MONTHYEARML20217B9061999-10-0101 October 1999 Proposed Tech Specs Re Control Rod Block Instrumentation ML20212H5261999-09-27027 September 1999 Proposed Tech Specs Pages,Revising TS Re Loss of Power Setpoints for 4 Kv Emergency Buses ML20210N0801999-08-0606 August 1999 Proposed Tech Specs Incorporating Note Which Will Permit one-time Exemption Until 990930,from 90 F Limit Stated in SR 3.7.2.2 ML20210E6001999-07-21021 July 1999 Proposed Tech Specs,Deleting Requirement for Refuel Platform Fuel Grapple Fully Retracted Position Interlock Currently Required by TS Surveillance Requirement 3.9.1.1 ML20209F7751999-07-12012 July 1999 Proposed Tech Specs Sections 2.1.1.2 & 5.6.5,incorporating Revised SLMCPR Due to Use of Cycle Specific Analysis & Deleting Previously Added Footnotes Which Are No Longer Necessary ML20209D9861999-07-0808 July 1999 Proposed Final Tech Spec Pages Correcting Minor Administrative Errors in Figure Showing Site & Exclusion Boundaries & Two SRs ML20209B9211999-07-0101 July 1999 Proposed Tech Specs,Reflecting Change in Corporate Structure ML20196A5441999-06-14014 June 1999 Proposed Final Tech Spec Pages for License Change Request ECR 98-01802 Re Installation of Digital Power Range Neutron Monitoring (Prnm) Sys & Incorporation of long-term thermal- Hydraulic Stability Solution Hardware ML20195B8271999-05-25025 May 1999 Proposed Final Tech Specs Pages for License Change Application ECR 96-01511 Re Rev to Loss of Power Setpoints for 4 Kv Emergency Buses ML20205F6391999-03-29029 March 1999 Proposed Tech Specs Pages,Deleting Requirement for Refuel Platform Fuel Grapple Fully Retracted Position Interlock Currently Required by TS Surveillance Requirement 3.9.1.1 ML20207E2551999-03-0101 March 1999 Proposed Tech Specs Supporting PBAPS Mod P00507 Which Will Install Power Range Neutron Monitoring Sys Incorporate long-term T/H Stability Solution Hardware ML20198N2531998-12-24024 December 1998 Proposed Tech Specs Revising Setpoints & Limits of Allowable Values for LOP Instrumentation for 4kV Emergency Buses Contained in TS Table 3.3.8.1-1, LOP Instrumentation ML20154C8271998-09-29029 September 1998 Proposed Tech Specs SR 3.6.4.1.2,revising Wording to Maintain Requirement That Secondary Containment Is Not Breached at Any Time When Secondary Containment Is Required ML20151Y3841998-09-14014 September 1998 Revised Proposed Final TS Pages for License Change Application ECR 97-02809,incorporating end-of-cycle Recirculation Pump Trip Sys at Units 2 & 3 ML20151Y3711998-09-11011 September 1998 Proposed Final TS Pages for License Change Application ECR 98-01403,revising SLMCPRs for Unit 2 ML20151Y3651998-09-11011 September 1998 Proposed Final TS Pages for License Change Applications ECR 96-02324 & 98-00499,revising MSIV Leakage & Safety Relief Valve Surveillance Testing ML20151T0421998-08-31031 August 1998 Proposed Final Tech Specs Pages for License Change Application ECR 97-02809,incorporating end-of-cycle Recirculation Pump Trip Sys at Plant ML20236W2201998-07-29029 July 1998 Proposed Tech Specs,Supporting Installation of Mod P00271 for Unit 2 Re Replacement of Source Range & Intermediate Range Monitors W/New Wide Range Neutron Monitoring Sys ML20236R3121998-07-10010 July 1998 Proposed Tech Specs Pages for License Change Application ECR 