Forwards Emergency Preparedness Exercise Insp Repts 50-373/87-14 & 50-374/87-14 on 870428-30.No Violations Noted.One Weakness Identified Re Inadequate Demonstration of Health Physics Contamination Control Actions
ML20214L615
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 05/22/1987
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML20214L618 List:
References
NUDOCS 8706010027
Download: ML20214L615 (3)


See also: IR 05000373/1987014

Text

-.

_-

.

. .

,

.

MAY 221987

Docket No. 50-373

Docket No. 50-374

Commonwealth Edison Company

ATTN: Mr. Cordell Reed

Vice President

Post Office Box 767

Chicago, IL 60690

Gentlemen:

This refers to the emergency pre)aredness exercise inspection conducted by

Mr. James Foster and others of t1is office on April 28-30, 1987, of activities

at the LaSalle County Station, Units 1 and 2, authorized by NRC Operating

Licenses No. NPF-11 and NPF-18, and to the discussion of our findings with

Mr. G. Diederich and others of your staff at the conclusion of the inspection.

The enclosed copy of our inspection re) ort identifies areas examined during

the inspection. Within these areas, tie inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

No violations of NRC requirements were identified during the course of this

inspection.

However, one weakness was identified which will need corrective

action by your staff.

This weakness is summarized in the enclosure to this

letter.

As required by 10 CFR 50, Appendix E (IV.F) any weaknesses that are

identified must be corrected and a written response submitted to this office

within 45 days.

In accordance with 10 CFR 2.790 of the Commission's regulations a copy of

thisletter,theenclosures,andyourresponsetothisletterwIllbeplaced

in the NRC Public Document Room.

8706010027 070522

y

PDR

ADOCK 05000373

/gg

g

PDR

i

_ _ _ _ - _ _ _ _ _ _ _ _ -

.

Commonwealth Edison Company

2

g g gg

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

marrginnt sised lir T.D. Etiaferer

W. D. Shafer, Chief

Emergency Preparedness and

Radiological Protection Branch

Enclosures:

1.

Exercise Weaknesses

2.

Inspection Reports

No. 50-373/87014 DRSS

No. 50-374/87014 DRSS

cc w/ enclosures:

D. L. Farrar, Director

of Nuclear Licensing

G. J. Diederich, Plant

Manager

DCS/RSB(RIDS)

Licensing Fee _ Management Branch

Resident Inspector, RIII

Richard Hubbard

J. W. McCaffrey, Chief, Public

Utilities Division

David Rosenblatt, Governor's

Office of Consumer Services

D. Matthews, EPB, NRR

W. Weaver, FEMA, RV

3

RII

RIII,

RIII

rig

'

r

qr

o

r

e

n

ee

Y.,

eb&

.

__ -

.

.

____

.

EXERCISE WEAKNESS

The post-accident sampling team failed to adequately demonstrate precautionary

actions and show increased awareness for Health Physics contamination control

during /87014-03; 50-374/87014-03) (Section 5d)the performance of a High Radiatio

(50-373

-