q
.
i,
no af ^
unstT E2 5T ATES
/
'
NUCLEAR REGULATORY COMMISSION
O'
'
REGION li
f
101 MARtETTA STREET, N W
'
g
ATL ANTA. GEORGI A 30323
f
s.,
v
- .. *
October 30, 1986
MEMORANDUM FOR:
Gary G. Zech, Director
Division of TVA Projects
FROM:
Caudle A. Julian, Chief
Operations Branch
Division of Reactor Safety
SUBJECT:
SER INPUT FOR SEQUOYAH RESTART - MAINTENANCE
Enclosed is the updated maintenance safety evaluation report (SER) input
supported by maintenance inspections documented in NRC Inspection Report
Nos. 50-327, 328/85-45, 50-327, 328/86-18, and 50-327, 328/86-48. This SER
provides our evaluation and conclusions regarding the comitments included in
the Revised Sequoyah Nuclear Performance Plan, Section 11.4.0, dated July 17,
1986. The enclosed SER input replaces in its entirety our previous maintenance
SER input dated August 7, 1986. Note that there are follow-up items that will
be resolved by Region II during inspections prior to startup of the Sequoyah
units.
~
9
Caudie A. Julian
Enclosure:
Sequoyah SER Maintenance Input
cc w/ encl:
A. F. Gibson
B. A. Wilson
R. E. Carroll
g21gQ h
(
O