,t SEP 2 41986 Docket No. 50-455 Corrmonwealth Edison Company ATTH: Mr. Cordell Reed Vice President Post Office Box 767 Chicago, IL 60690 Gentlemen:
SUBJECT:
EXAMINATION REPORT During the week of September 8,1986, the NRC administered examinations to employees of your company who had applied for licenses to operate your Byron Nuclear Power Station Unit Two. At the conclusion of the examination, any generic findings were discussed with those members of your staff identified in the enclosed report.
One major concern identified was the operating procedure for local control at the remote shutdown panel. There is no method within this procedure to allow for dealing with accidents. The details of this matter are discussed in the Report Details under the Exit Meeting section, paragraph 2.b.
In accordance with 10 CFR 2.790 of the Commissions regulations, a copy of this letter and the enclosure will be placed in the NRC Public Document Room.
Should you have any questions concerning this examination, please contact us.
Sincerely, EfE6afBrenedEyC.W.Eh1 Charles W. Hehl, Chief Operations Branch
Enclosure:
Examination Report No. 50-455/0L-86-03
_See Atta_ched Distribution RIII RIII RIII RIII Ydfp h
Reidinger/mab rdick Forney Heh' 09/24/86 14
%9, 8610100431 860924 I\\
DR ADOCK 0500 5
Corrrronwealth Edison Company 2
SEP 2 41996 Distribution cc w/ enclosure:
D. L. Farrar, Director i
of Nuclear Licensing i
V. I. Schlosser, Project Manager Gunner Sorensen, Site Project Superintendent R. E. Querio, Plant Manager T. K. Higgins, Plant Training Manager J. Hannon, Acting Branch Chief, OLB L. N. Olshan, Project Manager, NRR A. J. Vinnola, Contract Exam Supervisor, INEL DCS/RSB (RIDS)
Licensing Fee Management Branch Resident Inspector, RIII Byron Resident Inspector, RIII Braidwood Phyllis Dunton, Attorney General's Office, Environmental Control Division D. W. Cassel, Jr., Esq.
Diane Chavez, DAARE/ SAFE Steve Lewis, ELD l1. S. Taylor, Quality Assurance Division L.