98-01403,revising TS Section 2.0.W/non-proprietary Addl Info Re 1.10 Cycle Specific SLMCPR Cycle 13 ML20236P7531998-07-0909 July 1998 Proposed Tech Specs Supporting Installation of Mod P00271, for Unit 2 Re Facility Operating License Change Request 93-18 ML20247C2611998-05-0101 May 1998 Proposed Tech Specs Deleting Requirements for Functional Testing of SRVs During Each Unit Startup ML20217K3651998-04-28028 April 1998 Proposed Tech Specs Bases Through Unit 2 Bases Rev 17 & Unit 3 Bases Rev 19 ML20217G7531998-03-20020 March 1998 Proposed Tech Specs Re end-of-cycle Recirculation Pump Trip Sys at Plant ML20217Q4711998-03-0202 March 1998 Proposed Tech Specs Adding Requirements to Achieve Compliance w/10CFR50.36a, TS on Effluents from Nuclear Power Reactors ML20202F4201998-02-0404 February 1998 Proposed Tech Specs Revising SR 3.6.4.1.2 & Associated Bases to Reflect Changes in Requirements for Secondary Containment Doors ML20211H9281997-09-26026 September 1997 Proposed Tech Specs,Replacing Page 2.0-1 & Adding Page 5.0-21 for Unit 3 ML20211F4001997-09-22022 September 1997 Proposed Tech Specs Replacing Source Range & Intermediate Range Monitors W/New Wide Range Neutron Monitoring Sys ML20141G4871997-06-30030 June 1997 Proposed Tech Specs,Revising TS Section 2.0, Safety Limits to Incorporate Revised SLMCPRs Due to Use of GE13 Fuel Product Line & cycle-specific Analysis Performed by GE ML20140D8601997-06-0404 June 1997 Proposed Tech Specs,Revising Section 3.8.2.1 to Eliminate Inconsistency Between Requirements for ECCS Operability & auto-start & Trip Bypass of of EDGs on ECCS Initiation Signal During Listed Events in Application ML20141L0111997-05-23023 May 1997 Proposed Tech Specs Revising Section 5.5.12 to Exclude Measured Main Steam Isolation Valves Leakage from Total Type B & C Local Leak Rate Test Results ML20141E0801997-05-0909 May 1997 Proposed Tech Specs 3.6.1.3.16,replacing Frequency of Primary Containment Purge & Exhaust Valve Inflatable Seals ML20137P7561997-03-31031 March 1997 Proposed Tech Specs,Extending Surveillance Interval for Calibr of Average Power Range Monitor Flow Bias Instrumentation from 18 Months to 24 Months ML20134F6121996-10-30030 October 1996 Proposed Tech Specs,Section 2.0,revising Slmcprs Due to GE Determination That Previous Calculation Is Nonconservative ML20117L2891996-09-0606 September 1996 Proposed Tech Specs 3.3.5.1, ECCS Instrumentation, & 3.8.1, AC Sources-Operating ML20117F9471996-08-27027 August 1996 Proposed Tech Specs Re CRD Charging Water Header Pressure for Shutdown Margin Test ML20117H6761996-08-23023 August 1996 Proposed Tech Specs 2.0 Re Safety Limits ML20117M7041996-06-13013 June 1996 Proposed Tech Specs,Sr 3.3.1.1.12,for APRM Flow Biased High Scram Function,Allowing SR to Be Performed W/O Entering Associated Conditions & Required Actions for Up to Six H Provided Core Flow at or Above 82% ML20101K8131996-03-25025 March 1996 Proposed Tech Specs Section 2.0 Re Safety Limits ML20100J7591996-02-15015 February 1996 Proposed Tech Specs Re Implementation of 10CFR50,App J, Option B ML20096F1481996-01-16016 January 1996 Proposed Tech Specs Base Changes Re Implementation of Main Stack & Vent Stack Radiation Monitoring Sytems ML20095L0231995-12-22022 December 1995 Proposed Improved TS & Bases,Allowing Flexibility