OPERATINC DATA REPORT DOCKET NO. 050-400 DATE 12/5/86 COMPLETED BY J. H. Westmoreland TELEPHONE (919) 362-2597 OPERATING STATUS

1. Unit Name: Shearon Harris Unit 1
2. Reporting Period: November 1986 Notes:
3. Licensed Thermal Power (MWt):

2775 Fuel load completed

4. Nameplate Rating (Cross MWe):

950 11/21/86; 157 Fuel

5. Design Electrical Rating (Net-MWe): 900 Assemblies are in the

]

6. Maximum Dependable Capacity (Cross-MWe): 950 Reactor Vessel.

'7. Maximum Dependable Capacity (Net-MWe): 900

8. If Changes Occur in Capacity Ratings (Item Numbers 3 Through 7) Since Last Report, Give Reasons: N/A
9. Power Level to Which Restricted, If Any (Net-MWe):

0 MWe-Net; Unit Restricted to 5% Thermal Power by NRC License

[

10. Reasons for Restrictions, If Any: Operating License Restricted to 5%

Harris Unit 1 is in Start-up/ Power Ascension Test Phase.

This Month Yr.-to-Date Cumulative

11. Hours in Report Period 0

0 0

12. Number of Hours Reactor Was Critical 0

0 0

13. Reactor Reserve Shutdown Hours 0

0 0

14. Hours Generator On-Line 0

0 0

15. Unit Reserve Shutdown Hours 0

0 0

16. Cross Thermal Energy Generated (MWH) 0 0

0

17. Cross Electrical Energy Generated (MWH) 0 0

0

18. Net Electrical Energy Generated (MWH) 0 0

0

19. Unit Service Factor N/A N/A N/A
20. Unit Availability Factor N/A N/A N/A
21. Unit Capacity Factor (Using MDC Net)

N/A N/A N/A

22. Unit Capacity Factor (Using DER Net)

N/A N/A N/A

23. Unit Forced Outage Rate N/A N/A N/A
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
25. If Shutdown at End of Report Period, Estimated Date of Start Up:
26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY 12/26/86 N/A INITIAL ELECTRICITY 01/08/37 N/A COMMERCIAL OPERATION 03/04/87 N/A 86152170338 861130 PDR ADOCK 05000400 R

PDR

.t.

MEM/H08634640/ PACE 2/OSI

'CP&L CO.:

PLANT PERFORMANCE DATA SYSTEM APPENDIX B - AVERAGE DAILY POWER LEVEL HARRIS UNIT 1 DOCKET NO. 050-400 COMPLETED BY J. H. WESTMORELAND TELEPHONE (919)362-2597 NOVEMBER 1986 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET)

(MWE-NET) 1 0

17 0

2 0

18 0

3 0

19 0

4 0

20 0

5 0

21 0

6 0

22 0

7 0

23 0

8 0

24 0

9 0

25 0

10 0

26 0

11 0

27 0

12 0

28 0

13 0

29 0

14 0

30 0

15 0

16 0

1.16 - 8 CEH086/ attach 3464/2/OS4

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.:

050-400 f

UNIT NAME:

Harris l

DATE:

12/5/86 CONPLETED BY:

J. H. Westmoreland REPORT.NONTH: November 1986 TELEPHONE:

(919) 362-2597 i

op Licensee y,n Cause & Corrective c-n No.

Date oa gg Event 3

Action to e

yj ygm Report #

o Prevent Recurrence o

y o"

S;

'50 E

E"5{

"o n

o x

mu u

N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A l

i

\\

k t

k

's

\\,.

Reason:k 1

2 3

4 F: Forced

(

Nethod:

Exhibit C-Instructions S: Scheduled A-Equipnwnt Failure (Explain) 1-Hanual for Preparation of Data B-Maint4 nance or Test 2-Manual Scrant.

Entry Sheets for Licensee C-Refueling 3-Automatic Scram.

Event Report (LER) File D-Regulaitory Restriction 4-Continued (NUREC-0161)

E-Operai:or Training & License Examination 5-Reduced Load F-Admin-istrative 6-Other 5

C-Operai:lonal Error (Explain)

Exhibit 1-Same Source if-Other (Explain) i b

I CEH086/ attach 3464/3/0S4 l

\\

\\

Cp&L Carolina Power & Light Company HARRIS NUCLEAR PROJECT P. O. Box 165 New Hill, North Carolina 27562 DEC 121966 File Number: SHF/10-15505 Letter Number: HO-863464 (0)

Mr. James M. Taylor, Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 HARRIS NUCLEAR PROJECT DEPARTMENT UNIT NO. 1 DOCKET No. 50-400 LICENSE NO. NPF-53 MONTHLY OPERATIONS REPORT

Dear Mr. Taylor:

In accordance with Technical Specifications 6.9.1.5 for the Harris Nuclear Plant, Unit No. 1, Carolina Power & Light Company herewith submits the report of operation statistics and shutdown experience for the month of November, 1986.

Very truly yours, E

R. A. Watson Vice President Harris Nuclear Project MWH:bb Enclosure cc: