Text
y
@d bk-OCT 011986
/ Georgia Power Company
/ ATTN: Mr. J. H. Miller, Jr.
President P. O. Box 4545 Atlanta, GA 30302 Gentlemen:
SUBJECT:
CONFIRMATION OF MEETING ARRANGEMENTS - V0GTLE - DOCKET N0. 50-424 This confirms the telephone conversation between Mr. C. W. Hayes of your staff and Mr. M. V. Sinkule of my staff on September 25, 1986, concerning a management meeting to be conducted at your Vogtle facility on October 29, 1986, at 9:00 a.m.
This meeting was requested by the NRC for management to review the status of construction and operational preparedness. A proposed meeting agenda is enclosed.
Should you have any questions regarding these arrangements, we will be pleased to discuss them with you.
Sincerely, h
M 0N QW Gt m J. Nelson Grace Regional Administrator
Enclosure:
Proposed Meeting Agenda
_ pc' w/ enc 1:
vJ. P. O'Reilly, Senior Vice President
/ Nuclear Operations VR. E. Conway, Senior Vice President &
j Project Director v D. O. Foster, Vice President, Project Support
/P. D. Rice, Vice President, Project
/ Engineering g/ R. H. Pinson, Vice President, Project
/. Construction J
T. Beckham, Vice President &
vd.GeneralManager-Operations A. Thomas, Vice President, flicensing
- 2. S. Read, General Manager,
/.QualityAssurance C
W. Hayes, Vogtle Quality Assurance Manager (cc w/enci cont'd - see page 2) 0 A
4r1 --
% c Ui
0CT 011986
-Georgia Power Company 2
(cc w/ enc 1 cont'd)'
A.C.Ramsey, Manager-Readiness Review A. B. Bockhold, General Manager, M.NuclearOperations Gucwa, Manager, Nuclear Safety and Licensing j M. H. Googe, Project Construction Manager
/E.D. Groover, Quality Assurance Site Manager -
Construction d.A. Bailey,ProjectLicensing Manager.
/G.F.Trowbridge,Esq.,Shaw, Pittman, Potts and Trowbridge
/B.W. Churchill,Esq.,Shaw, j Pittman, Potts and Trowbridge JE. L. Blake, Jr., Esq., Shaw,
./.Pittms.n, Potts and Trowbridge E. Joiner, Troutman, Sanders, j Lockerman and Ashmore (J. G. Ledbetter, Commissioner, Department of Human Resources
/C. H. Badger, Office of Planning y and Budget D. Kirkland, III, Counsel, Office of the Consumer's Utility Council
/D.Feig,GeorgiansAgainst Nuclear Energy vPf. B. Margulies, Esq., Chairman, Atomic Safety and Licensing Board
.t/dr.anel P
O. H. Paris, Administrative Judge Atomic Safety and Licensing Board Panel
- f. A. Linenberger, Jr., Administrative Judge Atomic Safety and Licensing Board Panel
. P. Garde, Citizens Clinic, Director Government Accountability Project
y DCT 011986
- Georgia Power Company 3
[ccw/ encl:
Y
. Reis, GS0
. M. Hill, IE
. Miller, NRR
. Brach, GS0
. /M. Sinkule, RII v4 Christnot, RII RC Resident Inspector Document Control Desk State of Georgia I
8 RII RII RII RI 4 VLBrfwnlee EChris@tnot:jw tut u
alker mgg MSinktn e 9/2y/86 9/jfj/86 9/d/86 9Df/86 ggy i
I
r; x>
ENCLOSURE PROPOSED MEETING AGENDA Georgia Power Company October 29, 1986, 9:00 a.m. - 4:00 p.m.
I. Opening Remarks, Introduction M. L. Ernst R. E. Conway II. Status of Construction R. Penson Construction Problems Physical interface with Unit 2 III. Operational Preparedness G. Bockhold Operations Staffing and Training Shared Systems (Ventilation, Radioactive Waste, etc.
Auxiliary Shutdown Panel Capability Ultimate Heat Sink Operating Procedures IV. Status of Licensing R. A. Thomas V. Plant Tour G. Bockhold Control Room Cable Spreading Rooms Interface Barriers Diesel Buildings Auxiliary Shutdown Panels Auxiliary and Control Buildings VI. Closing Remarks M. L. Ernst R. E. Conway t
!