to Install Main Stack Rms (Mod 5386) W/O Need for Addl Licensing Actions & Addressing Annotations to Reflect pre- & post-mod Scenarios,Respectively ML20095J1321995-12-21021 December 1995 Proposed Tech Specs,Consisting of Change Request 95-08, Eliminating Outdated Matl from FOLs & Making FOL for Unit 2, Consistent W/Fol for Unit 3 ML20095J7011995-12-19019 December 1995 Proposed Tech Specs Re Administrative Change to Ventilation Filter Testing Program ML20095A1731995-11-30030 November 1995 Proposed Tech Specs,Changing Minimum Allowable Control Rod Scram Accumulator Pressure & Charging Water Header Pressure from Value of 955 Psig to Value of 940 Psig ML20094R2971995-11-22022 November 1995 Revised,Proposed TS Pages 147,157 & 158 Re Early Implementation of Improved TS Section 3.4.3 ML20094Q6801995-11-21021 November 1995 Proposed Tech Specs Re SR for High Pressure Test of HPCI & B 3.5-14 & B 3.5-28.Administrative Change Proposed to Eliminate Ref to Section Previously Eliminated ML20092A2141995-09-0101 September 1995 Proposed Tech Specs,Consisting of Change Request 95-07, Deleting License Condition 2.C ML20092A2841995-08-30030 August 1995 Proposed Tech Specs,Requesting Enforcement Discretion from Portion of FOL Condition 2.C ML20092B9871995-08-28028 August 1995 Proposed Improved Tech Specs ML20087E8881995-08-0404 August 1995 Proposed Tech Specs Re Implementation of New SR Associated W/Conversion to TS 1999-09-27
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20217B9061999-10-0101 October 1999 Proposed Tech Specs Re Control Rod Block Instrumentation ML20212H5261999-09-27027 September 1999 Proposed Tech Specs Pages,Revising TS Re Loss of Power Setpoints for 4 Kv Emergency Buses ML20210N0801999-08-0606 August 1999 Proposed Tech Specs Incorporating Note Which Will Permit one-time Exemption Until 990930,from 90 F Limit Stated in SR 3.7.2.2 ML20210E6001999-07-21021 July 1999 Proposed Tech Specs,Deleting Requirement for Refuel Platform Fuel Grapple Fully Retracted Position Interlock Currently Required by TS Surveillance Requirement 3.9.1.1 ML20209F7751999-07-12012 July 1999 Proposed Tech Specs Sections 2.1.1.2 & 5.6.5,incorporating Revised SLMCPR Due to Use of Cycle Specific Analysis & Deleting Previously Added Footnotes Which Are No Longer Necessary ML20209D9861999-07-0808 July 1999 Proposed Final Tech Spec Pages Correcting Minor Administrative Errors in Figure Showing Site & Exclusion Boundaries & Two SRs ML20209B9211999-07-0101 July 1999 Proposed Tech Specs,Reflecting Change in Corporate Structure ML20196A5441999-06-14014 June 1999 Proposed Final Tech Spec Pages for License Change Request ECR 98-01802 Re Installation of Digital Power Range Neutron Monitoring (Prnm) Sys & Incorporation of long-term thermal- Hydraulic Stability Solution Hardware ML20195B8271999-05-25025 May 1999 Proposed Final Tech Specs Pages for License Change Application ECR 96-01511 Re Rev to Loss of Power Setpoints for 4 Kv Emergency Buses ML20206C5821999-04-20020 April 1999 Rev 4 to RW-C-100, Solid Radwaste Sys Process Control Program (Pcp) ML20205F6391999-03-29029 March 1999 Proposed Tech Specs Pages,Deleting Requirement for Refuel Platform Fuel Grapple Fully Retracted Position Interlock Currently Required by TS Surveillance Requirement 3.9.1.1 ML20207E2551999-03-0101 