ML20215N282

From kanterella
Jump to navigation Jump to search
Insp Repts 50-327/86-45 & 50-328/86-45 on 860721-25.Major Areas Inspected:Preparation & Implementation of Design Baseline & Verification Program,Including Design Criteria Preparation,Engineering Change Notice & Sys Evaluations
ML20215N282
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/21/1986
From: Architzel R, Imbro E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
Shared Package
ML20215N277 List:
References
50-327-86-45, 50-328-86-45, NUDOCS 8611050169
Download: ML20215N282 (23)


See also: IR 05000327/1986045

Text

,

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSFECTION AND ENFORCEMENT

Division of Quality Assurance, Vendor, and Technical

Training Center Programs

Report Nos.:

50-327/86-45, 50-328/86-45

Docket Nos.:

50-327; 50-328

Licensee:

Tennessee Valley Authority

6N, 38A Lookout Place

1101 Market St.

Chattanooga, TN 37402-2801

Facility Name:

Sequoyah Nuclear Plant, Units 1 & 2

Inspection At:

Knoxville, TN

Inspection Conducted:

July 21-25, 1986

Inspection Team Members:

Team Leader:

R. E. Architzel, Senior Inspection Specialist, IE

Mechanical Systems:

F., Mollerus, Consultant, Mollerus Engineering Inc.

Mechanical Components:

~A. V. duBouchet, Consultant

Civil / Structural:

A. Unsal, Consultant, Harstead Engineering

Electrical Power:

S. V. Athavale, Inspection Specialist, IE

Instrumentation &

Control:

L. Stanley, Consultant, Zytor Inc.

Nuclear Systems:

J. M. Leivo, Consultant

,

Operations:

P. E. Harmon, Resident Inspector, SQN

Licensing:

J. J. Holonich, Project Manager, NRR

F. Rinaldi, Structural Engineer, NRR

0. Terao, Mechanical Engineer, NRR

h

W }/-[b

'

Ralph E. Architzel u

Date

Team Leader

W Y Wm b.

Icl2//)(

Eugene V. Imbro

' Date

Section Chief

g10$$b$$IbO

7

G

, _- -

.

.

LIST OF ABBREVIATIONS

AEC

Atomic Energy Commission

.

ANSI

American National Standards Institute

APM

Anchor Point Movement

CFR

Code of Federal Regulations

CGCS

Combustible Gas Control System

C/R

Commitment / Requirement

DBD

Design Basis Document

DBVP

Design Baseline and Verification Program

DNE

Division.<of Nuclear Engineering

EA

Engineering Assurance

ECN

Engineering Change Notice

ESF

Engineered Safety Features

EQ

Environmental Qualification

FSAR

Final Safety Analysis Report

GDC

10CFR50, Appendix A, General Design Criteria

HVAC

Heating, Ventilation and Air Conditioning

i

INP0

Institute of Nuclear Power Operation

IEEE

Institute of Electrical and Electronics Engineers

LBB

Leak Before Break

LOCA

Loss of Coolant Accident

NEB

Nuclear Engineering Branch

NMS

Neutron Monitoring System

NCR

Non-Conformance Report

'

NRC

Nuclear Regulatory Commission

NSSS

Nuclear Steam Supply. System

P&ID

Piping and. Instrumentation Diagram

RDBD

Restart Design Basis Document

SCR

Significant Condition Report

SQEP

Sequoyah Engineering Procedure

'

SQN

Sequoyah Nuclear Plant

TVA

Tennessee Valley Authority

'

i

.--

__

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

SEQUOYAH NUCLEAR POWER PLANT

Design Baseline and Verification Program v

-

Inspection Report 50-327/86-45 & 50-328/86-45

July 21-25, 1986

1.

INTRODUCTION AND BACKGROUND

,

The design baseline and verification program (DBVP) was developed by the

Division of Nuclear Engineering (DNE) to resolve design control issues

described in several TVA sponsored evaluations and audits and NRC inspections.

The Sequoyah Nuclear Plant (SQN) Design Baseline and Verification Program will

be used by TVA to provide the required level of confidence that the modifica-

tions to selected plant systems, implemented since receipt of the operating

license, have not resulted in any violation of the plant's licensing basis. The

program is described in the " Program Plan for the Engineering Assurance

Independent Oversight Review for the Sequoyah Nuclear Plant Design Baseline and

Verification Program;" ' dated May 9, 1986 and forwarded to the NRC as an

enclosure to Mr. R. L. Gridley's letter dated June 27, 1986.

2.

PURPOSE

NRC inspection activities related to the TVA's DBVP and associated Engineering

Assurance (EA) independent technical oversight of Sequoyah Nuclear plant are

planned to be conducted in several phases:

(1)

Inspection of program preparation and initial implementation (EA Review

plans and procedures, DBVP procedures, walkdown results).

(2)

Inspection of program implementation, including design criteria

preparation, Engineering Change Notice (ECN) and system evaluations.

(3)

Inspection of DBVP and EA oversight results and corrective actions.

.

This inspection focused on the development and updating of the design criteria.

The NRC previously conducted an inspection (Report Nos. 50-327/86-38 and

50-328/86-38) of the DBVP. This previous inspection focused on overall

DBVP plan and scope, implementing procedures, and the conduct and results of

walkdowns.

The purpose of this inspection was to (1) review TVA's program for design criteria

preparation, (2) review a sample of the revised and newly issued design

criteria, and (3) overview the efforts of TVA's Engineering Assurance (EA)

group for independent review of the design criteria. An integral part of the

design criteria preparation was the generation and use of a (new) commit-

ment / requirement (C/R) data base.

The purpose of the Sequoyah design criteria reconstitution program is to

generate revised design criteria documents which address system and general

functional design requirements governing the design of structures, systems and

components. At TVA, these design criteria documents include current licensing

commitments and regulatory requirements, as well as design criteria that are

.not commitments but TVA self-imposed standards of " good engineering practice."

The revised design criteria will be used by TVA as the basis to review all

plant modifications made to those systems or portions of plant systems within

1

s

_

9

-

.

.

.

'

4.

SUMMARY OF FINDINGS

.

4.1 Program for Design Criteria Preparation

,

Team review of SQEP-18, " Procedure for Identifying Commitments and Requirements

as Source Information for Sequoyah Design Criteria Development," showed that a

program has been established to identify the licensing commitments and other

design requirements. The team also reviewed SQEP-29, " Procedure for Preparing

the Design Basis Document," which addresses the methods to be used to capture

the C/Rs and other design input in an upper tier, commitment driven, compila-

tion of design and design documentation requirements.

During a prior inspection of the DBVP (Inspection Report 86-38), the team had

performed a preliminary review of the computerized list of licensing commit-

ments and design requirements called the " Commitment / Requirement Data Base."

The team found that this list, developed by TVA/Impell, was not independently

verified. Although Quality Assurance controls were not applied to the

information retrieval process, the Engineering Assurance group has conducted

reviews in this area on a sampling basis. The NRC team does not consider that

these reviews were done in sufficient technical depth or were of sufficient

scope to allow meaningful conclusions to be drawn regarding the completeness of

the C/R data base. This data base forms a portion of the basis for the newly

issued design criteria. d,ocuments.

.

The team discussed future plans the project was considering to verify the

accuracy of the C/R data base. Consideration was being given to independently

verifying incorporation of all C/Rs in design output documents, for example.

Prior to restart, TVA considers that the independent verification provided

during preparation of new and revised design criteria provides the required

verification of inc,o'rporation of C/Rs. The team remains concerned regarding

the identification of C/Rs. Therefore, TVA should clearly define their basis

for concluding that the C/R data base has accurately captured all licensing

commitments, regulatory requirements and other pertinent design information as

applicable, e.g. NSSS vendor interface requirements (Inspection Report 86-38,

Observation No. 5.4).

4.2 Revised and New Issue Design Criteria

The team identified a concern regarding the incorporation of proprietary

information in the design criteria due to a lack of availability (within

TVA) of proprietary source documents containing C/Rs (Observation No. 3.4)

The team identified several cases where C/Rs applicable to selected design

criteria were not captured (Observation Nos. 4.4, 5.5, 6.6, and 6.7).

Environmental Qualification requirements were found to be incorporated in an

inconsistent manner among various design criteria (Observation Nos 4.5 and

6.5). The team also identified missing requirements in the design criteria for

'

the neutron monitoring system, apparently at the interface between the NSSS

and TVA. These findings, collectively, raise a concern regarding the compre-

hensiveness of the design criteria.

Several technical observations were identified relating to the coordination

(between design criteria) of overcurrent protection and cable sizing for

medium voltage motors (Observation No. 5.6); the collection of varied single

l

failure definitions and commitments into a single document (Observation

!

l

3

-

-

-

-

<

'

.

-

.

the scope of the .DBVP since operating license issuance to provide assurance

'

that SQN is in conformance with its licensing basis.

As a part of the Design Baseline and Verification Program, TVA is preparing a

.

"

Design Basis Document (DBD) and a Restart Design Basis Document (RDBD). The

DBD defines, establishes, and maintains the design requirements for the

Sequoyah Nuclear Plant. Although a design basis currently exists for the

Sequoyah Nuclear Plant, the design basis documents were not always readily

retrievable in a verified form. Thus, TVA identified a need for a verified,

controlled design basis document to be maintained throughout plant life. The

DBD is intended tc, be used to evaluate and control design changes, to respond

to abnormal operations and events, to evaluate limiting conditions for

operation, to perform safety reviews, to assess conditions adverse to quality,

to assess operating experience reports',' end'to provide an interface with

outside organizations. The RDBD will be the initial issue of the DBD and will

cover those safety-related systems identified by TVA calculation SQN-0SG7-048

which are required to support hot shutdown and mitigate postulated accidents

described in FSAR Chapter 15.

The DBD contains general design criteria for site, plant, structures, and sys-

tems which establish the plant-specific design input requirements. The 080

also contains certain detailed design criteria, system descriptions, design

input drawings, engine'er.ing decisions, analysis results, and engineering para-

meters for detailed de' sign. The design commitments and requirements to be used

as a basis for developing the design criteria were identified using TVA

procedure SQEP-18.

~

3.

INSPECTION ACTIVITIES

The following activities were generally performed by all team members.

Evaluation of applicable DBVP procedures for generation of the

commitment / requirement data base and for updating the design basis

document.

Review of selected design criteria generated or updated as a result of

the DBVP.

Review a sample of the commitment / requirements associated with the

selected design criteria to verify their incorporation.

Examination of the results to date of the independent oversight review of

C/Rs and design criteria.

In addition, the HRR team members conducted a walkdown at the Sequoyah Nuclear

Plant to physically examine hardware which is the subject of substantive

technical issues. Observations from the walkdown in the small bore piping and

HVAC duct and support disciplines are also discussed in this report.

1

2

.

.

.

No. 6.8); an'd implementation of 10 CFR 50 General Design Criteria requirements

for containment penetrations (Observation No. 8.2)

Several concerns were identified by team members from the NRC Office of

Nuclear Reactor Regulation who are reviewing interim acceptance criteria being

applied for SQN piping, pipe supports, and cable tray designs (Observation

Nos. 8.1-8.4).

These findings are documented in this report for completeness,

but will be resolved independently by NRR during their review of these issues.

During this inspection, the team reviewed several system functional ' design

criteria, as well as two recently issued Civil Engineering Branch general

design criteria that supersede Watts Bar design criteria which TVA had used to

design pipe anchors and pipe supports at Sequoyah Nuclear Power Plant. The

team identified two design requirements specified in the Watts Bar design cri-

teria for the design and modification of pipe supports that TVA did not specify

in the Sequoyah design criteria issued on June 23, 1986. The new design

criteria does not require that the local stresses generated in the piping by

stiff pipe clamps with large preload be checked and allows pipe axial loading

of floor or wall sleeves that have not been designed for such pipe loads

(Observation No. 3.4).

The Sequoyah Project has not found any items which they determined necessitated

the issuance of a new desian criteria or any revision to existing design

criteria (prior to restart) in the Civil / Structural discipline during review of

the licensing commitments and design requirements. Several examples of

situations which the team' considers should have resulted in such criteria

changes were identified (Observation Nos. 7.2-7.3).

4.3 EA Independent Oversight Review Program Plan

The team expressed certain reservations with the review plan being implemented

for the instrumentation and control discipline to assess the technical adequacy

of design changes. The team's concerns included:

(1) establishing an appropriate balance between important technical

issues and quality assurance issues as described in the checklists;

(2)

the representativeness of the four systems selected, and

(3) the relatively small sample sizes chosen for. review of design

criteria, engineering change notices, and field change notices.

The instrumentation and control discipline specific action plan for EA review

of the C/R data base states that approximately ten representative commitments /

requirements would be selected from a variety of source documents including

letters and memorandums. These choices will then be reviewed for their inclu-

sion in the Sequoyah commitments / requirements (C/R) data base. Review attributes.

described in the implementing checklist include the identification of source

documents, training of personnel for this activity, kreparation of the C/R data

sheet used for input to the Sequoyah commitment / requirement data base, and dis-

tribution of the data base output to involved us~ers.

i

While a sample size of ten may be sufficient to validate the processing of

identified commitments and requirements through the Sequoyah C/R data base, the

t

4

,

--

-

_ _ _ _ _ _ __

proposed action plan is unlikely to be sufficiently comprehensive to vabdate

the method used to initially identify individual commitments and requirements

from the designated source documents. Since the overall effectiveness of the

C/R data base-is dependent upon the accuracy of the determination of specific

commitments and requirements, greater emphasis appears necessary to validate

the method and procedure used for identification of commitments and

requirements.

