Informs That Rev 6 to Licensed Operator Requalification Training Program Acceptable for Use Until Revs Made in Accordance W/Amended Regulations,Per Generic Ltr 87-07, Licensee 860904 & 870424 Submittals & 870501 Meeting W/Nrc
ML20215A986
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 06/09/1987
From: Kintner L
Office of Nuclear Reactor Regulation
To: Kingsley O
SYSTEM ENERGY RESOURCES, INC.
References
GL-87-07, GL-87-7, TAC-62717, NUDOCS 8706170172
Download: ML20215A986 (3)


Text

~

l

. June 9 - 1987..

N

' Docket No. 50-416 DISTRIBUTION w

Local PDR-

.ACRS (10)

'Mr. Oliver D. ' Kingsley, Jr.

PD22 Rdg.-

. Gray File Vice' President Nuclear Operations S.'Varga

-System Energy Resourcas; Inc.

G. Lainas P. 0.: Box 23054' L. Kintner i

Jackson, Mississippi -39205 D. Miller-OGC-Bethesda

Dear Mr. Kingsley:

SUBJECT:

GRAND GULF. NUCLEAR STATION, UNIT'l - LICENSED OPERATOR

.REQUALIFICATION TRAINING PROGRAM q

1 By letter dated September 4,1986, the licensee (Mississippi Power & Light Compan 20,- 1986 and System Energy Resources, Inc. after that-

' time) y prior to December submitted Revision 5 to the Grand Gulf Nuclear Station Unit l'(GGNS-1)'

il Licensed Operator Requalification Program. Revision 5 to the program incorporated,

changes' responsive to NRC staff's letter dated November 27, 1985 regarding Revision 4: to the program.- By letter dated April. 24, 1987,'the. licensee

.l informed the staff that. Revision 6 to the GGNS-1 Licensed 0perator Training 1

s Program l incorporated NRC staff recommendations regarding Revision 5 to;the-J

. program.

In the March 19,_1987 Generic Letter No.-87-07, "Information of Fina1'Rulemaking-to Operator Licensing - 10 CFR 55 and Conforming Amendments" all facility.'

licensees were infomed of a series of public regional meetings and 'a' subsequent:

NUREG to be' published after the completion of-the~ meetings.GGNS training

. staff attended meetings held on April 9,1987. In the-April 24, 1987, letter the licensee stated that. revisions to the requalification program will be made

.in accordance with the revised regulations and subsequent guidance as a result of the regional meetings. The revised regulations were published in the.

Federal Register'on March 25, 1987 (52 FR 9453) and became effective on:May 26,'

1987.

The NRC staff has reviewed the licensee's September 4,1986 and April 24,.

1987.submittals.

In addition, the staff has discussed the' requalification training program with the licensee in a. meeting on May 1, 1987.- Based on its-review, the staff concludes that Revision 6 to the requalification training.

. program is acceptable for use until revisions are made in accordance with the-amended regulations. Generic Letter 87-07 contains.an option whereby the

'B706170172 B70609 PDR ADOCK 05000416 ;

V PDR

Mr. Oliver D. Kingsley, Jr. revised recualification program need not be submitted for NRC staff review, provided the program is both accredited and is based on a systems approach to training. Additional guidance will be provided in NUREG-1262 as a result of the public meetings on the amended regulations.

Sincerely, Lester L. Kintner, Project Manager Project Directorate 11-2 Division of Reactor Projects-I/II cc: See next page i

t i

{

i L

P D22 P:

J LKin y,y,tner:bg s,e an,e7 ub s,enstein e,,,e7 ez e7 l

J l

l 4

Mr. Oliver D. Kingsley, Jr.

b System Energy Resources, Inc.

Grand Gulf Nuclear Station (GGNS)

CC*

Mr. Ted H. Cloninger Mr. C. R. Hutchinson Vice President, Nuclear Engineering GGNS General Manager and Support System Energy Resources Inc.

System Energy Resources, Inc.

Post Office Box 756 Post Office Box 23054 Port Gibson, Mississippi 39150 Jackson, Mississippi 39205 Robert B. McGehee, Esquire The Honorable William J. Guste, Jr.

Wise, Carter, Child, Steen and Caraway Attorney General P.O. Box 651 Department of Justice Jackson, Mississippi 39205 State of Louisiana Nicholas S. Reynolds, Escuire Bishop, Liberman, Cook, Purcell Office of the Governor and Reynolds State of Mississippi 1200 17th Street, N.W.

Jackson, Mississippi 39201 Washington, D. C.

20036 Attorney General Mr. Ralph T. Lally Gartin Building Manager of Quality Assurance Jackson, Mississippi 39205 i

Middle South Utilities System Services, Inc.

P.O. Box 61000 Mr. Jack McMillen, Director New Orleans, Louisiana 70161-Division of Solid Waste Management J

Mississippi Department of Natural i

Mr. John G. Cesare Resources Director, Nuclear Licensing and Safety Bureau of Pollution Control System Energy Resources, Inc.

Post Office Box 10385 P.O. Box 23054 Jackson, Mississippi 39209 j

Jackson, Mississippi 39205 l

Alton B. Cobb, M.D.

i Mr. R. W. Jackson, Project Engineer State Health Officer Bechtel Power Corporation State Board of Health 15740 Shady Grove Road P.O. Box 1700 Gaithersburg, Maryland 20877-1454 Jackson, Mississippi 39205 Mr. Ross L. Butcher President Senior Resident Inspector Claiborne County Board of Supervisors U.S. Nuclear Pegulatory Comission Port Gibson, Mississippi 39150 Route 2, Box 399 Port Gibson, Mississippi 39150 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W., Suite 2900 Atlanta, Georgia 30323 Mr. James E. Cross l

GGNS Site Director System Energy Resources, Inc.

P.O. Box 756 Port Gibson, Mississippi 39150