March 1999 Proposed Tech Specs Supporting PBAPS Mod P00507 Which Will Install Power Range Neutron Monitoring Sys Incorporate long-term T/H Stability Solution Hardware ML20202E6251998-12-31031 December 1998 PBAPS Unit 2 Cycle 13 Startup Rept. with ML20198N2531998-12-24024 December 1998 Proposed Tech Specs Revising Setpoints & Limits of Allowable Values for LOP Instrumentation for 4kV Emergency Buses Contained in TS Table 3.3.8.1-1, LOP Instrumentation ML20195J1651998-11-16016 November 1998 Rev D to LGS Emergency Preparedness NUMARC Eals ML20195J1541998-11-16016 November 1998 Rev D to PBAPS Emergency Preparedness NUMARC Eals ML20154C8271998-09-29029 September 1998 Proposed Tech Specs SR 3.6.4.1.2,revising Wording to Maintain Requirement That Secondary Containment Is Not Breached at Any Time When Secondary Containment Is Required ML20151Y3841998-09-14014 September 1998 Revised Proposed Final TS Pages for License Change Application ECR 97-02809,incorporating end-of-cycle Recirculation Pump Trip Sys at Units 2 & 3 ML20151Y3711998-09-11011 September 1998 Proposed Final TS Pages for License Change Application ECR 98-01403,revising SLMCPRs for Unit 2 ML20151Y3651998-09-11011 September 1998 Proposed Final TS Pages for License Change Applications ECR 96-02324 & 98-00499,revising MSIV Leakage & Safety Relief Valve Surveillance Testing ML20151T0421998-08-31031 August 1998 Proposed Final Tech Specs Pages for License Change Application ECR 97-02809,incorporating end-of-cycle Recirculation Pump Trip Sys at Plant ML20236W2201998-07-29029 July 1998 Proposed Tech Specs,Supporting Installation of Mod P00271 for Unit 2 Re Replacement of Source Range & Intermediate Range Monitors W/New Wide Range Neutron Monitoring Sys ML20236R3121998-07-10010 July 1998 Proposed Tech Specs Pages for License Change Application ECR 98-01403,revising TS Section 2.0.W/non-proprietary Addl Info Re 1.10 Cycle Specific SLMCPR Cycle 13 ML20236P7531998-07-0909 July 1998 Proposed Tech Specs Supporting Installation of Mod P00271, for Unit 2 Re Facility Operating License Change Request 93-18 ML20247C2611998-05-0101 May 1998 Proposed Tech Specs Deleting Requirements for Functional Testing of SRVs During Each Unit Startup ML20217K3651998-04-28028 April 1998 Proposed Tech Specs Bases Through Unit 2 Bases Rev 17 & Unit 3 Bases Rev 19 ML20206C5711998-04-16016 April 1998 Rev 11 to ODCM for Pbaps,Units 1 & 2 ML20217G7531998-03-20020 March 1998 Proposed Tech Specs Re end-of-cycle Recirculation Pump Trip Sys at Plant ML20217Q4711998-03-0202 March 1998 Proposed Tech Specs Adding Requirements to Achieve Compliance w/10CFR50.36a, TS on Effluents from Nuclear Power Reactors ML20202F4201998-02-0404 February 1998 Proposed Tech Specs Revising SR 3.6.4.1.2 & Associated Bases to Reflect Changes in Requirements for Secondary Containment Doors ML20202H4141998-01-31031 January 1998 Cycle 12 Startup Rept Unit 3 ML20211H9281997-09-26026 September 1997 Proposed Tech Specs,Replacing Page 2.0-1 & Adding Page 5.0-21 for Unit 3 ML20211F4001997-09-22022 September 1997 Proposed Tech Specs Replacing Source Range & Intermediate Range Monitors W/New Wide Range Neutron Monitoring Sys ML20141G4871997-06-30030 June 1997 Proposed Tech Specs,Revising TS Section 2.0, Safety Limits to Incorporate Revised SLMCPRs Due