Although no specific observations were identified, team members reviewing in

.Other disciplines also noted a lack of technical depth and breadth in the

samples selected for oversight by EA.

Limited oversight products were

available in the mechanical systems and nuclear systems areas.

In the electric

power area, the team found that the EA oversight was thorough and identified

findings (Action Items) similar to those identified by the team.

In the Civil / Structural. area the team found that the plan of action and the

attributes shown in the'EA oversight review plan indicate that an adequate plan

has been established to review the Sequoyah project work.

5.

SPECIFIC COMMENTS

Specific comments of individual NRC discipline inspectors are categorized as

observations. The observations and a description of the activities performed

by each discipline of:the NRC team are provided in Attachment A of this report.

TVA actions relating '.c individual observations will be reviewed by the NRC

during future inspections. These observations elaborate on the general

comments stated in this report and in some cases provide additional coments

not considered to be of a general nature.

6.

MEETING SUMMARIES - REFERENCES

A summary of the meetings. held relating to the DBVP inspection and a list of

references are provided in Attachment B.

5

.

.

.

- - .

--

.

- . .

. .

.

-

- - .

-- ..

.

Attachment A - Inspsction Activities and Obsarvations

NOTE: The observation numbers used in this report are a continuation of the

~

.

numbers used for the previous DBVP inspection.

(ReportNos. 50-327/86-38 &

,

i

50-328/86-38). The references are listed in Attachment B.

.

i

-

1.0 OPERATIONS

!

!

In the operations area the team examined selected design criteria, EA action

items from the previous inspection, incorporation of various commitments /re-

quirements, and coordinated with other team disciplines in the conduct of the

inspection. No observations were identified in the operations area.

,

2.

MECHANICAL SYSTEMS

In the mechanical systems discipline, the team reviewed the.following design

criteria generated for the baseline restart effort.

4

'

Responsible

<

Design Criteria No.

Ti tle

TVA Branch

SQN-DC-V-3.1.1

Steam Generator Blowdown System

MEB

SQN-DC-V-4.1.1

Main Steam System

MEB

>

SQN-DC-V-4.2

Feedwater System

MEB

SQN-DC-V-7.4

Essential Raw Cooling Water System

MEB

SQN-DC-V-13.9.3

. Auxiliary Building Ventilation & Cooling

MEB

SQN-DC-V-13.9.8

Auxiliary Feedwater System

MEB

<

SQN-DC-V-13.9.9

Component Cooling Water

MEB

SQN-DC-V-16.0

Auxiliary Contro1 Air System

MEB

SQN-DC-V-27.6

Residual Heat Removal System

MEB

!

The team reviewed the Engineering Assurance Oversight Review

!

Plan - Mechanical (Reference 9). This plan is organized by the following

activities.

  • Walkdowns

!

Licensing Commitments

!

Design Basis

l

Change Control Board

"

Evaluation of Change Documents

i

!

Comparison of Design Documents with Walkdown Results

System Evaluations

Modifications to Control Room Drawings

l,

Unreviewed Safety Question Determination (USQD)

l

Each activity description includes a plan of action, description of sample

j

size, and an attributes check list. The latter is basically a check list to

j

evaluate the acceptability of the activity being monitored.

1

One observation was identified concerning TVA's access to and incorporation of

j

proprietary information in the design criteria (Observation No. 2.3).

,.

)

Observation No. 2.3 - Status of NSSS Vendor Proprietary Information

i

Several of the commitment / requirements (C/Rs) listed in the analysis report for

l

l

the component cooling water system are NSSS vendor reports and memoranda that

!

}

A-1

b.

.,,


.,,,-,--,--..---.,,,-,,,n---.

- - .

, , - - , , , , , , - - , ,

- , , , , - - . - - - . - - - . - . - - - , - . , , . , ~ . , , . -

.,----,v,

,,, . - - + . .

-

Attachment A - Inspection Activities and Observations

are considered by the NSSS vendor to be proprietary and unavailable to outside

-

The NSSS vendor also stated.that the C/Rs contained in

organizations.

.

proprietary memoranda are also contained in formal documents that have been made

available to TVA. The inspection team was informed that the formal documents

are being used as a source of C/Rs for the design criteria; the NSSS vendor

proprietary correspondence is not. TVA's basis of the acceptability of_this

approach was the NSSS vendor's statement that all C/Rs are contained in the

formal documents. The titles of the proprietary correspondence will be kept in

the C/R tracking system until restart. At that time, TVA Branch Chiefs will

evaluate all remaining C/Rs not addressed in the design criteria.

The inspection team will continue to follow developments in this NSSS vendar

interface area and TVA's efforts to assure that all NSSS vendor C/Rs are

incorporated in the design basis documents.

3.

MECHANICAL COMPONENTS

In the mechanical components discipline, the team reviewed Sequoyah Design

Criteria SQN-DC-V-2. 14, Piping System Anchors installed in Category I

Structures, which was issued June 30, 1986 and supersedes Watts Bar design

Criteria WB-DC-40.31.15 for new pipe anchor designs and modifications to

existing pipe anchor designs.

-

'

The team also reviewed Seguoyah Design Criteria SQN-DC-V-24.1, Location and

Design of Piping Supports and Supplemental Steel in Category I Structures,

which was issued June 23,.1986 and supersedes Watts Bar Design Criteria

WB-DC-40.31.9 for new pipe support designs and modifications to existing pipe

support designs. Observation No. 3.4 was identified relating to elimination

of requirements from a design criteria document.

<

Observation No. 3.4 - Pipe Support Design Criteria

Sequoyah Design Criteria SQN-DC-V- 24.1, which TVA issued on June 23, 1986 for

the design of new pipe supports and modifications to existing pipe support

designs, supersedes Watts Bar Design Criteria WB-DC-40.31.9, but does not carry

forward the following two design requiremer.ts which are contained in the Watts

Bar design criteria document.

(1) Section 8.2.12 of the Watts Bar Design Criteria, Stiff Pipe Clamps, which

notes that stiff pipe clamps with extremely large pre-load may induce sig-

nificant localized piping stresses, and requires that piping stresses be

investigated for stiff clamps identified in NRC Information Notice 83-80.

(2) Section 8.3.1.2 of the Watts Bar Design Criteria, which prohibits pipe

axial loading of a floor or wall sleeve unless the sleeve has been designed

for a pipe load.

l

This issue needs to be further examined by TVA.

4.

NUCLEAR SYSTEMS

In the nuclear systems area the team reviewed TVA's Engineering Assurance (EA)

oversight work products. At the time of the inspection, the Nuclear Engineer-

ing Branch (NEB) EA products available for NRC review in this area were:

A-2

_ _ _

..

,

Attachment A - Insptcticn Activities and Observations

'

.

