ML20214P485

From kanterella
Jump to navigation Jump to search
Safety Insp Rept 50-289/86-12 on 860711-0814.Violation Noted:Improper Implementation of Mod Control Instructions/ Procedures & Conditions Adverse to Quality Not Promptly Corrected
ML20214P485
Person / Time
Site: Crane Constellation icon.png
Issue date: 09/03/1986
From: Blough A, Conte R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20214P480 List:
References
50-289-86-12, NUDOCS 8609230119
Download: ML20214P485 (19)


See also: IR 05000289/1986012

Text

, .

.

.a

.

, . -

.

..

e

'U.S. NUCLEAR REGULATORY COMMISSION-

REGION I

Report No.

50-289/86-12

. Docket No.

5'0-289

-

License No.

DPR-50

Priority --

Category C

Licensee:

GPU Nuclear Corporation

Post Office Box 480

Middletown, Pennsylvania 17057~

Facility At:

Three Mile Island Nuclear Stetion, Unit 1

. Inspection At:

Middletown, Pennsylvania

Inspection Conducted:

July 7 - 11 and August-14, 1986

Inspectors:

W. Baunack, Project Engineer

R. Conte, Senior Resident Inspector (TMI-1)

Reporting Inspector:

M

'7-Mcf(

f

R. Conte,' Senior- Resident- Inspector (TMI-1)

Date

Approved By:

7-3-d

'

A. BlostJh, Chief

Date

Reactor Projects Section No. IA

Division of Reactor Projects

Inspection Summary:

This was a special safety inspection based primarily on the performance

Appraisal Team findings (NRC Inspection Report No. 50-289/86-03).

It involved

54 inspection hours. Additional limited inspections of the licensee's modifi-

cation control procedures were' conducted to identify more specifically the

licensee procedures that implement NRC requirements applicable to PAT findings.

Inspection Results:

Four-violations, each with multiple examples, were identified. The four

applicable NRC requirements were for:

the conduct of safety evaluations in

accordance with 10 CFR 50.59 (paragraph 2); proper implementation of design

control requirements in accordance with ANSI 45.2.11-1974 (paragraph 3); proper

implementation modification control instructions / procedures (paragraphs 4 and

5); and, prompt corrective action on known conditions adverse to quality

(paragraph 6),

h

G

.

_.

-

-

.

.-

.

. . _ . . ._ .

. _- . _

.

.

.

.

2

,

.

J

Based on the modification control problems noted, NRC concerns were raised on

the adequacy of other modifications that have been developed under the same

licensee process, such as the emergency feedwater system modifications to be

installed in the upcoming refueling outage. This will require additional

licensee and NRC review prior to Cycle 6 startup, scheduled for April 1,1987.

l

,

4

i

f

&

.

$

t

.

.

1

i

i

!

.

k

5

--

- . , , - - , . -

,,,,,,,,-..,,_---n,

n.--,-

n,,.

.7m.-,.,

- , , , - . , . , - . ,,__.-

,,,-.w..r.

_,.

,,_

,

.-_-.,----_n

= _ , - ,

- _ _ - _ - _ - _

-

.

-

,.

.

4

DETAILS

- 1.

Introduction and Overview

i

The purpose of this inspection was to review the NRC Performance

Appraisal Team (PAT) inspection (Report No. 50-289/86-03) findings to

(1) determine which findings were examples of violations of NRC

requirements, and (2) itemize and, in some cases, clarify other items

requiring additional followup. The basis for this review was primarily

the objective findings of the PAT inspection as documented in the subject

report. However, a limited review of licensee procedures was conducted to

i

further identify procedures that implement the applicable NRC requirements.-

'

.The findings of PAT were grouped into four categories:

acceptable

items or positive comments for information only; unresolved items

(defined in paragraph 10); inspector follow items (defined in paragraph

10); and, other' findings not specifically numbered. The latter three

categories were independently reviewed by the Region I inspectors to

identify violations of NRC requirements. By its purpose, this inspection

necessarily focuses on the negative aspects of PAT findings and does not

revisit the positive findings.

.This report dispositions most of the PAT findings; these dispositions are

summarized in Attachment I to this report. Also, certain PAT observations

(not specifically numbered in the PAT report) were considered by Region I ,

to be issues warranting additional information to determine acceptability.

Accordingly, these are identified in this report as new unresolved items.

Certain PAT unresolved items involve multiple issues; these individual

issues are redesignated by this report to facilitate individual followup.

Some PAT findings retained their status (and numbering) since this review

identified no new information to update the items; these items also are

evident in Attachment 1.

2.

Safety Evaluation Implementation

i

2.1 Introduction

The Performance Appraisal Team (PAT) inspection identified a number

of examples in which design change safety evaluations were not

thorough enough to assure proper implementation of safety grade

criteria as reflected in the updated safety analysis report (SAR).

The 10 CFR 50.59(b) requires, in part, the licensee to perform a

written safety evaluation to assure that changes in the facility as

described in the SAR do not involve an unreviewed safety question

(defined by 10 CFR 50.59a(2)). To implement this requirement, the

licensee has Technical Functions (TF) Engineering Procedure

(EP)-016. Revision 1-00, dated January 18, 1985, " Nuclear Safety /

Environmental Impact Evaluation." In Exhibit 3, EP-016, paragraph

3.3 requires, in part, that the written safety evaluation for

facility changes describe how the proposed change will or will not

_ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _

'

.

