ML20214F545
| ML20214F545 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 05/15/1987 |
| From: | Stolz J Office of Nuclear Reactor Regulation |
| To: | Mroczka E NORTHEAST NUCLEAR ENERGY CO. |
| References | |
| GL-87-02, GL-87-2, NUDOCS 8705260142 | |
| Download: ML20214F545 (1) | |
Text
I O
May 15,1987 Docket No. 50-336 -
50 423 Mr. Edward J. Mroczka, Senior Vice President Nuclear Engineering and Operations Northeast Nuclear Energy Company
.P.O. Box 270 Hartford, Connecticut 06141-0270
Dear Mr. Mroczka:
Subject:
Granting Relief to Members of the Seismic Qualification Utilities Group (SQUG) From the 60 Day Reporting Requirement of Generic Letter 87-02 For your information, enclosed is a letter from Thomas E. Murley, Director, NRR, to Mr. Neil P. Smith, Chainnan, SQUG, granting relief from the 60 day reporting requirement of Generic Letter 87-02 to utilities who are members of SQUG.
Sincerely,
/s/
John F. Stolz Director Project Directorate I-4 Division of Reactor Projects I/II
Enclosure:
As Stated cc w/ enclosure:
See next page DISTRIBUTION Docket File.
NRC & Local PDRs PDI-4 Reading J. Stolz B. Boger S. Norris D. Jaffee 8705260142 870515 R. Ferguson PDR ADOCK 05000336 OGC-Bethesda P
PDR E. Jordan J. Partlow ACRS (10)
PD plant-specific file [ Gray File) cc: Plant Service list See next page L
I-4 P
PDIA4
-4 SN rr s DJ e
RFerguson J
A 5/14/87 5
87 5/ \\y87 54 /87
- ,' ~
UNITED STATES j
' ?/
'(
NUCLEAR REGULATORY COMMISSION
]
c wasmwatow.o.c.aosas
.. [
r, k'* *t,Q APR 2 8 }ggy Mr. Neil P. Smith I
Chairman Seismic. Qualification Utility Group 801 18th Street, N.W.
Suite 300 l
Washington, D.C.
- 20006,
Dear Mr. Smith:
I have received your letter dated April 10, 1987 requesting clarification of the 60-day reporting provisions.cf Generic Letter 87-02. In Generic Letter 87-02, the staff requested that each licensee subject to the USI A-46 equipment seismic adequacy verification requirements provide a schedule for implementation of the seismic verification within 60 days of receipt of the i
Generic Letter.
In your letter you stated that licensees who belong to the Seismic Qualification Utility Group (SQUG) will be unable to provide a schedule for i
implementation at this time because the generic implementation procedures are still under development by the SQUG and will not be finalized until the completion of seyeral trial plant reviews.
i The staff hatireviewed your request and concluded that it is appropriate to l
extend the 60-day reporting provisions of Generic Letter 87-02 for SQUG licensees until the generic implementation procedures are better defined and the trial plant reviews are completed. It is my understanding that the SQUG generic implementation procedures should be essentially cosplete before r
By that date at least two trial plant reviews will have been October 1,1587.
completed and the generic implementation procedures sufficiently defined and i
reviewed by NRC staff so that licensees can plan and schedule their plant specific reviews.
j
~
All licensees participating in the USI A-46 SQUG implementation program should provide the schedule for plant specific implementation no later than l
The NRC staff will review and evaluate the generic December 1, 1987.
procedures by October 1, to allow each utility 60 days to prepare their replies to the generic letter.
1 Sincerely, 1
l Thomas E. Murley, Ohnr Office of Nuclear Reactor Regulation nry4 m y,
,9 wi,avuayw,+
j k
s.
Mr. E. J. Mroczka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. 3 cc:
Gerald Garfield, Esq.
Ms. Jane Spector Day, Perry & Howard Federal Energy Regulatory Commission City Place 825 N. Capitol Street, NE Hartford, ' Connecticut 06103-3499 Room 8608C Washington, D.C.
20426 Mr. Maurice R. Scully, Executive Director Mr. Kevin McCarthy, Director Connecticut Municipal Electric Radiation Control Unit Energy Cooperative Department of Environmental Protection 268 Thomas Road State Office Building Groton, Connecticut 06340 Hartford, Connecticut 06115 Robert W. Bishop, Esq.
Burlington Electric Department Corporate Secretary c/o Robert E. Fletcher, Esq.
Northeast Utilities 271 South Union Street Post Office Box 270 Burlington, Vennont 05402 Hartford, Connecticut 06141 Mr. Thomas Shedlosky Senior Resident Inspector Office U. S. Nuclear Regulatory Commission Millstone III P. O. Box 811 Niantic, Connecticut 06357-08 Mr. Michael L. Jones, Manager Project Management Department Massachusetts Municipal Wholesale Electric Company Post Office Box 426 Ludlow, Massachusetts 01056 Regional Administrator U. S. NRC, Recion I 631 Park Avenue King of Prussia, Pennsylvania 19406 Mr. Karl Abraham Public Affairs Office, Region I U. S. Nuclear Regulatory Commission, King of Prussia, Pennsylvania 19406