APPENDIX A NOTICE OF DEVIATION

- Duquesne Light Company Docket No. 50-412 Beaver Valley Power Station Unit 2 License No. CPPR 105 As a -result of the ir:spection conducted on October 20-24, 1986, the following deviation from. a commitment to the NRC. contained in the Beaver Valley Power Station Unit 2 FSAR, was identified.

FSAR . paragraph 14.2.12.15.1, entitled " Recirculation Spray System Pumps and Controls Test," states under " Test Methods," item 3, that "Available ' net positive suction head will be determined."

Contrary to the above, as of October 24, 1986, preoperational test procedure P0 2-13.01, " Recirculation Spray System Pumps and Controls," does not determine available net positive suction head.

Duquesne Light ' Company is' hereby requested to submit to this office within thirty days of the date of the letter which transmitted this Notice, a written statement or explanation in reply including: (1) the corrective steps which have been taken and the results achieved; (2) corrective steps which will be '

taken to avoid further deviations; and (3) the date when full compliance will be achieved.

8612090136 861128 2 DR ADOCK 0500 OFFICIAL RECORD COPY IR BV2 86 0003.0.0 11/06/86

'