(1) A review of the design criteria for the combustible gas control system

(Reference'4) in accordance with SQEP-29, " Procedure for Preparing the

.

"

Design Basis Document for Sequoyah Nuclear Plant."

_

(2) A review of commitment / requirement (C/R) identification for the auxiliary

feedwater and essential raw cooling water systems in accordance with

SQEP-18, " Procedure for Identifying Commitments and Requirements as Source

Information for Sequoyah Design Criteria Development."

The team also reviewed a . sample of DBVP Project generated design criteria. At

the time of the inspection, approximately. half of the NEB design criteria had

been issued; none of the NSSS design criteria had been issued. The team

reviewed the design criteria issued for the combustible gas control system

(CGCS), containment isolation, single failure, and remote shutdown criteria

from locations outside control room (Refs. 4 through 7, respectively).

In

addition, the team reviewed the design criteria for the neutron monitoring

system that had recently been transmitted by _the NSSS vendor, but had not yet

been issued by TVA.

Three observations were identified relating to incorporation of commitments,

consistency of the design criteria, and completeness of design criteria

(Observations Nos. 4.4 - 4.6).

Observation No. 4.4 - Spray Shield Commitment / Requirement for Certain Hydrogen

Igniters in Upper Compartment

.

A spot check of CGCS C/Rs; identified by TVA for commitment changes (and

apparently excluded from the analysis report used in preparing design criteria)

indicated that TVA's C/R to provide enlarged spray shields for upper compart-

ment igniters (Reference 8) has not been included in the CGCS design criteria

(Reference 4). Thi,s' missing requirement does not. appear to have been

identified during the EA review of the design criteria. The team recognizes

that the igniters are provided for mitigation of accidents beyond the scope of

FSAR Chapter 15 events; however, since TVA appears to take credit for the

enlarged spray shields in assuring functionality of the igniters following a

degraded core loss of coolant accident, the team believes the requirement for

' enlarged shields should be included in the CGCS/ hydrogen mitigation system

design criteria.

Observation No. 4.5 - Clear and Consistent EQ Requirements in Design Criteria

The team observed that some of the environmental qualification (EQ) require-

ments as stated in'the few design criteria sampled appear to be somewhat

inconsistent and might be misinterpreted by a user of the criteria who is not

particularly knowledgeable of EQ requirements and procedures.

For example, the

CGCS design criteria do not clearly state what EQ requirements apply to

existing equipment.

Observation No. 4.6 - Missing Criteria for Neutron Monitoring System

While the Neutron Monitoring System (NMS) design criteria had not yet been

issued by TVA, the team reviewed the design criteria provided recently by the

NSSSvendor(Reference 3). Based on the NMS' boundary definition provided in

References 1 and 2, the design criteria appear to be incomplete in the

~

following areas:

l

A-3

l

'

, . - - . - , - -

- - - - - -

.

-

- - . - -

-

- - - - - -

- - - . - . .

Attachment A - Inspection Activities and Observations

.

(1) No requirements are stated or referenced for providing indication of

source range flux outside the control room as required to accomplish safe

-

shutdown from outside the control room; for example, these requirements

are not presented in paragraphs 3.5.1.n or Tables 3.1-1, 3.1-4 of the

document.

(2) No requirements are stated or referenced for electrical penetrations that

are required for NMS functionality.

An indirect reference to IEEE-317

~

provided in Section 3.5.2.8 of the document is not considered sufficient -

to cover the special penetration requirements for these high impedance

.

instruments.

This observation also reflects the concern expressed in Observation No. 4.2

(Inspection Report 86-38) that system functional boundaries should be expli-

citly defined for this system.

For example, it appears that the NSSS vendor

has limited the scope of the NMS design criteria to the system and equipment in

its scope of supply, rather than addressing the functionality of the integrated

system for safe restarts TVA should give sufficient attention to the NSSS/Bal-

ance-of-Plant interfaces, as well as to overall system functionality, so that

no significant items are inadvertently omitted from the review scope.

5.

ELECTRIC POWER

In the electric power di,scipline, the team reviewed portions of design criteria

SQN-DC-V-11.4.1 (Revis' ion 2), for auxiliary power; SQN-DC-V-11.3 for cable

applications; and TVA':s DBVP procedures SQEP-16 (Revision 0), SQEP-29

'

.(Revision 1), and SQEP-18.(Revision 1). The team also reviewed the action

items identified during EA's independent oversight review of design criteria

SON-DC-V.11.2, SQN-DC-V.11.6, SQN-DC-V-11.8 and DBVP procedure SQEP-16

~

(Revision 0). The team noted that of the eight design criteria documents

required in this discipline prior to restart, the EA oversight team had

completed reviews for six design criteria documents. This review resulted in

the identification of 15 Action Items, similar in nature to the observations

identified by the team.

Two observations were identified relating to commitment / requirement incorpora-

tion and cable sizing (Observation Nos. 5.5 and 5.6).

Observation No. 5.5 - Commitment / Requirement Inclusion in Design Criteria for

the Auxiliary Power System

The team reviewed portions of Design Criteria SQN-DC-V-11.4.1 (Revision 2), and

noted the following weak areas.

(1) Many commitment / requirements have been identified on the commitment /

requirement evaluation sheet but were not captured in the design criteria.

Examples include the following.

SON EEB DRW 1072 - TVA's commitment pursuant to IE Bulletin 79-25, which

prohibits the use of Westinghouse type BFD and NBFD relays.

SQN EEB DRW 1073 - TVA's commitment pursuant to IE Bulletin 79-11, which

prohibits the use of Westinghouse type DB-50 and DB-75 circuit breakers

with overcurrent devices.

A-4

. .__

_

_-

'

~ Attachment A - Insp;ction Activities and Observations

SQN EEB DRW 1077 - This.C/R requires mandatory fusing of control ~ circuits.

.

,

SON EEB DRW 1078 - This C/R deals with problems of spurious operation of

diesel generator breaker differential relaying.

(2) Many commitment / requirements which are applicable to the auxiliary power

system were not shown on the commitment / requirement evaluation sheet for

this system. Examples includes the following.

SQN EEB DRW 1092 - This C/R addresses the increased' fault interrupting duty

of 6.9 kv breakers for 3-phase faults during periods when the turbine

generator is operated at higher voltages (25.2 kv) to meet the demands of

the distribution grid.

SON EEB DRW 1017, 1018, 1019 - These C/Rs address the topic of class 1E

station battery capacity, and were not included in the auxiliary power C/R

evaluation.

Observation No. 5.6 - Cable Sizing for Overload Currents

Section 8.5.3d of Design Criteria SQN-DC-V-11.4.1 (Revision 2), stipulates that

for medium voltage motors the overload signal will activate an alarm, only.

In

such situations, since the overload signal does not trip the breaker, the motor

feeder cable could carry an overload current from the time of alarm actuation

until the breaker is tripped manually.

