Amends 157 & 148 to Licenses NPF-10 & NPF-15,respectively, Consisting of Changes to TS 3.3.5, ESFAS Instrumentation, in Response to 981231 Application & Suppl
ML20212A232
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 09/07/1999
From: Stephen Dembek
NRC (Affiliation Not Assigned)
To:
Shared Package
ML20212A236 List:
References
NUDOCS 9909160124
Download: ML20212A232 (14)


Text

Smurag 1

UNITED STATES f

j NUCLEAR RERULATORY COMMIDSION

,2 CASHINGTON, D.C. 2066H001 e%...../

SOUTHERN CALIFORNIA EDISON COMPANY SAN DIEGO GAS AND ELECTRIC COMPANY THE CITY OF RIVERSIDE. CALIFORNIA THE CITY OF ANAHEIM. CAllFORNIA, DOCKET NO. 50-361 i

SAN ONOFRE NUCLEAR GENERATING STATION. UNIT 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.157 License No. NPF-10 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Southem Califomia Edison Company, et al.

l (SCE or the licensee), dated December 31,1998, as supplemented June 14, 1999, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; l

D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendmentis in accordance with 10 CFR Part 51'of the Commission's regulations and all applicable requirements have been satisfied.

9909160124 990907 PDR ADOCK 05000361 P

PDR

, 2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C(2) of Facility Operating License No. NPF-10 is hereby amended to read as follows:

(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No.

157, are hereby incorporated in the license. Southern Califomia Edison Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3.

This license amendment is effective as of its date of issuance and shall be implemented within 30 days of its issuance.

FOR THE NUCLEAR REGULATORY COMMISSION Step en Dembek, Chief, Section 2 Project Directorate IV & Decommissioning Division of Licensing Project Management Office of Nuclear Reactor Regulation Date ofissuance: September 7,1999

l ATTACHMENT TO LICENSE AMENDMENT NO.157 FACILITY OPERATING LICENSE NO. NPF-10 DOCKET NO. 50-361 Replace the following pages of the Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal l

lines indicating the areas of change.

REMOVE INSERT 3.3-22 3.3-22 3.3-23 3.3-23 l

3.3-24 3.3-24 3.3-25 3.3-25 l

1 f-4 l

i 1

l l

l l

l l

l l

o L.

1 l

)

i ESFAS Instrumentation 3.3.5 3.3 INSTRUMENTATION 3.3.5 Engineered Safety Features Actuation System (ESFAS) Instrumentation LC0 3.3.5 Four ESFAS tri) and bypass removal channels for each function in Ta)le 3.3.5-1 shall be OPERABLE.

l APPLICABILITY:

According to Table 3.3.5-1.

ACTIONS


NOTES------------------------------------

i l

1.

Separate Condition entry is allowed for each ESFAS Function.

2.

If a channel is placed in by) ass, continued operation with the channel in 1

the bypassed condition for t1e Completion Time s)ecified by Required Action A.2, B.2, or E.2.2 shall be reviewed by tie Onsite Review l

Committee.

CONDITION REQUIRED ACTION COMPLETION TIME A.

One or more functions A.1 Place Functional Unit I hour with one automatic in bypass or trip.

ESFAS trip channel inoperable (other than AHQ RWST Level-Low for the l

RAS function or SG A.2 Restore channel to Prior to Pressure-Low or SG OPERABLE status, entering MODE 2 Pressure Difference-following next l

High for the EFAS MODE 5 entry function).

l l

B. 'One automatic trip B.1 Place Functional Unit I hour channel inoperable for in bypass.

RWST Level-Low for the RAS function or SG ARQ Pressure-Low or SG Pressure Difference-B.2 Restore channel to Prior to High for the EFAS OPERABLE status, entering MODE 2 function.

following next l

MODE 5 entry (continued) l 1

l SAN ONOFRE--UNIT 2 3.3-22 Amendment No.157 i

I(..

ESFAS Instrumentation 3.3.5 ACTIONS (continued)

CONDITION

~ REQUIRED ACTION COMPLETION TIME C.

.One or more Functions C.1


NOTE---------

l l

with two automatic LCO 3.0.4 is not ESFAS trip channels applicable.

inoperable (other than RWST Level-Low for the RAS function Place one Functional I hour

.or SG Pressure-Low or Unit in bypass and SG Pressure the other in trip.

Difference-High for the EFAS Function).

l D.

Two automatic ESFAS D.1


NOTE---------

trip channels LC0 3.0.4 is not inoperable for RWST applicable.

Level-Low for the RAS l

function or SG l

Pressure-Low or SG Place one Functional I hour 1

Pressure Difference-Unit in bypass and High for the EFAS the other in trip.

function.

