Forwards Safety Insp Repts 50-282/87-03 & 50-306/87-03 on 870215-0418 & Notice of Violation.Response Requested Re Why Safeguard Logic Testing Procedures Not Changed More Expeditiously Following Two Previous Reactor Trips
ML20215L459
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 05/01/1987
From: Guldemond W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Larson C
NORTHERN STATES POWER CO.
Shared Package
ML20215L463 List:
References
NUDOCS 8705120254
Download: ML20215L459 (2)


See also: IR 05000282/1987003

Text

_ _ _ _ _ - - _ _ - _ - _ _ - _ - _ - _ _

h tn B

-

.:

p

fy 4

MAY 1 1987

Docket No. 50-282:

Docket No. 50-306

Northern States Power Company

. ATTN: Mr. C. : E. Larson

Vice President, Nuclear

Generation

'414 Nicollet Mall

Minneapolis, MN 55401

Gentlemen:

~

This refers to the routine safety inspection conducted by Messrs. J. E. Hard

and M. M. Moser of this office on February 15, through April 18, 1987, of

activities at the Prairie Island Nuclear Generating Plant, Units 1 and 2,

authorized by NRC Operating Licenses No.-DPR-42 and No. DPR-60 and to the

discussion of our findings with Mr. Watzl and other members of your staff

at the conclusion of the inspection.

The~ enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective ,

examination of procedures and representative records, observations, and

interviews with personnel.

During this inspection, certain of your activities appeared to be-in violation

with NRC requirements, as described in the enclosed notice. A written response

is required.. In addition, a written response is requested addressing why

safeguard logic testing procedures were not. changed more expeditiously following

the two previous reactor trips that had occurred within:one year during conduct-

of this testing.

In accordance with 10 CFR 2.790(a) of the Commission's regulations, a copy of

this letter and the enclosure will be placed in the NRC Public Document Room.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

OIUCINAL SICED BY W. G. CL'IEDOND

Q51%k

G

E5 2

W. G. Guldemond, Chief

ProjectsBranch-2

Enclosures:

1. Notice of Violation

2. Inspection Reports

No. 50-282/87003(DRP); and

No. 50-306/87003(DRP)

See Attached Distribution

RII RII

RI p R

'

[ ond

47

a Gu

up

/ -

n/n Ma d)

-

.

ix f'.

,

. Northern States' Power Company 2- MAY Y MI

'

( Distribution': -

'ccw/ enclosures':

'E. L. Watzl, Plant Manager

-DCS/RSB:(RIDS)1

Licensing' Fee Management-Branch'

' Resident Inspector,1RIII Prairie

' Island-

Resident-Inspector ~ RIII Monticello~

, ,

i.  : John W. Ferman, Ph.D. ,

"

1 Nuclear Engineer, MPCA

-

p

k

+

_.-+-,w. ~-.- , , ,--