Sizing of the cables should address

this situation.

The team found that design criteria SON-0C-V-11.3 does not address overload

current condition but-stipulates the use of 125% of full load current as the

basis for sizing the, feeder cables.

In situations where overload setting 'is

more than 125% of the full load current, the cable sizing may not be adequate.

This margin of 25% may not be sufficient since the margin may be required for

low voltage operation of the motor and by the motor's service factor (capability

of supplying greater than rated load).

In situations where a motor is required

to operate below its normal rated voltage and/or the motor service factor is

more than 1.0, the motor draws more tha.: its normal full load current. The team

believes that for cable sizing, the c'riteria should address evaluation of each

load on a case by case basis and require sizing the cable accordingly, instead

of directing cable sizing using a blanket rule of 125% of full load current.

6.

INSTRUMENTATION AND CONTROL

The inspection team reviewed TVA procedures SQEP-18 for identification of

commitments and requirements and SQEP-29 for preparation of the design basis

document. A detailed review was made of TVA Design Criteria 26.2 for

environmental qualification, 32.0 for the auxiliary control air system, and

2.16 for single failure criteria. Portions of Westinghouse Design

Criteria 27.6 for the residual heat removal system, 27.8 for the neutron

monitoring system, and 27.9 for the reactor protection system were reviewed for

their instrumentation and control aspects.

In the course of this NRC team

review, several system and technical subject output sorts from the TVA data

base for commitments and requirements were used as well as a TVA computerized

document data base (RIMS) output sorted by the reactor protection system

keyword. A number of commitment / requirement record files in the electrical,

A-5

.

.

.

.

--

_

-

-

_ _ - -

Attachment A - Inspection Activitics and Obstrvations

-

mechanical, and nuclear disciplines were examined, as well as some source

documents such as the FSAR, project letters, and plant drawings.

The NRC team also examined instrumentation and control action items identified

by the TVA EA oversight team during their review of TVA procedures SQEP-18 and

-29 and during their review of the steam generator blowdown and accident

monitoring design criteria. The EA team indicated that one or two more design

criteria would be reviewed; however, the team was concerned with the lack of

depth of technical review being demonstrated by the instrumentation and control

discipline.

Four observations were identified in the Instrumentation and Control discipline

relating to specifications for replacement parts, inclusion of C/Rs in design

criteria, and definition of the single failure criterion (Observation

Nos. 6.5-6.8).

Observation No. 6.5 - Replacement Part and Equipment Qualification

TVA Design Criteria SQN-DC-V-32.0 for the safety-related auxiliary control air

system has inconsistent criteria for the qualification of Class IE replacement

parts and equipment in that section 3.3.1.f specifies the use of IEEE Trial Use

Standard 323-1971. For example, a number of containment isolation valve

solenoids for this system are located in a narsh environment, and must now

conform to IEEE 323-1974 to satisfy the requirements of 10 CFR 50.49.

Although replacement equipment can be exempted from these requirements, sound

reasons must be provided as described in Regulatory Guide 1.89.

Consequently,

the design criteria should be changed to specifically describe those conditions

where use of the IEEE 323-1971 standard might be permitted.

Observation No. 6.6 - Auxiliary Control Air System Design Criteria

A comparison was made of the design basis commitments and requirements data

base output with the design criteria document for the auxiliary control air

system (SQN-DC-V-32.0).

In three instances, the team noted that applicable

commitments or requirements had not been explicitly converted into design

criteria, as follows.

C/R SQN MEB LWB 1208 stated that an air compressor time delay relay had

been replaced with a different relay to achieve a time delay requirement

of 3 seconds. This time delay is used to initiate rapid loading of the

after the air header pressure has

auxiliary control air compressor shortly (which had a range of 20 to 200

dropped to 80 psig. The original timer

seconds) did not assure that a minimum 70 psig air header pressure

requirement would be maintained. The design criteria document did not

reflect this particular time delay requirement.

C/R SQN NED FAK 1229 identified a licensee event report (LER) that

contained a statement that TVA would upgrade the air supply to

safety-related for containment radiation monitoring containment isolation

valves. The design criteria does identify various valves connected to the

auxiliary control air system, but does not list the radiation monitor

isolation valves. The team found that upgrading the air supply to

containment radiation monitor containment isolation valves was not

addressed during revision of the design criteria document.

A-6

Attachment A - Inspection Activities and Observations

'

C/R SQN MEB LWB 1060 identified physical separation requirements for air

-

headers inside cbntainment in response to NUREG 0737. A comitment was

made that there was no adverse interaction due to a design basis event

,

within' containment that would cause a pressure transient that could-fail

equipment needed to mitigate the transient. The design criteria document

did not identify this commitment or the resultant implementation of

physical separation requirements for this system.

Observation No. 6.7 - Oil Free Compressed Air Requirement

TVA commitment / requirement SQN WES RMM 1110 identified a Westinghouse technical

bulletin for solenoid pilot valves in response to NRC IE Bulletin 80-11. In

section 4-9 of the Westinghouse SIP /10-1 manual, a requirement was stated in

the Westinghouse document that the compressed air system must be oil free.

This requirement was omitted from the design criteria document because a

satisfactory definition of " oil free" could not be developed in response to an

internal TVA review comment. No technical justification was provided that use

of a 5 micron filter would suffice to satisfy the oil free requirement.

Observation No. 6.8

, Single Failure Design Criteria

The team reviewed the single failure criteria document, SQN-DC-V-2.16,

dated 7/14/86, with respect to the commitment / requirement data base output.

Three types of concerns . ere noted by the team; (1) the collection of single

w

failure criteria from various sources has led to a loss of clarity regarding

certain constraints for application to both fluid and electric systems; (2) the

~

resolution process used during review of the document prior to issuance has

produced some definitions that are no longer sufficient, and (3) some specific

single failure criteria have not been captured in design documents from the

commitment / requirement data base output.

Thesinglefailurebesigncriteriadocumentdidnotaddresseachoftheinitial

assumptions of: (1) a loss of offsite power, (2) a design basis event, and (3)

the consequential failures that are a direct result of that event prior to the

application of an individual single failure.

The design criteria identified the possibility of passive component failure in

electric systems as stated by the definition section in 10 CFR 50 Appendix A.

However, the concept of passive failure has been applied only to mechanical

fluid systems where certain failures are not postulated during the short-term

period.

Industry practice has been that postulated failures in electric

systems make no distinction between short-term and long-term. periods, and are

generally identified as active failures to minimize confusion.

When an undetectable failure exists that cannot be detected by periodic

surveillance tests, IEEE Standard 379-1977, endorsed by Regulatory Guide 1.53,

states.that the preferred course of action is to redesign the system or the

test scheme to make the failure detectable. The preferred course of action

outlined in the TVA design criteria was to revise the test scheme to eliminate

the undetectable condition, and if this could not be achieved, then a redesign

may be considered. The team considered that TVA design criteria is too

permissive since it appears to encourage the retention of undetectable failures

in the system design.

