Forwards Safety Evaluation Re Util 840413 & 850701 Responses to Reg Guide 1.97, Emergency Response Capability. Responses Acceptable.Requests Addl Info Re Instrument Range of RCS Pressure Instrumentation within 60 Days
ML20211G109
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 10/23/1986
From: Richard Lee
Office of Nuclear Reactor Regulation
To: Tison Campbell
ARKANSAS POWER & LIGHT CO.
Shared Package
ML20211G114 List:
References
RTR-REGGD-01.097, RTR-REGGD-1.097 NUDOCS 8611030204
Download: ML20211G109 (2)


Text

I 1

Docket No.: 50-368 Mr. T. Gene Campbell Vice President Nuclear Operations Arkansas Power & Light Company Post Office Box 551 Little Rock, Arkansas 72203

Dear Mr. Campbell:

SUBJECT:

EMERGENCY RESPONSE CAPABILITY - REGULATORY GUIDE 1.97 The Commission has completed the review of your responses dated April 13, 1984 and July 1, 1985 pertaining to the above subject matter for the Arkansas Nuclear One, Unit 2. Our evaluation concludes that your responses are acceptable.

However, there are two items for which we do not have adequate information.

The two items relate to the instrument rar.ge of the reactor coolant system pressure instrumentation and the lack of instrumentation to monitor containment sump water temperature. We request that you provide the additional information to resolve our concerns detailed in our Safety Evaluation related to the above-stated items within 60 days of receipt of this letter. Our Safety Evaluation with attached Technical Evaluation Report is enclosed.

The reporting and/or recordkeeping requirements contained in this letter affect fewer than ten respondents. Therefore, OMB clearance is not required under P.L.96-511.

Please contact us if your have any questions concerning this letter.

Sincerely, Isl Robert S. Lee, Project Manager PWR Project Directorate No. 7 Division of PWR Licensing-B

Enclosure:

N O3o204 e61023ApocK0500$8 As stated P

cc: See next page DISTRIBUTION:

Docket File F. Miraglia J. Partlow NRC PDR OGC-Bethesda N. Thompson LPDR E. Jordan R. Lee PD7 Reading B. Grimes j

J. Lee ACRS (10) k M

$ndhton 10/.

6 10/22B6 10/p/86 La uvenul 0he PYoAMo&-

~

Mr. T. Gene Campbell Arkansas Nuclear One Arkansas Power & Light Company Unit No. 2 cc:

Mr. J. Ted Enos, Manager Mr. Charlie B. Brinkman, Manager Nuclear Engineering and Licensing Washington NuclearOperations Arkansas Power and Light Company C-E Power Systems P. O. Box 551 7910 Woodmont Avenue Little Rock, Arkansas 72203 Suite 1310 Bethesda, Maryland 20814 Mr. James M. Levine, Director Site Nuclear Operations Arkansas Nuclear One P. O. Box 608 Russellville, Arkansas 72801 Nicholas S. Reynolds, Esq.

Bishop, Liberman, Cook, Purcell & Reynolds 1200 Seventeenth Street, N.W.

Suite 700 Washington, D.C.

20036 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Office of Executive Director for Operations 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Senior Resident Inspector U.S. Nuclear Regulatory Consnission P. O. Box 2090 Russellville, Arkansas 72801 Mr. Frank Wilson, Director Division of Environmental Health Protection Arkansas Department of Health 4815 West Markam Street Little Rock, Arkansas 72201 Mr. Robert B. Borsum Babcock & Wilcox huclear Power Generation Division Suite 220 7910 Woodmont Avenue Bethesda, Maryland 20814

.