-

, . .

4

...

,

.

affect the. safety function (10 CFR 50 Appendix A Criterion 34) by

addressing: system. performance (paragraph 3.3.1); natural phenomena

with respect to seismic classification (paragraph 3.3.3);. electrical

isolation criteria (paragraph 3.3.9); and, single failure criteria

(paragraph 3.3.11). Specific examples of ifcensee failure to meet

these requirements from the PAT report are addressed in paragraphs

2.2, 2.3, and 2.5 below.

The 10 CFR 50.59(b) also requires that a similar review be completed

for change to procedures as addressed in SAR. To implement this

requirement, the licensee has Administrative Procedure (AP) 1001A,

Revision 10, dated April 17, 1986, " Procedure Review and Approval."

Figure AP 1001A-5, paragraph'2, implements that' requirement to

identify whether or not a procedure change constitutes an unreviewed

safety question. A specific example of licensee failure to meet

these requirements is addressed in paragraph 2.5 below.

2.2 (Closed) Unresolved Item 289/86-03-09):

Inadequate Control

of lead shielding installation.

Paragraph III.A.3.a (1) of the PAT report identified that lead

shielding was installed on important to safety systems without a 10 CFR 50.59 evaluation.

Further, the technical evaluations for

installed lead shielding did not fully address piping system perfor-

mance under dynamic loads along with assuring adequate protection for

a seismic event. This failure to fully evaluate the installation of

lead shielding is example of apparent violation of 10 CFR 50.59(b)

,

and EP-016, Exhibit 3, paragraphs 3.3.1 and 3.3.3.

2.3. (Closed) Unresolved Item 289/86-03-01: Two-Hour Backup Instrument ~

Air System did not meet safety grade single failure criteria.

Paragraph III.A.1.a of the PAT report described a design basis

single failure susceptibility of the Two-Hour Backup Instrument Air

(TBIA) sub-system for the Emergency Feedwater (EFW) system at supply

i

lines for MS-V-6, pressure regulator for the inlet to the turbine-

driven EFW pump. The TBIA was a safety grade restart modification.

Although the licensee completed a 10 CFR 50.59 evaluation, licensee

personnel did not identify the single failure susceptibility until

identified by PAT inspectors. Accordingly, this failure to identify

the single failure susceptibility of the EFW TBIA is another example

of an apparent violation of 10 CFR 50.59 and EP-016, Exhibit 3, para-

graph 3.3.11.

Licensee immediate corrective actions were to report the item in

accordance with 10 CFR 50.72 and 50.73 (See Licensee Event Report

86-07), along with shutting IA-V1450 and IA-V1459 manual isolation

valves upstream of the subject check valves to preclude the single

failure susceptibility.

.

-

..

5

-.

.

2.4 (Closed) Unresolved Item 289/86-03-06: _ Remote Shutdown Panel EFW

Instrumentation not electrically isolated from control room panels.

Paragraph III.A.2.b(1) identified that the safety grade steam

generator (digital) level display at the remote shutdown panel (RSP)

was not electrically isolated from the control panels with respect

to power supplies. The PAT report focussed on compliance with 10 CFR 50 Appendix R electrical isolation requirement.. However,

commitments were also made by the licensee for restart (as reflected

in updated SAR section 7.3.2.2.b(8)) that the RSP steam generator

level instrumentation would be (electrically) isolated from control

room panels.

Paragraph III.A.2.b(2) of the PAT report also identified that the

power supply for. safety grade containment water level instrumen-

tation outside the control room location (local panel) were not

electrically isolated from the control room panels. The updated SAR

section 7.3.1.1.c(11)(b) states, in part,'that the containment water

level instrument output signal condition cabinet (and local panels)

are isolated from control room panels.

The electrical isolation findings noted above would be significant

if the control room indicator were not seismically qualified, that-

is, a failure of the indicator due to a seismic event could effect A,'

i.

,

the entire safety grade instrument loop. The licensee reports that

these indicators were seismically qualified. This is unresolved

pending Region I review of the licensee qualification data / analysis

for these instruments.

(289-86-12-17)

,

2.5 (Closed) Unresolved Item 289/86-03-24: Adequacy of EFW pump

surveillance testing.

Paragraph III.D.1.b of the PAT report identi-

fled that the appropriate surveillance test for EFW pump testing was

inconsistent with the applicable section of the SAR. The SAR section

10.8.2.2.f states, in part, that the flow test to demonstrate feeding

the steam generator would be done using normal alignment. However,

surveillance procedure (SP) 1303-11.42, Revision 6, dated June 26,

1986, " Emergency Feedwater Flow Test from Condensate Storage Tank,"

requires ~that respective cross-connect valves, "EF-V2A and B" be

closed during the test which is contrary to the normal alignment of

being open. The revised test lineup precluded the ability of the

test to detect excessive backflow through discharge check valves of

idle EFW Pumps. With excessive backflow, the consequences of a

loss-of-feedwater transient could be worsened.

Apparently, previous safety evaluations did not address the test

alignment inconsistency with the SAR commitment. The failure to

identify this inconsistency is an apparent violation of 10 CFR 50.59(b) and AP 1001A, Figure AP 1001A-5.

Paragraph III.D.1.a of the PAT report also addresses a concern that

the monthly surveillance test of EFW pump (SP 1300-3G A/8, Revision

21) creates an artificial initial condition by operators blowing

I

-

-

..