&HQ' I

D.2 Restore one affected 7 days automatic trip channel to OPERABLE i

status.

)

l l

E.

One or more Functions E.1 Disable bypass l' hour l

with one automatic

channel, bypass removal l-channel inoperable.

QR E.2.1 Place affected I hour l

automatic trip channel in bypass or trip.

1 AHQ E.2.2 Restore bypass Prior to l

removal channel and entering MODE 2 associated automatic following next trip channel to MODE 5 entry OPERABLE status.

(continued) 1-SAN ONOFRE--UNIT 2 3.3-23 Amendment No. 157

r ESFAS Instrumentation 3.3.5

. ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME F.

One or more Functions


NOTE-------------

with two automatic LCO 3.0.4 is not applicable.

bypass removal channels inoperable.

F.1 Disable bypass I hour l

channels.

DE 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> F.2 Place one affected l

automatic trip channel in bypass and place the other in trip.

G.

Required Action and G.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> l

associated Completion Time for Safety

&HQ Injection Actuation Signal, Containment G.2 Be in MODE 4.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> l

Spray Actuation Signal, Containment

-Isolation Actuation Signal, Main Steam

. Isolation Signal, or Emergency Feedwater Actuation Signal not i

met.'

)

1 H.

Required Action and H.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> l

associated Completion Time for Recirculation

&HQ

. Actuation Signal not met.

H.2 Be in MODE 5.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> l

1 i

i l

SAN ONOFRE--UNIT 2 3.3-24 Amendment No.157

.p' ESFAS Instrumentation 3.3.5 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.3.5.1 Perform a CHANNEL CHECK of each ESFAS 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> channel.

SR 3.3.5.2' Perform a CHANNEL FUNCTIONAL TEST of each 30 days on a ESFAS channel.

STAGGERED TEST BASIS SR 3.3.5.3 Perform a CHANNEL FUNCTIONAL TEST of each 120 days ESFAS channel bypass removal function.

SR 3.3.5.4 Perform a CHANNEL CALIBRATION of Function 18 months 5, Recirculation Actuation Signal.

SR 3.3.5.5 Perform a CHANNEL CALIBRATION of each ESFAS 24 months che.nnel, with the exception of Function 5, including bypass removal functions.

SR 3.3.5.6 Verify ESF RESPONSE TIME is within limits.

24 months on a STAGGERED TEST BASIS

'SR 3.3.5.7 Perfom a CHANNEL FUNCTIONAL TEST on each Once within automatic bypass removal channel.

120 days prior to each reactor startup SAN ONOFRE--UNIT 2 3.3-25 Amendment No.157

pag g g

UNITED STATES g

j NUCLEAR REGULATORY COMMISSION A'

WASHINGTON, D.C. 20666 0001

'+,.....,o SOUTHERN CALIFORNIA EDISON COMPANY SAN DIEGO GAS AND ELECTRIC COMPANY THE CITY OF RIVERSIDE. CALIFORNIA THE CITY OF ANAHEIM. CALIFORNIA DOCKET NO. 50-362 SAN ONOFRE NUCLEAR GENERATING STATION. UNIT 3 AMENDMENT TO FACILITY OPERATING LICENSE i

f Amendment No.148 License No. NPF-15 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Southem Califomia Edison Company, et al.

(SCE or the licensee), dated December 31,1998, as supplemented June 14, 1999, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

I L

2-2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C(2) of Facility Operating License No. NPF-15 is hereby amended to read as follows:

(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No.148, are hereby incorporated in the license. Southern California Edison Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3.

This license amendment is effective as of its date of issuance and shall be implemented within 30 days of its issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

)

Stephen Dembek, Chief, Section 2 Project Directorate IV & Decommissioning Division of Licensing Project Management Office of Nuclear Reactor Regulation Date ofIssuance: September 7,1999

4 ATTACHMENT TO LICENSE AMENDMENT NO.148 j

FACILITY OPERATING LICENSE NO. NPF-15 DOCKET NO. 50-362 Replace the following pages of the Appendix A Technical Specifications with the attached I

revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

REMOVE INSERT 3.3-22 3.3-22 3.3-23 3.3-23 3.3-24 3.3-24 3.3-25 3.3-25 i

t i

l t

l

ESFAS Instrumentation 3.3.5 j

3.3 INSTRUMENTATION-3.3.5 Engineered Safety Features Actuation System (ESFAS) Instrumentation LCO 3.3.5 Four ESFAS trip and bypass removal channels for each Function in Table 3.3.5-1 shall be OPERABLE.

APPLICABILITY:

According to Table 3.3.5-1.

ACTIONS


NOTES------------------------------------

1.

Separate Condition entry is allowed for each ESFAS Function.

2.

