Mr. Russell A. M:ll:r March 18, 1998 Vice Presid:nt - Operations and Decommissioning Connecticut Yankee Atomic Power Company 362 injun Hollow Road East Hampton, Connecticut 06424-3099
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR EXEMPTION FROM OFFSITE EMERGENCY PLANNING REQUIREMENTS (TAC NO. M99015)
Dear Mr. Mellor:
We are continuing our review of your proposed changes to your requested exemptions from emergency plannin0 requirements, as detailed in your letter to us dated May 30,1997.
However, in order for us to independently evaluate your conclusion that the spent fuel stored at Haddam Neck would not be susceptible to a zircalloy fuel clad fire and would not result in offsite radiological dose consequences in excess of Environmental Protection Agency Protective Action Guides, should the spent fuel pool be drained of all water, we require site-specific dimensions and construction information partaining to the Haddam Neck wet spent fuel storage system. The information needed is listed in the attachment. This request affects nine or fewer respondents and therefore,is not subject to Office of Management and budget review under P.L.96-511. In accordance with 10 CFR 50.30(b),
your response must be executed in a signed original under oath or affirmation.
j If you have any questions regaiding this request, please contact me at (301) 415-1112.
Sincerely, ORIGINAL SIGNED BY:
Thomas L. Fredrichs, Preiect Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket No. 50-213
Enclosure:
As stated
\\
l cc w/onclosure:
T)\\[]\\
/,
See next page l
~
l DISTRIBUTION:
l E-MAIL HARD COPY j
RDudley JMinns Docket File 50-213 JRoe RLeeman MFairtile LThonus PUBLIC SWeiss JO' Brian PHarris MWebb EHylton MMasnik AMarkley DWheeler TFredrichs OGC PDND r/f Region I
..itLd y
g PDND (d)SC g PDND:(A)D PDND:P g
P
,D
/
TFredrichd i E
on MMasnik MMje donca 3/N/98 3// /96 3/j' /98 3////98 OFFICIAL RECORD COPY DOCUMENT NAME: G:\\SECY\\FREDRICH\\RAl99015 9903260206 980318 PDR ADOCK 05000213 e]m hd*'a -
ar fh f-
![,i F
1 1^
- Mr. Russell A. Milior March 18, 1998
' Vice President - Operations and Decommissioning
{
I Connecticut Yjg}kee Atomic Power. Company 362 injun HoIlow Road East Hampton, Connecticut 06424-3099
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR EXEMPTION FROM OFFSITE EMERGENCY PLANNING REQUIREMENTS (TAC NO. M99015)
Dear Mr. Meltor:
We are continuing our review of your proposed changes to your requested exemptions from emergency planning requirements, as detailed in your letter to us dated May 30,1997.
However, in order for us to independently evaluate your conclusion that the spent fuel stored at Haddam Neck would not be susceptible to a zircalloy fuel clad fire and would not result in offsite radiological dose consequences in excess of Environmental Protection Agency Protective Action Guides, should the spent fuel pool be drained of all water, we require site-specific dimensions and construction information pertaining to the Haddam Neck j
wet spent fuel storage system. The information needed is listed in the attachment. This j
request affects nine or fewer respondents and therefore, is not subject to Office of
'l Management and budget review under P.L.96-511. In accordance with 10 CFR 50.30(b),
your response must be executted in a signed original under oath or affirmation.
If you have any questions regarding this request, please contact me at (301) 415-1112.
j Sincerely, ORIGINAL SIGNED BY:'
Thomas L. Fredrichs, Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket No. 50-213
Enclosure:
As stated cc w/ enclosure:
See next page DISTRIBUTION:
E-MAIL HARD COPY RDudley JMinns Docket File 50-213 JRoe RLeeman MFairtile LThonus PUBLIC SWeiss JO' Brian PHarris MWebb EHylton MMasnik AMarkley DWheeler TFredrichs OGC PDND r/f Region i W\\
1 PDND:P P
D' PDNDJk)SC PDND:(A)D TFredrichd i E
on MMasnik MMje donca 3/N/98 3// /98 3/h/98 3////98 j
OFFICIAL RECORD COPY l
DOCUMENT NAME: G:\\SECY\\FREDRICH\\RAl99015
p reg g
i UNITED STATES s
j NUCLEAR REGULATORY COMMISSION 4
WASHINGTON, D.C. 30865 4 001 March 18, 1998 g,,
Mr. Russell A. Mellor Vice President - Operations and Decommissioning.
Connecticut Yankee Atomic Power Company 362 Injun Hollow Road East Hampton, Connecticut 06424-3099 l
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR EXEMPTION FROM OFFSITE EMERGENCY PLANNING REQUIREMENTS (TAC NO. M99015)
Dear Mr. Mellor:
We are continuing our review of your proposed changes to your requested exemptions from emergency planning requirements, as detailed in your letter to us dated May 30,1997.
However, in order for us to independently evaluate your conclusion that the spent fuel stored at Haddam Neck would not be susceptible to a zircalloy fuel clad fire and would not result in offsite radiological dose consequences in excess of Environmental Protection Agency Protective Action Guides, should the spent fuel pool be drained of all water, we require site-specific dimensions and construction information pertaining to the Haddam Neck wet spent fuel storage system. The information needed is listed in the attachment. This request affects nine or fewer respondents and therefore, is not subject to Office of Management and budget review under P.L.96-511. In accordance with'10 CFR 50.30(b),
your response must be executed in a signed original under oath or affirmation.
If you have any questions regarding this request, please contact me at (301) 415-1112.
i Sincerely, n,4r Thomas L. Fredrichs, Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket No. 50-213
Enclosure:
As stated cc w/ enclosure:
See next page
n Connecticut Yankee Atomic Power Co.