6

.

.

down steam traps before the test of the turbine-driven pump.

In

their response letter, dated June 27, 1986, to the PAT report, the

licensee indicated that they had performed a test to confirm that the

blowdown was not an artificial condition.

This area remains unre-

solved pending additional Region I review of the licensee's evalua-

tion of the above-noted test data (289/86-12-01).

2.6 Conclusion

The failures (see paragraphs 2.2, 2.3 and 2.5 above) to properly

evaluate facility changes and procedure changes to assure consistency

with SAR commitments (no unreviewed safety question) constitute an

apparent violation of 10 CFR 50.59b.

(289/86-12-02)

3.

Design Control Implementation

3.1

Introduction

During their review of modifications, the PAT inspection identified

certain problems in the areas of adequacy of design inputs, control

of design inputs, implementation of the design verification process,

and post-modification testing.

These problems were, in general,

identified as violations of ANSI N45.2.11 and in some instances

were noted as being contrary to facility procedures.

Specific examples associated with this apparent violation are as

follows.

3.2 Review,-Approval and Basis for Design Input

3.2.1

EFW Air Bottle Sizing

As part of unresolved item 289/86-03-05, the PAT Inspection

Report paragraph III.A.1.e.(1), noted that the calculation

which determined the minimum allowable manifold pressure of

the two-hour backup instrument air system needed to maintain

an adequate stored air capacity was based on inappropriate

system leak tests.

The licensee provided documentation which indicated that

Calculation No. 1101-852-5360-001 dated July 21, 1983 was

based on appropriately reviewed test procedures and test

results (SP 250/3.1, test results reviewed May 12,1983).

This aspect of the item is considered closed.

The PAT inspector apparently was not aware of the May 1983

test and believed the licensee had used November 1982 data

which was unacceptable.

Adequacy of testing is still unresolved, tracked by a

later item (see paragraph 7.2).

.

-

,.

7

.

.

3.2.2

Battery Sizing

As part of unresolved item 289/86-03-05, the PAT Inspec-

tion Report 50-289/86-03 paragraph,III.A.2.a.(2),noted

a weakness in the design input associated with battery

sizing. The team reviewed the latest sizing calculation

for the new battery to be installed during the March /

April 1986 outage and determined that the battery was

sized based upon a minimum battery temperature of 72 F.

No reference was included in the calculation for the

basis of this minimum temperature. Actual battery tem-

peratures recorded were found to be lower than the 72 F

minimum temperature assumed. The team also found that

other design input data used in the calculation, such as

pump and valve starting and running currents, lacked

sufficient references to permit complete verification of

the calculations. This lack of control of design inputs

is contrary to the requirements of ANSI N45.2.11, paragraph

3.1.

3.2.3

DC Distribution Fuse Sizing

As part of unresolved item 289/86-03-05, the PAT

Inspection Report, paragraph III.A.2.a.(4), noted the use

of prelimir.ary, unverified design input as a basis for fuse

changes in de system power distribution panels. The use of,

preliminary, unverified design input is contrary to the

requirements of ANSI N45.2.11, paragraph 3.1.

3.3 Vendor Design Interface

As part of unresolved item 289/86-03-05, the PAT Inspection Report

paragraph III.A.I.e.(2), noted the design input associated with

sizing of air regulating valves was provided by GPU to an architect

engineer but was subsequently changed by the licensee without

notifying the affected design organization,

i.e., the architect

engineer. This failure to control interfaces between organizations

.

is an example of an apparent violation of ANSI N45.2.11, paragraph

5.1.3.

3.4 Design Verification

3.4.1

(Closed) Unresolved Item 289/86-03-02:

EFW Two-Hour

Backup Instrument Air Modification Testing. The PAT

Inspection Report 50-289/86-03, paragraph III.A.I.c,

discussed problems with the post-modification functional

testing of the two-hour backup supply air system.

The

system is designed to supply bottled air for a minimum of

two hours following the loss of normal and backup instru-

ment air systems. The team found the post-modification

testing was not structured to confirm that the design basis

.-

-

.

- - -

-

-

.

. _ -

--

-

. - _ .

-

_-

.

-

.-

8

.

.

for the system been satisfied.

Specifically, the team

determined the test did not confirm that the system was

adequately sized to supply sufficient air to cycle all

associated valves twenty times as specified in the design

or to observe a minimum of ten strokes per valve as

required by the System Design Description (SDD). The

failure to implement a test procedure, which verified that

the modification was capable to perform its intended func-

tion, is an example of an apparent violation of the

requirements of ANSI N45.2.11, paragraph 6.3, and Techni-

cal Functions Procedure 5000-ADM-7335.01, "Startup and

Test Program and Test Requirements."

3.4.2

(Closed) Unresolved Item 289/86-03-09 (Part): Design

Verification on Lead Shielding. The PAT Inspection Report

50-289/86-03, paragraph III.A.3.a.(4), noted calculations

to support lead shielding installations were not verified

in a timely manner. There had been approximately ten

shielding calculations accomplished and only one had been

verified prior to the installation of the shielding. The

failure to accomplish design verifications prior to the

installation of the design is an example of an apparent

violation of the requirements of ANSI N45.2.11, para-

graph 6.1.

3.4.3

(Closed) Unresolved Item 289/86-03-11): Design

Verification for Various Modifications.