to Use of GE13 Fuel Product Line & cycle-specific Analysis Performed by GE ML20140D8601997-06-0404 June 1997 Proposed Tech Specs,Revising Section 3.8.2.1 to Eliminate Inconsistency Between Requirements for ECCS Operability & auto-start & Trip Bypass of of EDGs on ECCS Initiation Signal During Listed Events in Application ML20141L0111997-05-23023 May 1997 Proposed Tech Specs Revising Section 5.5.12 to Exclude Measured Main Steam Isolation Valves Leakage from Total Type B & C Local Leak Rate Test Results ML20141E0801997-05-0909 May 1997 Proposed Tech Specs 3.6.1.3.16,replacing Frequency of Primary Containment Purge & Exhaust Valve Inflatable Seals ML20141J0311997-05-0808 May 1997 Rev 7 to Pump & Valve IST Program Third Ten Yr Interval ML20137P7561997-03-31031 March 1997 Proposed Tech Specs,Extending Surveillance Interval for Calibr of Average Power Range Monitor Flow Bias Instrumentation from 18 Months to 24 Months ML20217M8301997-01-30030 January 1997 Rev 10 to ODCM, for Peach Bottom Atomic Power Station Units 1 & 2 ML20134A6751997-01-24024 January 1997 Cycle 12 Startup Rept Unit 2 ML20134F6121996-10-30030 October 1996 Proposed Tech Specs,Section 2.0,revising Slmcprs Due to GE Determination That Previous Calculation Is Nonconservative ML20138B0081996-09-27027 September 1996 Rev 3 to Solid Radwaste Sys Process Control Program (Pcp) ML20117L2891996-09-0606 September 1996 Proposed Tech Specs 3.3.5.1, ECCS Instrumentation, & 3.8.1, AC Sources-Operating ML20117F9471996-08-27027 August 1996 Proposed Tech Specs Re CRD Charging Water Header Pressure for Shutdown Margin Test ML20117H6761996-08-23023 August 1996 Proposed Tech Specs 2.0 Re Safety Limits ML20117M7041996-06-13013 June 1996 Proposed Tech Specs,Sr 3.3.1.1.12,for APRM Flow Biased High Scram Function,Allowing SR to Be Performed W/O Entering Associated Conditions & Required Actions for Up to Six H Provided Core Flow at or Above 82% ML20101K8131996-03-25025 March 1996 Proposed Tech Specs Section 2.0 Re Safety Limits ML20100J7591996-02-15015 February 1996 Proposed Tech Specs Re Implementation of 10CFR50,App J, Option B ML20096F1481996-01-16016 January 1996 Proposed Tech Specs Base Changes Re Implementation of Main Stack & Vent Stack Radiation Monitoring Sytems 1999-09-27
[Table view] |
Text
. _ _ .
i APPENDIX A to '
License No. DPR-12 TECHNICAL SPECIFICATIONS for Peach Bottom Atomic Power Station Unit No. 1 1.0 LOCATION AND SITE The Peach Bottcm Atomic Power Station Unit No. 1 is located in Peach Bottom Township,. Pennsylvania, on the western shore of the Conowingo Pond at the mouth of Rock Run Creek on a site owned by Philadalphia Electric Company. The Exclusion Area shall consist of an area within the Peach Bottom Atomic Power Station which is enclosed within locked barriers, and contains the Containment Vessel, Spent Fuel Pool Building and Radwaste Building. The only activity carried on within the Exclusion Area shall be routine and emergency inspections and maintenance associated with the possession of the decommissioned Peach Bottom Station Unit No. 1.
The Peach Bottom Atomic Information Center may be located on the site and be open to the public, provided a suitable evacuation procedure is maintained. Peach Bottom Atomic Power Station, Units 2 and 3 are also located on the site.
