Submits Results of Lll Exam of Facility Raceway Support Bolted Connections.Exams Conducted Due to Allegations Re Adequacy of Anchor Bolts & Feedback from Lll That Adequacy of Bolting Might Be Safety Issue
ML20215H922
Person / Time
Site: Diablo Canyon, 05000000
Issue date: 05/07/1987
From: Morrill P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
Shared Package
ML20213D283 List:
References
FOIA-84-21 NUDOCS 8705070149
Download: ML20215H922 (2)


Text

.-

=_.

o J.e}.. m.g'e

[

'f f,

UNITED STATES j.

NUCLEAR REGULATORY COMMISSION

{..

j REGION V 1480 MARIA LANE,sulTE 210 t,

,#g WALNUT CREEK. CALIFORNIA 94596 MEMORANDUM FOR:

T. W. Bishop, Director, Division of Resident, a

Reactor Projects and Engineering Programs i

THRU:

D. F. Kirsch, Chief, Reactor Projects 'Section No. 3 FROM:

P. J. Morrill, Reactor Inspector 1

SUBJECT:

INSPECTION RESULTS, LAWRENCE LIVERMORE NATIONAL 4

LABORATORY PERSONNEL EXAMINATION OF RACEWAY SUPPORT BOLTED CONNECTIONS AT DIABLO CANYON (DN 50-275 AND 50-323)

The purpose of this memorandum is to document the results of an examination of bolted connections of raceway supports at Diablo Canyon. This effort was conducted for two reasons; first, we have received allegations related to the l

adequcy of the anchor bolts which secure raceway supports to concerte (RV-83-A-033), and second, based on the feed-back I have been receiving from fL the Lawrence Livermore National Laboratory (contract) personnel, it appeared that adequacy of bolting of raceway supports might be a safety issue.

I requested the contract inspectors to tabulate and transmit to me the number of i

raceway supports examined, the number of bolts / nuts examined, and the number and type of deficiencies observed. This information was transmitted to me on November 8, 1983 and is current as of October 28, 1983.

i i

Raceway Supports Examined In Detail ---- 81 I

l Raceway Supports Partially Examined ---- estimated to be 200 to 300 Through Wall Anchor nuts / bolts ---- 10 to 20 examined:

One found deficient, item of non-compliance issued, licensee

' reinspected all similiar installations,10 out of several hundred j

(estimated) found lose and tightened.

Other Anchor nuts / bolts ---- 1,000 to 1,500 examined:

i Two were found loose, licensee tightened and documented with Minor Variation Reports (MVR)

Spring Nuts ---- 1,000 to 1,500 examined:

4 Four were found loose, licensee tightened and documented with NCRs j

1 8705070149 870505 PDR FOIA A

^

GARDE 84-21 PDR

{

/ S}

d',*-

I (u-1 o

T. W. Bishop 2-Conduit Nuts ---- 1,000 to 1,500 examined:

One was found loose, licensee tightened and documented with a MVR Lack of Thread Engagement ---- Several Thousand examined:

One lacked proper engagement, licensee corrected and documented with a MVR Based on this information, I recommend we continue to use our contract inspectors to examine raceway supports at the current level of effort. Should the licensee's deficiency rate decrease further however, I think we should examine some other area with potential problems.

I i

l W

l P. J. Morrill Reactor Inspector cc:

M. Mendonca, RV, Diablo Site l

G. Hernandez, RV W. Wade, EG&E, San Ramon i