The PAT Inspec-

tion Report 50-289/86-03, paragraphsIII.A.3.c.(1),(2),

and (3), discussed certain deficiencies associated with

the design verification process as follows:

3.4.3.1

III.A.3.c.(1): This paragraph identified three

engineering calculations, Calculation No. 1101X-322F-165 -

Flow Rates for Two-Hour Backup Air Supply System; Calcula-

tion No. 1101X-322F-424-1 - EFW System Resistance; and

Calculation No. 1302X-5320-A50 - Shielding stress, which

had no design verification accomplished.

3.4.3.2

III.A.3.c.(2):

This paragraph identified three design

verifications, Calculation No.1101X-3228-003 - Air

Consumption by EF-V-30 Valves; Calculation No.

1101X-322F-157 - EFW Pump Turbine Relief Valve Setpoint;

and Calculation No.1101X-322B-004 - Air consumption by

MS-V-6, which did not have required verification check-

lists prepared.

3.4.3.3

III.A.3.c.(3): This paragraph identified System Design

Descriptions (SDDs), which had not been design verified.

The SDDs, which were not verified were SDDs 424A, B, C,

D, and E, Division I and II, involving the EFW system,

its backup instrument air supply, and supporting

. -

'

p

r.

.

V

...

[.l1

9-

,

,,

L

F

instrumentation. The team; following a review of an

additional Technical Functions Procedure,.a visit to the

licensee's architect engineer's offices, and discussions

with Itcensee personnel; verified that SDDs were considered

i

design inputs and, as such, required verification.-

3.4.4

The above (paragraphs 3.4.1, 3.4.2,'and'3.4.3) are con-

sidered to be examples of the f,ailure to adhere to the

ANSI N45.2.11 design verification requirements, which are

o

reflected in' Technical Functions Procedure 5000-ADM-

L

7311.02, " Design Verification."

3.5 Conclusion

The above.'noted failures to properly implement ANSI 45.2.11 are

examples of an apparent violation of 10 CFR 50 Appendix B and QAP

Appendix C (289/86-12-03).

The number of items identified raises questions as to whether the

problems are as a result of-procedures associated with facility

modifications not being sufficiently' clear to assure that the

requirements of ANSI N45.2.11 are incorporated in modification

packages or whether or not personnel are attentive to procedural

'

requirements. During the review, the inspector noted that many

Technical Functions procedures do not provide information as to what

sections of ANSI 45.2.11 or other sections of the ANSI 45.2 series

documents were being satisfied by the specific procedure. Thus, the

correlation between ANSI 45.2 series requirements is not always

clear. This area will continue to be reviewed by Region I and is

considered to be unresolved (289/86-12-04).

4.

Minor Modification Program Implementation

4.1

Introduction

During their design change program review, the PAT inspection

evaluated in detail the mini-mod process described in procedure

5000-ADM-7350.05, " Mini-Mods." Also, four specific mini-mods were

reviewed. The four mini-mod work packages were evaluated for

procedure compliance as well as appropriate design change control

requirements.

l

The team found the basic program and control of mini-mods to be

adequate. However, two types of procedural implementation problems

were noted. The first dealt with the failure to recognize that the

modifications affected the FSAR descriptions and the second identi-

fled the failure to address all the attributes which the mini-mod

procedure required to be addressed. These identified procedural

violations indicate that, even though good overall procedures

covering mini-mods have been prepared additional attention is

,

needed to assure that procedures are adhered to.

The specific items

identified are described as follows.

.

.-

10

.-

.

4.2 (Closed) Unresolved 289/86-03-10:

Improper Implementation of the

Minor Modification Program. The PAT Inspection Report 50-289/86-03,

paragraphs III.A.3.b.(1) and (2), documented certain minor modifica-

tion (" Mini-Mod") procedural implementation problems as follows.

4.2.1

III.A.3.b.(1):

This paragraph documented two instances in

which 10 CFR 50.59 evaluations for two mini-mods (addi-

tional limit switches for the fuel handling crane and

removal of instrument air lines for EFW pumps recircula-

tion valves) were incorrectly marked as no change being

required to the FSAR when, in fact, changes to the FSAR

were required.

4.2.2

III.A.3.b.(2):

This paragraph documented that none of

the four mini-mods reviewed in the PAT report addressed

all the design information which was required to be

addressed by Technical Functions Procedure 5000-ADM-7350.05

(EMP-002), Revision 0-00, dated September 3, 1985,

"Mi n i-Mod s. " The team considered that all the attributes

required to be addressed by the procedure were relevant and

should be part of the modification documentation.

4.3 Conclusion

The Code of Federal Regulations,10 CFR 50, Appendix B Criterion V

requires that activities affecting quality shall be prescribed by

instructions, procedures or drawings and shall be accomplished in

accordance with those procedures, instructions or drawings.

The failure to adhere to the requirements of Procedure 5000-ADM-

7350.05 is an example of violation of 10 CFR 50 Appendix B

Criterion V.

(289/86-12-04) (see also below)

5.

Modification Installation Procedure Implementation

,

5.1 Introduction

The PAT team inspected design aspects of certain restart modifica-

tions. As a result of this review, two instances were identified in

which the actual installation of the modifications differed from the

intended design.

These team findings show a need for establishing

or implementing procedures which will assure that modifications are

installed as intended, because an otherwise adequate design can be

voided by improper installation.