The TVA design criteria's definition of. independence is "t'he freedom from

effect of one train of equipment on another train." This definition does not

A-7-

,

-

_ - -

.

.

.

-

'

Attachment A - Inspection Activities and Observations

C/R SQN MEB LWB 1060 identified physical separation requirements for air

headers inside containment in response to NUREG 0737. A commitment was

made that there was no adverse interaction due to a design basis event

within containment that would cause a pressure transient that could fail

equipment needed to mitigate the transient. The design criteria document

did not identify this commitment or the resultant implementation of

physical separation requirements for this system.

b

Observation No. 6.7 - Oil Free Compressed Air Requirement

TVA commitment / requirement SQN WES RMM 1110 identified a Westinghouse technical

bulletin for solenoid pilot valves in response to NRC IE Bulletin 80-11. In

section 4-9 of the Westinghouse SIP /10-1 manual, a requirement was stated in

the Westinghouse document that the compressed air system must be oil free.

This requirement was omitted from the design criteria document because a

satisfactory definition of " oil free" could not be developed in response to an

internal TVA review comment.

No technical justification was provided that use

of a 5 micron filter would suffice to satisfy the oil free requirement.

Observation No. 6.8 - Single Failure Design Criteria

The team reviewed the single failure criteria document, SQN-DC-V-2.16,

dated 7/14/86, with respect to the commitment / requirement data base output.

Three types of concerns were noted by the team; (1) the collection of single

failure criteria from v'arious sources has led to a loss of clarity regarding

certain constraints for application to both fluid and electric systems; (2) the

resolution process used during review of the document prior to issuance has

produced some definitions ,that are no longer sufficient, and (3) some specific

single failure criteria have not been captured in design documents from the

commitment / requirement data base output.

The single failure design criteria document did not address each of the initial

assumptions of: (1) a loss of offsite power, (2) a design basis event, and (3)

the consequential failures that are a direct result of that event prior to the

application of an individual single failure.

The design criteria identified the possibility of passive component failure in

electric systems as stated by the definition section in 10 CFR 50 Appendix A.

However, the concept of passive failure has been applied only to mechanical

fluid systems where certain failures are not postulated during the short-term

period.

Industry practice has been that postulated failures in electric

systems make no distinction between short-term and long-term periods, and are

generally identified as active failures to minimize confusion.

When an undetectable failure exists that cannot be detected by periodic

surveillance tests, IEEE Standard 379-1977, endorsed by Regulatory Guide 1.53,

states that the preferred course of action is to redesign the system or the

test scheme to make the failure detectable. The preferred course of action

outlined in the TVA design criteria was to revise the test scheme to eliminate

the undetectable condition, and if this could not be achieved, then a redesign

may be considered. The team considered that TVA design criteria is too

permissive since it appears to encourage the retention of undetectable failures

in the system design.

The TVA design criteria's definition of independence is "the freedom from

effect of one train of equipment on another train." This definition does not

A-s

Atitachment A - Inspection Activities and Obssrvations

~

~

~~

.

)

. Observation No. 7.2 - Comitments/ Requirements Related to Drilled in Anchors

TVA engineers reviewed the computer listing of the comitments/ requirement data

base related to all systems.

In this review they determine whether a

comitment/ requirement should be included in the restart phase of the D8VP.

TVA excluded most of the comitments/ requirements which relate to drilled-in

anchors and placing supports on block walls. TVA's basis for not revising the

design criteria prior to restart was that corrective actions to check adequacy

in this area were being independently pursued by a significant condition

J

report. The NRC team believes that these comitments/ requirements should be

,

re-evaluated to determine whether they should be included in the design

4

criteria for the restart phase because they relate to TVA design standard

DS-C1.7.1 which was recently revised to cover interim criteria.

Observation No. 7.3 - Revision of Design Criteria for Restart

i

Team review of comitment no. SQNCEB-CG1170 from an "all systems" comitment/

requirement data base computer listing shows that this item was included in the

restart phase and that a revision to design criteria SQN-DC-V-1.1.1 ~was

i

necessary. The comitment addresses attachments to reinforced masonry block

walls, which are only to be made with through wall bolts.

No revision to the

design crite'rf a has been made and there was no schedule to revise this design

criteria before restart to incorporate the C/R. TVA should reexamine the

incorporation of C/Rs prior to restart in the Civil Engineering Branch area.

>

.

8.

LICENSING

.

,

.

In the licensing area, theiteam focused on the review of TVA newly developed

i

interim design criteria and related engineering design evaluation, principally

in the Civil Engineering area (Civil / Structural and Mechanical Components

disciplines in this report). The acceptability of TVA's interim acceptance

criteria is still under review by the NRC's Office of Nuclear Reactor Regula-

tion. One day was spent at the Sequoyah plant site, where a walkdown of cable

tray and piping systems in containment was conducted.

On July 23, 1986, the NRR team members conducted a walkdown at the Sequoyah

Nuclear Plant. The team was aware of extensive reanalysis of small bore piping

systems currently underway at Sequoyah due to several substantive technical

issues identified by TVA in their SCR/NCR restart activities. Accordingly, the

j

purpose of the walkdown was to gain a better understanding of the technical

issues by viewing specific examples of those designs where the concerns are

evident. The team also observed HVAC support designs and typical duct span

lengths. The team walkdcwn primarily included areas inside reactor containment

"

i

and in the auxiliary building.

,

Four observations were identified in the licensing area relating to anchor

,

point movement loads, incorporation of 10 CFR 50 General Design Criteria (GDC)

requirements in TVA's design criteria and the results of the site walkdown of

>

cable tray, piping, and HVAC systems (Observations Nos. 8.1, 8.2, 8.3 and 8.4).

'

All observations stated below constitute open licensing issues that will be

,

independently resolved by NRR and the licensee. Consequently, these are

considered closed for the purpose of this inspection.

,

,

4

A-9

i

-n-

.

w..,-

- , ,, ,,

, , , , - - ~ ~

n,,----

- - , , . - - - - - - - - - - . - - . -

--,-,--,--..,,w.~,-

- , - - - - - -

- - - -

- - _ .

._

=_

.

.

-.

..

_

'

AttacNmentA-InspectionActivitiesandObservations

,

.

Observation No. 8.1 - Anchor Point Movement Loads

The team found that anchor point movement (APM) loads associated with a design

basis accident (double-ended guillotine break in the reactor coolant loop) were

!

included in the Watts Bar Design Criteria WB-DC-40.31.9 (previously used for,

the design of Sequoyah supports) but were not included in the new Sequoyah

Design Criteria SQN-DC-V-24.1. The licensee's response to the team's

observation was that DBA anchor point movement loads were not a licensing issue

!

at Sequoyah. Primary system movements at branch lines resulting from the~ DBA

loading were found to be less than 1/4 inch.

