Concurs w/861023 Request to Extend Until 861124 Response to Generic Ltr 86-06, Implementation of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pumps
ML20211G089
Person / Time
Site: Calvert Cliffs  
Issue date: 10/29/1986
From: Thadani A
Office of Nuclear Reactor Regulation
To: Tiernan J
BALTIMORE GAS & ELECTRIC CO.
References
TASK-2.K.3.05, TASK-TM GL-86-06, GL-86-6, NUDOCS 8611030173
Download: ML20211G089 (2)


Text

October 29, 1986 i

Distribution,

Docket Nos. 50-317 Docket File w '

NThompson and 50-318 "NRC/ Local PDR PKreutzer PBD8 Reading SAMcNeil FMiraglia ACRS (10)

FShroeder 0GC-Bethesda Mr. J. A. Tiernan JPartlow Vice President-Nuclear Energy EJordan Baltimore Gas & Electric Company BGrimes P. O. Box 1475 Gray File 3.2a Baltimore, MD 21203

Dear Mr. Tiernan:

SUBJECT:

EXTENSION OF CALVERT CLIFFS DATE OF RESPONSE TO GENERIC LETTER NO. 86-06, " IMPLEMENTATION OF THE TMI ACTION ITEM II.K.3.5, AUTOMATIC TRIP 0F REACTOR COOLANT PUMPS" The NRC has reviewed your October 23, 1986 request for extension to November 24, 1986 in responding to Generic Letter (GL) 86-06.

The October 23, 1986 submittal provided all of the information requested in GL 86-06 with the exception of the subcooled margin monitor's (SMM) loop uncertainties.

Furthermore, the NRC understands that the SMM loop uncertainties which you are developing cover a wider range of primary temperatures than the information provided by Combustion Engineering.

Consequently, the NRC deems that your requested extension to November 24, 1986, for providing the SMM loop uncertainties is justified.

As such, the NRC concurs in extending the response date for the SMM loop uncertainties to November 24, 1986.

Sincerely,

/s/

Ashok C. Thadani, Director PWR Project Directorate #8 Division of PWR Licensing-B cc: See next page W

PBD-8:

PBD PBD-8:

00: PLB Div:

B PJ gutzer SAJkMItil:jch AThap/86 ani FShroeder FMiraglia 10/q /86 10/ 0 )'86 10/2, )

104p/86 10/4f86 8611030173 861029 PDR ADOCK 05000317 P

PDR

Mr. J. A. Tiernan Baltimore Gas & Electric Company Calvert Cliffs Nuclear Power Plant cc:

Mr. William T. Bowen, President Regional Administrator, Region I Calvert County Board of U.S. Nuclear Regulatory Commission Commissioners Office of Executive Director Prince Frederick, Maryland 20768 for Operations 631 Park Avenue D. A. Brune, Esq.

King of Prussia, Pennysivania 19406 General Counsel Baltimore Gas and Electric Company P. O. Box 1475 Baltimore, Maryland 21203 Jay E. Silberg Shaw, Pittman, Potts and Trowbridge 2300 N Street, N.W.

Washington, DC 20037 Mr. M. E. Bowman, General Supervisor Technical Services Engineering Calvert Cliffs Nuclear Power Plant MD Rts 2 & 4, P. O. Box 1535 Lusby, Maryland 20657-0073

- Resident Inspector c/o U.S. Nuclear Regulatory Commission P. O. Box 437 Lusby, Maryland 20657-0073

/

Bechtel Power Corporation ATTN:

Mr. D. E. Stewart Calvert Cliffs Project Engineer 15740 Shady Grove Road Gaithersburg, Maryland 20760 Combustion Engineering, Inc.

ATTN:

Mr. W. R. Horlacher, III Project Manager P. O. Box 500 1000 Prospect Hill Road Windsor, Connecticut 06095-0500 Department of Natural Resources Energy Administration, Power Plant Siting Program ATTN:

Mr. T. Magette Tawes State Office Building Annapolis, Maryland 21204

October 29, 1986 1

Distribution Docket Nos. 50-317 Docket File NThompson i

and 50-318 NRC/ Local PDR PKreutzer PBD8 Reading SAMcNeil FMiraglia ACRS (10)

FShroeder OGC-Bethesda Mr. J. A. Tiernan JPartlow Vice President-Nuclear Energy EJordan Baltimore Gas & Electric Company BGrimes P. O. Box 1475 Gray File 3.2a Baltimore, MD 21203

Dear Mr. Tiernan:

SUBJECT:

EXTENSION OF CALVERT CLIFFS DATE OF RESPONSE TO GENERIC LETTER NO. 86-06, " IMPLEMENTATION OF THE TMI ACTION ITEM II.K.3.5, AUTOMATIC TRIP OF REACTOR COOLANT PUMPS" The NRC has reviewed your October 23, 1986 request for extension to November 24, 1986 in responding to Generic Letter (GL) 86-06.

The October 23, 1986 submittal provided all of the information requested in GL 86-06 with the exception of the subcooled margin monitor's (SMM) loop uncertainties.

Furthermore, the NRC underrotands that the SMM loop uncertainties which you are developing cover a wider range of primary temperatures than the information provided by Combustion Engineering.

Consequently, the NRC deems that your requested extension to November 24, 1986, for providing the SMM loop uncertainties is justified. As such, the NRC concurs in extending the response date for the SMM loop uncertainties to November 24, 1986.

Sincerely,

/s/

Ashok C. Thadani, Director PWR Project Directorate #8 Division of PWR Licensing-B cc: See next page PBD-8:

PBD-8; PBD-6:

'DD: PLB Div.

B PJyutzer SA)4c2911:jch ani FShroeder FMiraglia 10/q /86 10/R7/86 AThap/86 10/4f86 10/1}