The specifics associated with the team findings are described below.

- -

.

- -

-

i

.

-

..

11

.

.

5.2 (Closed) Unresolved Items 289/86-03-03 and 289/86-03-09:

Improper Installation of Modifications.

The PAT Inspection Report

50-289/86-03, paragraph III.A.1.d and III.A 3.a.(5), identified

certain problems with the installation of modifications. The

problems were noted with the installation of the air cylinders for

the two-hour backup supply air system and the installation of

permanent shielding to shield drain lines for the letdown

prefilters. Two specific problems were noted as follows,

5.I.]

III.A.I.d: Calculation 609-0293, Revision 0, " Bottle Rack

.

for RM-13h," (EFW Two-Hour Backup Instrument Air (TBIA)

'

,

Subsystem) provided the rack design for restraint of air

cylinders for the two-hour backup supply air system during

a seismic event.

Inspection of the installation by the

team revealed that no turnbuckles were installed,'the chain

restraints were loose,

"S" links were not closed, and eye

bolts were not securely fastened to the frame; which was

contrary to instructions contained in the design calcula-

tion 609-0293.

5.2.3

III.A.3.a.(5): The installation criteria established by

the licensee for the installation of shield blocks to

shield letdown prefilters (MU-F-2A and 28) was that the

center of gravity of the top blocks be no more than 12

inches off the floor, the blocks be no closer than 2 feet

to important-to-safety (ITS) equipment due to seismic

,

considerations, and that a warning sign be installed

identifying the 2-foot requirement. Site inspection of

the as-installed blocks by the team revealed that (1) the

top block center of gravity was 15 inches off the floor in

some locations, (2) ITS valves SF-V-77 and SF-V-71 were

located within 6 inches and 19 inches of the blocks,

respectively, and (3) no warning sign was installed.

This was contrary to the installation procedure for this

modification.

5.3 Conclusion

The failures to make installation of modifications in accordance with

prescribed instructions or procedures is another example of violation

of 10 CFR 50 Appendix B Criterion V.

(289/86-12-04)

6.

Corrective Action Implementation

6.1 Introduction

A number of items raised in the PAT report were repetitive of issues

previously brought to the licensee's attention based on past inspec-

tions.

Specifically, outstanding issues at TMI-1 have been:

improper implementation of administrative control for correcting

out-of-specification log readings and lack of proper control of

- -

.

.

-

. . .

12

.

design documents, such as drawings. The 10 CFR 50 Appendix B

Criterion XVI and the NRC-approved QA plan, sections 8.1.1 and 8.2.1

require, in part, that the licensee assure conditions adverse to

quality; such as, deficiencies, deviations and nonconformances, are

promptly corrected.

Specific examples of delayed and/or ineffective

corrective actions are noted below.

6.2 (0 pen) Inspector Follow Item 289/86-03-04:

Component Level

Quality Control List. Paragraphs III.A.1.f(1) and (2) identified

the various sub-systems of EFW system had different quality classi-

fication. The licensee Quality Control List (QCL) (ES-011) provides

for three basic classifications (nuclear safety related, important

to safety, and not important to safety). The QCL did not break down

the classification into component levels. The 10 CFR 50 Appendix B

Criterion II requires, in part, that the licensee identify struc-

tures, systems, and components to be covered by the quality assur-

ance program. Based on the licensee's response letter, dated

June 27, 1986, to the PAT report, the component level QCL is to be

issued by the end of 1986.

In view of the licensee's updated commitment to correct this item by

the end of 1986, the issuance of an adequate component level QCL is

,

unresolved pending completion of this licensee action and Region I

review-(289/86-12-06).

'

The PAT report also noted that the lack of identification on the QCL

of the safety grade Two-Hour Backup Instrument Air (TBIA) system.

4

The inspector confirmed on July 9, 1986, that ES-11, Revision 9,

dated July 9, 1986, classified the sub-system as important to safety

(System Number 852.6). However, the inspector also noted that the

licensee response letter, dated June 27, 1986, to the PAT report

states that the TBIA ..."has been specifically identified on the

.

QCL".. . as an important-to-safety system. As of July 8,1986, this

licensee action was in progress, but was not yet complete.

This was

1

discussed with licensee management at the time of inspection and

also at the TMI-1 SALP Management meeting, July 30, 1986.

I

6.3 (Closed) Unresolved Item 289/86-03-21: Corrective Action Related

to Out-of-Specification Operator Log Data Entries.

Paragraph

l

III.C.2 of the PAT report noted that out-of-specification log

i

entries on important-to-safety system were not effectively corrected

within a timely manner. A specific example is related to the refill

tank truck (for the EFW TBIA) air pressure being out of specifica-

tion (low) for a number of shifts.

The NRC Inspection 50-289/85-30

for the period December 13, 1985, to January 10,1986,(paragraph

3.2.8) noted similar examples with out-of-specification readings

existing for many shifts or days. Contributing to the corrective

action problem, personnel were not following related administrative

controls as follows:

out-of-specification log data entries were not circled as

--

required by the instructions on the affected log sheets;

_ _ . _ __

_,

_ . . - _ _ _ _

_._

__

__.

_ _ _ _

_

_ _ . _

- _ _ .

,

- - . _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _

.

-

..

13

.