If a channel is placed in by) ass, continued operation with the channel in the bypassed condition for t1e Completion Time specified by Required Action A.2, B.2, or E.2.2 shall be reviewed by the Onsite Review l

Committee.

CONDITION REQUIRED ACTION COMPLETION TIME A.

One or more Functions A.1 Place Functional Unit I hour with one automatic in bypass or trip.

ESFAS trip channel inoperable (other than AND RWST Level-Low for the RAS function or SG A.2 Restore channel to Prior to Pressure-Low or SG OPERABLE status.

entering MODE 2 Pressure Difference-following next High for the EFAS MODE 5 entry function).

B.

One automatic trip B.1 Place Functional Unit I hour channel inoperable for in bypass.

RWST Level-Low for the RAS function or SG ANQ Pressure-Low or SG Pressure Difference-B.2 Restore channel to Prior to High for the EFAS OPERABLE status.

entering MODE 2 function.

following next MODE 5 entry (continued)

SAN ONOFRE--UNIT 3 3.3-22 Amendment No. 148

i ESFAS Instrumentation 3.3.5 LACTIONS.(continued)

CONDITION REQUIRED ACTION COMPLETION TIME C.

One or more functions C.1


NOTE---------

l with two automatic LC0 3.0.4 is not 1

ESFAS trip channels applicable.

l inoperable (other l

than RWST Level-Low for the RAS function Place one Functional I hour or SG Pressure-Low or Unit in bypass and SG Pressure the other in trip.

Difference-High for the EFAS Function).

D.

'Two automatic ESFAS D.1


NOTE---------

trip channels LCO 3.0.4 is not inoperable for RWST applicable.

Level-Low for the RAS function or SG Pressure-Low or SG Place one Functional I hour Pressure Difference-Unit in bypass and High for the EFAS the other in trip.

function.

Ali2 D.2 Restore one'affected 7 days automatic trip channel to OPERABLE status.

E.-

One or more Functions E.1 Disable bypass I hour l

with one automatic channel.

bypass removal-channel inoperable.

DE E.2.1 Place affected I hour l

automatic trip channel in bypass or i

trip.

E Prior to l

Restorebkpass E.2.2 removal c annel and entering MODE 2 i

associated automatic following next trip channel to MODE 5 entry OPERABLE status.

l (continued)

SAN ON0FRE--UNIT 3-3.3-23 Amendment No.148

s

i ESFAS Instrumentation 3.3.5 J

' ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME F.

One or more Functions


NOTE-------------

l with two automatic LCO 3.0.4 is not applicable.

bypass removal channels inoperable.

F.1 Disable bypass channels.

I hour l

DR F.2 Place one affected I hour l

automatic trip channel in bypass and place the other in trip.

1 G.

Required Action and G.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> l

I associated Completion Time for Safety AHQ Injection Actuation Signal, Containment G.2 Be in MODE 4.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> l

Spray Actuation j

Signal, Containment Isolation Actuation i

Signal, Main Steam Isolation Signal, or i

Emergency Feedwater-Actuation Signal not met.

H.

Required Action and H.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> l

associated Completion Time for AND Recirculation Actuation Signal not H.2 Be in MODE 5.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> l

met.

i l

SAN ONOFRE--UNIT 3 3.3-24 Amendment No.148 i

.J ESFAS Instrumentation 3.3.5 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.3.5.1 Perform a CHANNEL CHECK of each ESFAS 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> channel.

SR 3.3.5.2 Perform a CHANNEL FUNCTIONAL TEST of each 30 days on a ESFAS channel.

STAGGERED TEST BASIS SR 3.3.5.3 Perform a CHANNEL FUNCTIONAL TEST of each 120 days ESFAS channel bypass removal function.

SR 3.3.5.4 Perform a CHANNEL CALIBRATION of Function 18 months 5, Recirculation Actuation Signal.

SR 3.3.5.5 Perform a CHANNEL CALIBRATION of each ESFAS 24 months channel, with the exception of Function 5, including bypass removal functions.

.SR 3.3.5.6 Verify ESF RESPONSE TIME is within limits.*

24 months on a STAGGERED TEST BASIS SR 3.3.5.7 Perform a CHANNEL FUNCTIONAL TEST on each Once within automatic bypass removal channel.

120 days prior to each reactor startup

  • Verification of the RESPONSE TIME of the 30 subgroup relays identified in the February 18, 1997 Edison letter is not ap)11 cable until return to Mode 4 from the Unit 3 Cycle 9 refueling outage, wit) the additional commitments made in the February 18, 1997 letter. The safety justification for not performing this testing is also included in the February 18, 1997 letter.

SAN ONOFRE--UNIT 3 3.3-25 Amendment No.148 i