l,000/ t g\ MGF/maf: pwrup37. doc 0 Attachments cc: Mr. L. A. Reyes, Region II Administrator 33QL[ Mr. J. I. Zimmerman, NRR Project Manager Mr. T. M. Ross, Plant Sr. Resident Inspector 9804230224 980417 PDR ADOCK 05000348 P pop

k ATTACHMENT I Joseph M. Farley Nuclear Plant Units 1 and 2 License Conditions Related to Power Uprate Facility Operating Licenses and Technical Specifications Change Request ADDITIONAL CONDITIONS OPERATING LICENSE NO. NPF-2 I i

                                                                                 )

i

        ~

? . I I t

                  .                                  APPENDIX C i

ADDITIONAL CONDrflONS OPERATING LICENSE NO. NPF-2 1 Southern Nuclear Operatmg Company, Inc. shall comply with the following conditions on the schedules noted below. l Amendment Condition Number Additional Condition Comoletion Date xxx SNC shall complete classroom and simulator training Prior to Unit 2 for operations crews as described in SNC's letter dated entering Mode 2 from September 22,1997 ar.d evaluated in the staffs Safety the spring 1998 Evaluation dated .1998. refueling outage. L J l xxx SNC shall complete final simulator modifications in 2 years after restart accordance with ANSI /ANS 3.5-1985 and review from the Unit I fall , results of the Cycle 16 startup testing to determine any 1998 refueling outage. l potential effects on operator training as described in SNC's letter dated September 22,1997 and evaluated l in the staffs Safety Evaluation dated . ! 1998. l xxx SNC shall provide a Steam Generator Tube Rupture Prior to the Unit 1 radiological consequences analysis that incorporates a steam generator flashing fraction which is appropriate for the Unit I replacement outage in design. spring 2000. l i l t l

l . i . ATTACIIMENTII Joseph M. Farley Nuclear Plant Units 1 and 2 License Conditions Related to Power Uprate Facility Operating Licenses and Technical Specifications Change Request ADDITIONAL CONDITIONS OPERATING LICENSE NO. NPF-8 I I i 1

i l

              .                                  APPENDIX C ADDITIONAL CONDITIONS OPERATING LICENSE NO. NPF-8 Southern Nuclear Operating Company, Inc. shall comply with the following conditions on the schedules noted below.

Amendment Condition Number Additional Condition Comoletion Date xxx SNC shall complete classroom and simulator training Prior to Unit 2 for operations crews and temporary simulator entering Mode 2 from modifications as described in SNC's letter dated the spring 1998 September 22,1997 and evaluated in the staff's Safety refueling outage. Evaluation dated .1998. I xxx SNC shall review results of the Cycle 13 startup Prior to Unit I startup i testmg to determine any potential effects on operator from the fall 1998 training and incorporate these changes into Licensed refueling outage. , Operator training as described in SNC's letter dated l September 22,1997 and evaluated in the staff's Safety Evaluation dated .1998. xxx SNC shall provide a Steam Generator Tube Rupture Prior to the Unit 2 , radiological consequences analysis that incorporates a steam generator flashing fraction which is appropriate for the Unit 2 replacement outage in design. spring 2001. I}}