.

explanatory notes were not made on the log sheets for out-of-

--

specification data entries as required by Administrative

Procedure 1016, paragraph 3.3.4 and

log sheet discrepancies, such as those noted above, went

--

uncorrected and apparently unnoticed during shift turnover

reviews of the logs by the shift foreman and the on-coming

operators.

This is an example of failure to take timely and appropriate

'

corrective action on handling out-of-specification log entries

(see paragraph 6.5).

6.4 (Closed) Unresolved Items 289/86-03-12, 13, and 14: Document

Updating as a Result of Facility Changes.

Paragraphs III.A.3.d,

III.A.3.e, III.A.3.f. and III.A.3.g of the PAT report discussed

items related to design document updating. The highlights of

these paragraphs and the disposition of the items is discussed

below. The lack of updated design documents was a previously

i

l

cited violation (reference NRC Inspection Report 50-289/81-22,

1

November 12,1981).

6.4.1

III.A.3.d: Certain design documents, particularly

drawings, were not updated when required administratively,

i.e., when six or more changes had been posted. A Quality

j

Assurance audit performed in September 1985 identified

)

similar problems with some of the licensee's specified

'

j

corrective actions. Also, the inspection noted that a

i

change to a procedure on "GPUN Drawings" was being recently

prepared and that the progress of this effort is relatively

(

slow. This is an example of ineffective corrective action.

6.4.2

III.A.3.e: There was no procedure for the use of the

Computer Assisted Records and Information Retrieval System

(CARIRS) and that the use of and interpretation of CARIRS

was not well understood by plant personnel.

In their

response to the PAT report, the licensee made commitments

for the more effective use of CARIRS as an aide in design

document updating. This is unresolved pending Region I

review of licensee corrective action implementation.

(289/86-12-07)

6.4.3

III.A.3.f: Two of twenty control room Piping and Instru-

ment Otagrams (P& ids) were found to be out of date and that

no audit of control room drawings had been performed since

July 1985. The licensee has responded to this matter and

noted that a check of the plant configuration control list

identified six of approximately 2,100 control room drawings

with changes outstanding for more than thirty days. Also,

the out-of-date drawings have been updated.

.

-

...

14

.

.

.

6.4.4

III.A.3.g: This paragraph, as well as paragraph III.B.S.b,

identified inconsistencies and errors in drawings and

System Design Descriptions. The licensee has responded to

the drawing inconsistencies noted and stated that, where

appropriate, corrective action has been initiated.

Collectively, paragraphs 6.4.1, 6.4.3, and 6.4.4 constitute another

example of failure to take timely corrective action for conditions

adverse to quality (see paragraph 6.5).

This item is similar to a

violation cited in NRC Inspection 50-289/81-22, November 12, 1981,

for which the corrective actions apparently have not been fully

effective.

6.5 Conclusion

Paragraphs 6.3 and 6.4 represent examples of an apparent violation

of 10 CFR 50 Appendix B Criterion XVI and QAP Sections 8.1.1 and

8.1.2 on failure to take prompt corrective action on known conditions

adverse to quality (289/86-12-08).

In order to fully resolve the programmatic problem discussed above,

a detailed review of the licensee's design document updating proce-

dures, resolution of audit findings, use of CARIRS and adequacy of

corrective actions taken will be performed by Region I and/or the

next PAT inspection.

7.

Other Significant Inspection Findings

'

7.1 Introduction

During the inspection of design changes and modifications, the PAT

team identified other issues that were considered to be significant.

These are described below.

7.2 (Closed) Unresolved Item 289/86-03-25:

Inservice Testing of Newly

Installed E N Instrument Air Valves.

The PAT Inspection Report

50-289/86-05, paragraphs III.A.1.b and III.D.2.a. b, and c, noted the

EN Two-Hour Backup Supply Air system was tested as part of its

acceptance process but no further testing had been performed and no

future testing of this system was planned. Specific examples are

noted below.

Proper operation of the E N Two-Hour Backup Supply Air System

--

depends on ten identical isolation check valves. These valves

were not routinely tested and, under normal operating condi-

tions, experience no differential pressure.

The control of each EN flow control valve depends on the

--

repositioning of a three-way air valve. These three-way valves

were not routinely tested.

.

..

-*

..

15.

.

.

The ability of the EFW system flow control valves to fail in a

'- -

safe manner depends on a small pressurized air flask' located at

each flow control valve. Each air flask was protected from

depressurizing by a check valve, but those check valves were

also not routinely tested.

The necessity and requirements associated with additional testing of

.these valves will be further reviewed and, if necessary, referred to

the Office of Nuclear Reactor Regulation (NRR). This is an unre-

solved item (289/86-12-09).

7.3 (Closed) Unresolved Item 289/86-03-07): Cable Used in EFW System

Not Environmentally Qualified.

In reference to PAT paragraph

III.A.2.c, the qualifications of this cable were established by the

licensee and the area was extensively reviewed as documented in NRC

Inspection Report (IR) Nos. 50-289/86-06 and 86-10. An apparent

violation of NRC requirements (10 CFR 50.49) was identified along

with several unresolved issues. These issues are being tracked

separately based on the IR 86-06 review.

8.

Update on Other Findings

8.1 Introduction

The PAT report discussed other findings that were not identified as

unresolved or inspector follow items and were not assigned outstand-

ing item numbers. The inspector reviewed these issues and determined *

that the below listed items should be followed separately as

unresolved items.