Haddam Neck Plant Docket No. 50-213 cc:
Lillian M. Cuoco, Esq.
Resident inspector Senior Nuclear Counsel Haddam Neck Plant Northeast Utilities Service Company c/o U.S. Nuclear Regulatory Commission P. O. Box 270 362 injun Hollow Road Hartford, CT 06141-0270 East Hampton, CT 06424 3099 Mr. Kevin T. A. McCarthy, Director Mr. James S. Robinson i
Monitoring and Radiation Division Manager, Nuclear Investments and Department of Environmental Administration Protection New England Power Company 79 Elm Street 25 Research Drive Hartford, CT 06106-5127 Westborough, MA 01582 Mr. Allan Johanson Mr. G. P. van Noordennen l
Assistant Director Manager - Nuclear Licensing Office of Policy and Management Northeast Utilities Service Company Policy Development and Planning 362 injun Hollow Road Division East Hampton, CT 06424-3099 450 Capitol Avenue-MS#52ENR P. O. Box 341441 Regional Administrator Hartford, CT 06134-1441 Region i U.S. Nuclear Regulatory Commission Mr. F. C. Rothen 475 Allendale Road Vice President - Work Services King of Prussia, PA 19406 Northeast Utilities Service Company P. O. Box 128 Board of Selectmen Waterford, CT 06385 Town Office Building Haddam, CT 06438 Mr. D. M. Goebel Vice President - Nuclear Oversight Northeast Utilities Service Company P. O. Box 128 Waterford, CT 06385 Mr. J. K. Thayer Recovery Officer, Nuclear Engineering and Support Northeast Utilities Service Company P. O. Box 128 Waterford, CT 06385 l
l l
ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION l
ASSESSMENT OF THE LOSS OF WATER FROM THE SPENT FUEL POOL AT HADDAM NECK As part of the submittal review, corJirmatory calculations will be performed regarding the maximum temperature of the spent fuel given the water of the poolls completely drained.
To expedite the process, please provide the following information in the designated units.
Provide any variables that are dependent on temperature at 533'K [500*F] and 700*K
[800*F]. State all assumptions made and provide drawings,if necessary. If approximate values are provided, indicate the degree of certainty conservatively applied to the value.
For each batch of assemblies, provide the following information:
l 1.
Location or region in pool, if applicable (do not provide the rack location coordinates) 2.
Number of assemblies per batch 3.
Fuel burnup (MWD /MTU) 4.
Enrichment (%)
5.
Metric tons of urenium per assembly (MTU)
I 6.
Batch discharge date For the following parameters (7-22), provide the applicable information for each batch.
l Batches with the same properties can be identified in groups.
l 7.
Spent fuel array parameter (i.e,15x15,7x7) 8.
Number of active fuel rods per assembly 9.
Outside rod diameter of the fuel (m)
- 10. Rod center-to-center pitch (m)
- 11. Fuel rack cell / channel dimension (s) (m)
- 12. Thickness of the cell wall. If the rack is an open-lattice type, please state as such (m)
- 13. Center-to-center pitch of assemblies (m)
- 14. Diameter of baseplate hole (m)
- 15. Thermal conductivity of the cell walls (W/m K)
- 16. Specific heat of cell walls (Joule /Kg-K)
- 17. Density of cell walls (Kg/m')
l
- 18. Thermal conductivity of the fuel (W/m-K) j
- 19. Specific heat of fuel (J/Kg-K) l
- 20. Density of fuel (Kg/m')
- 21. Cladding material
- 22. Thermal conductivity of the clad (W/m-K)
I
- 23. Specific heat of clad (J/Kg K) i
- 24. Density of clad (Kg/m')
- 25. Thickness of the clad (m) i i
?. -
l ~.
[ '.
2-i For the spent fuel pool and building, provide the following information:
. 26. Thermal conductivity of the concrete [ pool encasement) (W/m X)
{
= 27. Specific heat of concrete (Joule /Kg K)
)
l
- 28. Density of concrete (Kg/m*)
I
' 29. Thickness of pool concrete encasement (m)
- 30.. Thermal conductivity of the storage building walls and ceiling (W/m-K) i 31.. Specific heat of storage building walls and ceiling (Joule /Kg K)
- 32. Density of storap building walls and ceiling (Kg/m )
S
'33. - Average thickness of the storage building walls and ceiling (m)
- 34. Total surface area of the storage building walls and ceiling (m')
- 35. Volume of storage building (m )
8 2
- 36. Total surface area of the pool floor (m )
37i ' Height from pool floor to baseplate of the rack (m)
- 38. Width of downcomer - distance between racks and the edge of the pool (m)
- 39. Cross-sectional area of the border of the pool [ space between the pool wall and the 2
cells) (m )
. 40. Length of active fuel (m)
. 41. Length from the top of the active fuel to the top of the spent fuel rack (m)
_ 4 2.
To characterize the open volume in the racks that do not contain assemblics, please describe the amount of empty cells, water boxes, etc. In the pool.
l
- 43. Provide diagrams showing elevations or distances for the pool:
Top view Provide a top view of the pool. Please include, but not limited to, the lengths and widths _of pool, clearances / space around the edge of the pool, layout of the modules, open space, and cask loading area (if applicable),
j Top view Provide a top view of a cell showing the wall thickness and cell dimensions.
Side view Provide an elevation drawing of the fuel racks from the pool floor to the top of the racks Please include, but not limited to, the space j
between the floor and the bottom of the spent fuel rack, the active fuel height, the distance from the top of the active fuel to the top of the cell, and the overall depth of the pool, i
- 44. Decay heat for each assembly (KW), and decay profile of assemblies.