Because the APM results in a

secondary stress in the attached branch lines in a plant faulted condition, the

licensee concluded that the ASME Code does not require its evaluation.

4

'

According to the licensee, this was a Westinghouse-NRC negotiated position.

Furthermore, according to the licensee, this load case does not occur under the

Leak-Before-Break (LBB) position recently approved by the NRC.

Although secondary stresses in the piping due to plant faulted conditions (e.g.

SSE loading) are generally neglected because they are not expected to cause

'

gross structural failure due to local yielding and minor distortions in the '

,

pipe, the -licensee should provide the documentation of the basis for' concluding

that the anchor point movements associated with a DBA event are sufficiently

t

small to produce secondary, self-limiting type stresses. Under the Leak-

Before-Break position recently established by the NRC, the issue of anchor

point movement associated with a DBA becomes moot. However, the licensee must

ensure that the associated requirements established in the LBB position are

adequately implomented in its plant. The NRC office of Nuclear Reactor

Regulation sent a letter to TVA (S.A. White from J. Youngblood, dated September

29,1986), requesting additional information relating to the treatment of

anchor point movement loads for Sequoyah.

i

1

Observation No. 8.2 - Conformance to GDC for Containment Isolation

Appendix A to Design Criteria SQN-DC-V-2-15, " Containment Isolation System,"

,

'

states that the Sequoyah design was recently questioned by an NRC inspector who

cited the utility for noncompliance with the General Design Criteria (GDC).

Because the basis for the original design criteria for containment isolation

was AEC criterion 53, TVA referenced this in SQN-DC-V-2.15 and intends .to

remove the GDC reference in the Final Safety Analysis Report and replace it

j

with a reference to AEC Criterion 53. Since the Sequoyah operating license

application date (December 9,1973) falls more than six months after the

effective date of the GDC (May 21,1971), the plant must meet the GDC;

!

therefore, the licensee cannot change the references, but rather must demon-

l

strate compliance with the GDC.

Observation No. 8.3 - Cable Tray Systems

!

The following concerns were identified by the team relating to cable tray

support systems.

(1) Review of cross sections of cable trays identified cable masses outside

,

l

the trays.

Consideration should be given to securing the cables and to

-

evaluating resulting eccentricities. An example of this condition was

found in the plant at Elevation 714' and Coordinates A12S.

'

(2) A few locations in the cable tray systems appeared to contain large unsup-

ported spans. These locations were identified to technical personnel

A-10

- --- -

- -

. .

-

- - - -

- -

..-- - - - - ,

. _ - -

.

.

._

Attachment A - Inspection Activities and Observations

-

involved in the evaluation of these systems accompanying the team.

,

This situation was noted at elevation 714 and coordinates A1Q and A2Q,

at elevation 734 at unspecified coordinates, and at elevation 685 in the

auxiliary relay room.

(3) Cables were observed dropping from conduits and cable trays to other cable

trays in large bundles without significant support along the vertical drop

span. This was observed particularly in the cable spreading room, but

also at other locations'. TVA indicated this situation was being evaluated.

Results of the analytical and testing programs will be reviewed by the

NRC.

(4) Other concerns identified during the site visit were identified by TVA

personnel as currently being evaluated. These concerns include the

following:

Supports located near free edges and connections near edges of support

plates (Action Item 86-07).

Punch-shear problems between large vertical support tubes and lateral

support tubing.

Correction of weld connections between main and secondary structural

members.

.

(5) Various team discussions with TVA technical staff did not clarify how

TVA would assure that all employee concerns applicable to the interim

criteria would be evaluated.

l

The NRC Office of Nuc, lear Reactor Regulation is evaluating cable tray support

systems at Sequoyah.f A request for additional information was sent to TVA

(Mr. S.A. White from J. Youngblood, dated August 28,1986) on this subject.

Observation No. 8.4 - Piping and HVAC Systems

For small bore piping inside containment, the NRC observed several large,

extended motor-operators on valves which were unrestrained. These large

motor-operated valves were found to be extremely flexible and sensitive to

dynamic excitations. This generic issue was previously identified by TVA in a

recent SCR (SCRSQNCEB8614). TVA found that the effect of torsion due to

seismic acceleration of large eccentric masses (e.g., valve operators) was at

times neglected. The safety implications were that excessive pipe stresses and

pipe support loads could result. Additionally,~ excessive displacements could

potentially impair the operability of the valve and cause damage to adjacent,

sensitive equipment.

In 1979, a program for review of unsupported valve

operators resulted in the correction of several deficiencies in this area.

However, as-documented in the above noted SCR, some problems may still exist.

Motor-operated and pneumatic valves will be reviewed in the alternate program

and deficiencies will be evaluated and corrected.

The second issue observed by the NRC relates to non-seismic piping inside

containment. The team observed a large portion of a small bore piping system

which was not supported in the horizontal direction.

The licensee believed

the line to be non-seismic and, thus, should be addressed in the seismic (II/I)

interaction program. There currently appear to be at least two programs in

place at TVA which may address this potential issue.

A-11

,

.

- - _

__

_ _

,

Attachment A - Insp:ction Activities and Observations

Alternately analyzed Category I (L) type non-ANS safety class line (those

'

performing a secondary safety function) are being evaluated by the TVA

mechanical discipline through a contract with EQE Inc., which performs

walkdowns to assess the seismic integrity of the piping system.

Secondly, the staff is aware of a Sequoyah probabilistic seismicity

calculation (Analysis No. SQNNAL5-003) and an evaluation by Stevenson &

Associates which calculated the probability of a seismic event inducing a

failure in a non-seismically designed pipe.

This observation was identified to document and track resolution of these

~

issues. The NRC Office of Nuclear Reactor Regulation is evaluating TVA's

alternate analysis programs and interim acceptance criteria and will follow

resolution of these issues.

1

i

f

6

A-12

--.

.-_

__ ___

. _ _ , _ -

.- _ _ , _

1

,

Attichm:nt B - M:etings and References

.

.

1.

Meetings

~

Inspection activities were conducted at the DNE offices in Knoxville,

Tennessee.

Entrance and exit meetings were held to discuss the inspection

plans and findings, respectively.

The following describes the general purpose

of these meetings.

Table B.1 is provided as a matrix of meeting attendance and

principal persons contacted. Other licensee personnel were also contacted.

Meeting 1:

On July 21, 1986, an entrance meeting was held at the DNE offices

in~ Knoxville.

The NRC explained the plans for the assessment of TVA's program

for design criteria preparation and the associated Engineering Assurance

oversight.

Meeting 2: On July 25, 1986 an exit meeting was held at the DNE offices in

Knoxville. The scope and findings of the inspection were discussed.

The team

members presented the more significant findings within each discipline.