8.2 PAT Report Paragraph III. A.3.h.(1): Prospective Evaluations of a

Design Change. Job Ticket CH 269 removed instrument air lines for

an E N pump recirculation line, EF-V-8A, without evidence or refer-

ence to a' proper safety evaluation. Since the valve is now perma-

nently blocked open, the air' lines are no longer needed. The

licensee response to the PAT report identified that the disabling of

air'to the valve was previously evaluated and approved by NRC. The

'

appropriate analysis was referenced in CMR No. 0515M., This is

unresolved pending Region I review of licensee internal documents

evaluating the removal of instrument air lines for EF-V-8A

(289/86-12-10).

8.3 PAT Report Paragraph III.A.3.h.(2):

Proper Completion of Safety

Evaluation Forms Regarding Safety Analysis Report Updating.

In this paragraph and in other paragraphs of the PAT report,

licensee representatives inappropriately marked applicable safety

evaluation forms as not needing SAR updating when, in fact, the SAR

addressed those systems and SAR updating was warranted.

It appears

to the inspector that either licensee personnel are not familiar with

the SAR contents or inappropriate personnel are being assigned safety

evaluation review responsibilities.

._.

.

-

..

16

-

.

In their response to the PAT report, the licensee indirectly commit-

ted to increased training in this area. The licensee should consid-

er specifically how well reviewers are trained in SAR content. This

is unresolved pending a Region I review of the effectiveness of

ifcensee training and actions with respect to SAR update

determinations (289/86-12-11).

9.

Exit Interview

The inspectors discussed the inspection scope and findings with the

licensee management at a final exit interview conducted August 14, 1986.

Senior licensee personnel attending the final exit meeting included the

following:

J. Colitz, Plant Engineering Director, TMI-1

H. Hukill, Vice President and Director, TMI-1

R. Keaton, Director, Engineering Projects, Technical Functions

E. Kintner, Executive Vice President, Office of the President

R. McGoey, Manager, PWR Licensing, Technical Functions

R. Toole, Operations and Maintenance Director, TMI-1

A representative of the Commonwealth of Pennsylvania, Ajit Bhattacharyya,

also attended the meeting.

At the exit meeting, the licensee expressed concern regarding redundancy

of effort involved in responding to this report since he has already

provided a written response dated June 27, 1986 to report 50-289/86-03.

The NRC encouraged the licensee to (1) evaluate his June 27, 1986

responses for adequacy and completeness as corrective actions for vio-

lations described herein, and (2) where appropriate, incorporate his

June 27 response by reference, to reduce redundancy.

The inspection results, as discussed at the meeting, are summarized in-

the cover page of the inspection report.

Licensee representatives

indicated that none of the subjects discussed contained proprietary or

safeguards information.

Unresolved Items are matters about which information is required in order

to ascertain whether they are acceptable, violations, or deviations.

Unresolved item discussed during the exit meeting are addressed in all

paragraphs of this report because of the nature of this inspection as

followup to previous inspection findings.

Inspector Follow Items are significant open issues warranting followup by

the inspector at a later time to determine if it is acceptable, unre-

solved, a violation, or a deviation.

Inspector follow items discussed

during the exit meeting are addressed in a majority of paragraphs of this

report because of the nature of the inspection as followup to previous

findings.

.

y

uw.

-..

.-

~-

-

, - . -

.,----,---..--e

,n.,

-.,---,,------,--,~,--e,----

..,nn..,

~n

--e,

nne

,

,

.

.

.

.

Attachment 1 - 86-12

Page 1

,

ILSP. RPT. 86-03

INSP RPT 86-12

PARA NO. SEC. lit

ITEM DESCRIPTION

PARA NO.

DISPOSITION

OUTSTANDING ITEM NO. ASSIGNED

A.1.a

Single Failure of Two-Hour Backup

2.3

Violation

86-03-01

86-12-02

Air System

A.1.b

Two-Hour Backup Ai r System Va lve

7.2

Unresolved

NA

86-12-09

Testing

(See Ill.D.2.a,b,c)

A.1.c

Two-Hour Backup Ai r System Post-

3.4.1

Violation

86-03-02

86-12-03

Modification Functional Testing

A.1.d

installation of Two-Hour Backup

5.2.1

Violation

86-03-03

86-12-04

instrument Ai r System Ai r

Cylinders

A.1.e(1)

Design input to Two-Hour Backup

3.2.1

Acceptable

NA

NA

Air System Related to Minimum

Air Pressure

A.1.e(2)

Design input to Two-Hour Backup

3.3

Violation

NA

86-12-03

Air System Related to Sizing of

Regulating Valves - Vendor

Interface

A.1.f.(1)&(2)

Safety Classification of EFW

6.2

Unresolved

86-03-04

86-12-06

System Components

A.2.a.(1)

Design input Associated with

NA

Unresolved

86-03-05

86-12-12

EFW Pump Motor Overcurrent

Assigned

Protection

A.2.a.(2)

Control of Design inputs

3.2.2

Violation

86-03-05

86-12-03

Associated with Battery Sizing

A.2.a.(3)

Design Analysis Not Available

NA

Unresolved

86-03-05

86-12-13

for 118 VAC Circuits

Assigned

A.2.a.(4)

Unverified Design input for dc

3.2.3

Violation

86-03-05

86-12-03

Distribution Panet Fuses

A.2. a . ( 5 )

Design Analysis for Minimum

NA -

Un re so l ved

86-03-05

86-12-14

Motor Sta rting Voltages

Assigned

A.2.b.(1)&(2)

Electrical isolation of Safety

2.4

Un re so lved

86-03-06

86-12-17

Grade Instrumentation

A.2.c

Environmental Qualification of

7.3

Violation

86-03-07

86-06-07

EFW Cable

(IR-86-06)

l

t

_ _ - _ _ _ _ _ - - - _ _ - - - _ - . _ . _ _ - . _ - - _ - _ _ _ _

-- . _ .

