Forwards Chronology of Approved Safeguards Plan,Establishing Record of Safeguards Amends & Providing Assistance in Insp Effort
ML20213H001
Person / Time
Site: Beaver Valley
Issue date: 05/14/1987
From: Tam P
Office of Nuclear Reactor Regulation
To: Carey J
DUQUESNE LIGHT CO.
References
NUDOCS 8705190091
Download: ML20213H001 (3)


Text

)

fi2y 14, 1987 f

Docket No. 50-412 Mr. J. J. Carey, Senior Vice President Duquesne Light Company Nuclear Group ,

Post Office Box 4 i Shippingport, Pennsylvania 15077

Dear Mr. Carey:

Subject:

Beaver Valley Unit 2 - Chronology of Approved Safeguards Plan

? Enclosed please find the chronology of the approved safeguards plan for Beaver i Valley Unit 2. This chronology should be maintained with your safeguards i plans. This document, in addition to establishing a record of current safeguards amendments, provides assistance in the inspection effort, since licensees can only be inspected against the approved safeguards plan for violations, not against the regulations.

If you have any questions, please feel free to contact me.

Sincerely,

/s/

Peter S. Tam, Project Manager Pro. ject Directorate I-4

, Division of Reactor Pro.iects I/II b

Enclosure:

As stated i,

! cc w/ enclosure: .

See next page l

DISTRIBUTION l j Docket. File-  !

NRC & Local PDRs O PDI-4 Reading j) J. ,tolz '

J B. Boger S. Norris P. Tam 8705190091 870514 OGC-Bethesda pDR ADOCK 0500 2 E. Jordan J. Partlow ACRS (10)

PD plant-specific file [ Gray File]

cc: Plant Service list See next page LAPDI-4 PDI-4 PDI S PTam;1h JSt 1 5//_5/87 5//(t/t 7 5////87 1

i Mr. J. J. Carey Duquesne Light Company Beaver Valley 2 Power Station cc:

Gerald Charnoff, Esq. Mr. R. E. Martin, Manager Jay E. Silberg, Esq. Regulatory Affairs Shaw, Pittman, Potts & Trowbridge Duquesne Light Company 2300 N Street, N.W. Beaver Valley Two Project Washington, DC 20037 P.O. Box 328 Shippingport, Pennsylvania 15077 Mr. C. W. Ewing, Ouality Assurance Pennsylvania Office of Consumer Manager Advocate Ouality Assurance Department ATTN: Michael Bardee Duquesne Light Company 1425 Strawberry Square P.O. Box 186 Harrisburg, Pennsylvania 17120 Shippingport, Pennsylvania 15077 John D. Burrows, P.E.

Director, Pennsylvania Emergency Director of Utilities Management Agency State of Ohio Room B-151 Public Utilities Commission Transportation & Safety Building 180 East Broad Street Harrisburg, Pennsylvania 17120 Columbus, Ohio 43266-0573 Mr. T. J. Lex Bureau of Radiation Protection Westinghouse Electric Corporation PA Department of Environmental Power Systems Resources P.O. Box 355 ATTN: R. Janati Pittsburgh, Pennsylvania 15230 P.O. Box 2063 Harrisburg, Pennsylvania 17120 Mr. P. RaySircar Stone & Webster Engineering Corporation BVPS-2 Records Management Supervisor P.O. Box 2325 Duquesne Light Company i Boston, Massachusetts 02107 Post Office Box 4 I Shippingport, Pennsylvania 15077 Mr. J. Beall U.S. NRC John A. Lee, Esq.

P.O. 181 Duquesne Light Company Shippingport, Pennsylvania 15077 1 0xford Centre 301 Grant Street Regional Administrator, Region I Pittsburgh, Pennsylvania 15279 ,

. U.S. Nuclear Regulatory Commission (

631 Park Avenue King of Prussia, Pennsylvania 19406 l

7 --

l ..-

50-412 Beaver Valley Power Station Unit 2

< The approved security plans for the Beaver Valley Power Station, Unit 2, consist of the following amendments, revisions, and changes:

I

" Beaver Valley Power Station Physical Security Plan"

- Issue 4, Revision 0, February 1987 (letter dated February 19,1987).

- Issue 4, Revision 0, March 1987 (letter dated March 23,1987).

- Issue 4, Revision 0, April 1987 (letter dated April 15,1987).

r Valley Safeguards Contingency Plan" "Beave'

- Issue 4, Revision 0, February 1987 (letter dated February 19,1987).

" Beaver aV lley Training and Qualification Plan"

- Issue 4, Revision 0, February 1987 (letter dated February 19,1987).

Issue 4, Revision 0, April 1987 (letter dated April 15,1987).

i t .

9 I