Table A.1 MEETINGS

Name

Organization

Title

Meeting Attended

1

2

REArchitzel

USNRC-IE

Team Leader

x

x

SVAthavale

USNRC-IE

NRC-Electric Power

x

x

PEHarmon

USNRC-RII

Resident Insp.,5QN

x

ADuBouchet

NRC-Consultant

NRC-Mech. Components

x

x

FJMollerus

NRC-Consultant

NRC-Mech. Systems

x

x

AIUnsal

NRC-Consultant

NRC-Civil / Structural

x

x

JMLeivo

NRC-Consultant

NRC-Nuclear System

x

x

LStanley

NRC-Consultant

NRC-Instr./ Controls

x

x

WCDrotleff

<TVA-DNE

Dir. DNE

x

x

JEHuston

TVA-DNQA

Dep. Dir. Nuc. QA

JFWeinhold

TVA-DNE

EA Manager

x

APCappozzi

TVA/S&W

Consultant - EA

x

x

MP8erardi

TVA-EA

EA Oversight Team Lead

x

x

AWLatti

TVA-DNE

Manager DBVP

x

x

RPSvarney

TVA-EA

Civil / Structural Engr.

x

x

APagano

TVA-EEB

EEB Asst. BC

x

JPLittle

TVA-MEB

Supervisor

x

JPDurnhan

Impell

Consultant

x

JFCox

TVA-DNE

Ast. PE SQEP-K

x

x

MJScruggs

TVA-DNE

Elec. Engineer SQEP-K

x

x

CFBowman

TVA-DNE

DPB Mgr.

x

JJSas

TVA-DNE

Dep. Director DNE

x

JARaulston

TVA-DNE

Chief Nuc. Engr.

x

FAKoontz

TVA-NEB

Gr. Head T/H & Plant Sup.x

CWParker

TVA-NEB

Nuc. Engr.

x

JJWilder

TVA-NEB

Nuc. Engr.

x

BHall

TVA

Licensing - Sequoyah

x

x

GRReed

TVA-DNE

Elec. Engr. - DBTF

x

RL0lberding

TVA-DNE

Mech. Engr.

x

RCWilliams

TVA

Reg. Rep.

x

DLWilliams

TVA

Nuc. Engr.

x

'

,

B-1

--

1

.

Atttchment B - Meetings and References

.

Table A.1 MEETINGS (cont.)

Name

Organization

Title

Meeting Attended

1

2

JWilliams

TVA

Staff Specialist

x

FRinaldi

NRC-NRR

Structural Engr.

x

x

DTerao

NRC-NRR

Mechanical Engr.

x

x

JHolonich

NRC-NRR

Project Mgr.

x

2.

REFERENCES

1.

TVA Calculation SQN-0567-048, Revision 1 dated 5/15/86,

" Identification of Systems Required for Restart."

" Design Ba~eline and Verification Program, Sequoyah Nuclear Plant,"

2.

s

Revision 0 dated 5/1/86.

3.

TVA Design Criteria SQN-DC-V-27.8 and " Status of C/R Review" for

" Neutron Monitoring System," transmitted by Westinghouse letter dated

7/16/86 to TVA for information and use; not yet issued by TVA.

4.

TVA Design Criteria SQN-DC-V-26.1 Revision 0 dated 7/11/86,

,

" Combustible Gas Control System."

5.

TVA Design Criteria SQN-DC-V-2.15 Revision 0, " Containment Isolation

System."

6.

TVA Design Criteria SQN-DC-2.16 Revision 0, " Single Failure."

7.

TVA Design Criteria SQN-DC-2.17 Revision 0, " Remote Shutdown Criteria

from Locations Outside the Main Control Room."

8.

TVA letter 11/2/84, Mills to NRR, topic:

Hydrogen Igniter Spray

Shield Design.

9.

Review Plan No. 4100R2, Tennessee Valley Authority, Sequoyah Nuclear

Plant, Engineering Assurance Oversight Review Plan, Mechanical,

July 23, 1986.

'

B-2

l

l

_

,

. _ _ _ .

..

_.

r-

_-

-

-

,

%%g

Mr. C. C. Mason

-4-

ggyg

i

Distribution (w/ encl)

DCS

PDR

'

LPDR

DQAVT Reading

QAB Reading

RArchitzel, IE

LSpessard, IE

EVImbro,-IE

HJMiller, IE

i

BKGrimes, IE

!

JMTaylor, IE

.

'

RWStarostecki, IE

,

HRDenton, NRR

.

GZech, RII

l

KBarr, RII

BBHayes, 01

BDebbs, RII

SRConnelly,-OIA

ELJordan, IE

i

JYoungblood, NRR

HThompson, NRR

,

l

DMuller, NRR

'

Inspection Team (8)

JHolonich, NRR

i

Resident Inspector

?

NSIC

j

Regional Administrator, RII

1

CRStahle, NRR

-

TMNovak, NRR

!

NTIS

i

ELD

I

OGC

i

i

!

I

j

D

S

Wh

l

IE:0QAVT:QAB

IE:0QAVT:QAB

IE:DQAVT:,QAB:C'

IE:

DD

j

REArchitzel

EVImbro

HMiller

ler

10/)//86,

10/q//86

10/11*/'/86

0/ ./86

,

j

Q

IE:h

$(.

IE:DD

I

1

s

'LSpsssard

RWStarostecki

JM aylor

j

Op/86

10/gf/86

10/9/86

b

10/) /86

,

i

i

I

_ - _ . _ . . _ .

. _ _ _ _ ~ . , ,

.. .__ _ _ _

.-_._ .._ .,___ _ . _ _,_, _ _ ,_._ . _ _.-_ ___- _ -._

.

Mr. C. C. Mason

-4-

g

g

Distribution (w/ encl)

DCS

PDR

,

LPDR

DQAVT Reading

QAB Reading

RArchitzel, IE

LSpessard, IE

EVImbro, IE

HJMiller, IE

BKGrimes, IE

JMTaylor, IE

RWStarostecki, IE

HRDenton, NRR

l

GZech, RII

KBarr, RII

l

BBHayes, 0I

___

(

BDebbs, RII

SRConnelly, 0IA

ELJordan, IE

JYoungblood, NRR

l

HThompson, NRR

!

DMuller, NRR

-'

,

Inspection Team (8)

-

.

-

JHolonich, NRR

Resident Inspector

-

NSIC

Regional Administrator, RII

CRStahle, NRR

TMNovak, NRR

NTIS

ELD

OGC

.-

WL -

?,t

IE:DQAVT:QAB

IE:DQAVT:QAB

IE:DQAVT:'QAB:C

IE:D

DD

REArchitzel

EVImbro

HMiller

H ' ler

lof//86

10A'q '/86

10/J/86

0/ /86

.

QAJ .D

IE:lig:D

$gb

g

IE:DD

I

'

s

LSpfssard

RWStarostecki

JM a lor

Ohg/86

10(gf/86

10/F/86

10/){86

__