- _ _ _ .

_ _

- - . _ _ _ _ . _ . _ _ _ _ _ . - _ _ _ _ _ __

_ - - _ _ _ _ _ _ _ _ _ _ _ _ - _ - - _ _ _ _ _ - - _ _ -._-- _-__ __. -.

_.

_

.

,

.

DISPOSITION OF PAT INSPECTION ITEMS.

IwSP. RPT. 86-03

INSP RPT 86-12

PARA NO. SEC. III

ITEM DESCRIPTION

PARA NO.

DISPOSITION

OUTSTANDING ITEM NO. ASSIGNED

A.2.d

Appendix R Review - Overcurrent

NA

Unresolved

86-03-08

NA

Protection Coordination

A.2.e

Grounding Practices

NA

Inspector

NA

86-12-15

Follow item

Assigned

A. 3. d. ( 1 )

10 CFR 50.59 Evaluation for Lead

2.2

Violation

86-03-09

86-12-02

c.

Shielding

A.3.a.(2)h(3)

Procedure Adequacy and implemen-

NA

Unresolved

86-03-09

86-12-16

tation for Shielding Installation

Assigned

A.3.a.(4)

Design Verification of Lead

3.4.2

Violation

86-03-09

86-12-03

Shielding

A.3.a.(5)

Improper installation of Lead

5.2.3

Violation

86-03-09

86-12-04

Shielding

A.3.b.(1)k(2)

Implementation of Mini-Mod

4

Violation

86-03-10

86-12-04

Prog ram

A.3.c.(1)h(2)t(3)

Design Verification for Various

3.4.3

Violation

86-03-11

86-12-03

Modifications

A.3.d

Updating Design Documents

6.4.1

Violation

86-03-12

86-12-08

A.3.e

use of CARIRS

6.4.2

Un re so lved

NA

86-12-07

A.3.f

Cont ro l Room Drawing Control

6.4.3

Violation

86-03-13

86-12-08

A.3.g

Document Control Errors

6.4.4

Violation

86-03-14

86-12-08

A.3.h.(1)

Modification Evaluation for

8.2

Un reso lved

NA

86-12-10

EFW Recirculation Valve

A.3.h.(2)

FSAR Updating for Tempora ry

8.3

Un reso lved

NA

86-12-11

Modifications

8.1

Preventive Maintenance on HPS

NA .

Closed

NA

NA

Valve

IR 86-05

8.2.a.(1)(2)a(3)

Limitorque Maintenance Procedure

NA

Inspector

86-03-15

NA

Adequacy

Follow Item

B. 2. b . ( 1 )( 2 )&( 3 )

Torque Switch Setting Records

NA

Inspector

86-03-16

NA

Follow Item

-O

.g

l

s

DISPOSITION OF PAT INSPECTION ITEMS

'

ILSP. RPT. 86-03

INSP RPT 86-12

PARA NO. SEC. Ill

ITEM DESCRIPTION

PARA NO.

DISPOSITION

OUTSTANDING ITEM NO. ASSIGNED

B.3

EFW Pump Packing Procedure

NA

Inspector

86-03-17

NA

Adequacy

Follow item

u.4

Vendor Tech Manuals

NA

inspector

86-03-18

NA

follow item

B.5.a

Pipe Support Installation

NA

Un re so lved

86-03-19

NA

b.5.b

Drawing Deficiencies

6.4.4

Unresolved

NA

86-12-08

B.5.c

EFW Pump Coo l ing Wa te r Va l ve

NA

No NRC Action MA

NA

Position

Action Required

B.5.d

Physical Location of Block Valve

NA

Inspector

86-03-20

NA

Follow Item

C.)

Control Room Observations

NA

No NRC Action NA

NA

Requ i red

"

C.2

Operator Log Entries

6.3

Violation

86-03-21

86-12-08

C.3

Procurement of Instrument Ai r

NA

Un re so lved

86-03-22

NA

C.4

Cont ro l of Lif ted Loads and Jumpers

NA

Unresolved

86-03-23

NA

D.1.a

Surveillance Test initial Conditions

2.5

Un reso l ved

86-03-24

86-12-01

D.1.b

Change to Procedures Described in FSAR

2.5

Violation

86-03-24

86-12-02

D.2.a,0&c

Test of Newly Installed EFW Check &

7.2

Un reso lved

86-03-25

.86-12-09

Control Valves

,

E.1.2.3&4

T ra ining

NA

No NRC Action NA

NA

Action

F.1

QA Program Technica l & Design Issues

NA

No NRC Action MA

NA

Requi red

F.2

Comments Relating to QA Audits

NA -

No NRC Action NA

NA

Required

F.3

Corrective Actions

6.4.3

Violation

NA

86-12-08

F.4

Safety Review Program

NA

No NRC Action NA

NA

Required