2.0 ADMINISTRATIVE AND PROCEDURAL SAFEGUARDS 2.1 Administrative Organizations and Controls (a) Manager - Nuclear Plant c.y The' Manager - Nuclear Plant of Peach' Bottom shall have the responsibility for administration of all Unit No. 1 functions.
(b) Controls
- 1. Except when opened to provide egress for inspections, surveys and repairs, the following exclusion area barriers shall be maintained locked:
- 1. The gate in the Exclusion Area. fence located outside the containment personnel access lock at Elevation 116'-0".
l fa R 5i g g .,, -
PDR
'1 f.
App 3ndix A Page 2
- 11. The gate in the Exclusion Area fence located outside the Spent Fuel Pool Area personnel door at Elevation 116'-0".
iii. The gate in the Exclusion Area fence located outside the containment personnel access lock on Elevation 176'-6" iv. Containment personnel access lock at Elevation 176'-6"
- v. Containment personnel access lock at Elevation 116'-0" vi. Grating over southwest stairway leading from refueling floor of Containment to Containment lower levels vii. Personnel door into Spent Fuel Pool Area at Elevation 116'-0" viii. Radwaste Room personnel door at Elevation 104'0"
- 2. Employees of the Peach Bottom Atomic Power Station shall report to the Peach Bottom Manager - Nuclear Plant or his designated representative any observed indication of change in facility status as shown by smoke, fire, tornado, flood or attempted break-in and take any immediate action authorized.
- 3. Administrative procedures shall be established for the notification and reporting of the following events:
- 1. The entrance of an unauthorized person (s) into the facility.
ii. A significant change in the radiation or contamination levels in the facility.
- 4. Security of the facility shall be included as a part of the Peach Bottom Atomic Power Station security plan.
Appendix A. Paga 3
- 5. In the event of a Probable Maximum Flood, the personnel access door will be opened in accordance with the Peach Bottom Atomic Power Station Units 2 and 3 flood procedures.
2.2 Records Licensee shall keep logs and records in sufficient scope and detail to establish that the facility is being maintained within the limitations of the Part 50 Possession Only license. The following items shall be recorded:
(a) Facility radiation surveys (b) Inspections of the physical barriers (c) Reportable events 2.3- Pe'r iodic Inspections A definite inspection schedule shall be established for the Unit No. 1 facility that will be performed by personnel knowledgeable in nuclear radiation monitoring and with the radiological hazards associated with-the decommissioned. plant. Inspections of the plant will be conducted concurrently with radiation monitoring. The frequency of these inspections shall be no less than seminannua'lly. The records of these inspections shall be maintained on file.
The inspection shall include a survey of radiation levels and surface contamination as well as air particulate activity in uncontrolled areas in the containment vessel. The filter on the ventilation
" breather" tube from the containment vessel shall also be changed annually and surveyed for activity.
If entry and/or work in the controlled area of the containment should be necessary, radiation level and airborne activity surveys shall be performed prior to beginning work and all work shall be performed under controls, as appropriate, to minimize the radiation exposure of personnel and to prevent the release of radioactivity to the environment.
All radiation surveys, tests, counting work and radiation exposure control measures shall be performed
'in accordance with written instructions and procedures that conform with the requirements of the Peach Bottom
.' f ; 4f-CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Amendment were served on
.the following by deposit in the United States mail,.first-class' postage prepaid, on this 4th day of March,1987.
Regional Administrator U.S. Nuclear Regulatory Commission, Region I 631 Park Avenue King of Prussia,'PA 19406 T. P. Johnson, Resident Inspector U. S. Nuclear Regulatory Commission Peach Bottom Atomic Power Station P. O. Box 399 Delta, PA 17314 Mr. Thomas Gerusky, Director Bureau of Radiation Protection Department of Environmental Resources Fulton Bank-Building, 5th Floor Third 4 Locusts Streets Harrisburg, PA 17120 l
a
/
EugenpJ./Bradley (
Attorney for Philadelphia Electric Company
. .