Advises That Info Provided in Listed Submittals Re Inservice Insp During Winter 1986 Refueling Outage Acceptable. Documents 870119 Verbal Authorization to Commence Startup
ML20211F854
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 02/17/1987
From: Rajender Auluck
Office of Nuclear Reactor Regulation
To: Farrar D
COMMONWEALTH EDISON CO.
References
TAC-64338, TAC-64484, NUDOCS 8702250215
Download: ML20211F854 (2)


Text

_

d

  • Docket No. 50-265 DISTRIBUTION: RDiggs

-Docket File Glainas NRC PDR'~ OGC-Bethesda (info)

Local PDR RBernero Mr. Dennis L. Farrar CJamerson EJordan Director of Nuclear Licensing TRote11a BGrimes Commonwealth Edison Company JZwolinski JPartlow Post Office Box 767 RHermann NThompson Chicago, Illinois 60690 WKoo ACRS (10)

WHazelton BWD1 R/F

Dear Mr. Farrar:

BLiaw QC File

SUBJECT:

INSERVICE INSPECTION INFORMATION REVIEW FOR UNIT-2 RESTART (TACS 64338, 64484)

Reference:

Quad Cities Nuclear Power Station, Unit 2 By submittals dated December 24 and 30, 1986 and January 15 and 19,1987, Commonwealth Edison Company (CECO) provided NRC staff with certain Inservice Inspection Information for Quad Cities Nuclear Power Station, Unit 2. Specifically, this information provided a description of pipe weld flaws found, analytical evaluation results, and repair actions taken during the Winter 1986 Refueling Outage.

NRC staff has completed a preliminary review of the information provided and has concluded that restart of Quad Cities Nuclear Powe:r Station, Unit 2 is acceptable. This letter serves to document our verbal authorization, given on January 19, 1987, to commence startup from the Winter 1986 Refueling Outage for Quad Cities Nuclear Power Station, Unit 2.

A final Safety Evaluation will be issued by NRC staff regarding the long term acceptability of your pipe repairs.

If you should have any questions regarding the above discussion or require additional information, please contact Thomas S. Rotella, NRC Project Manager, Quad Cities Nuclear Power Station.

Sincerely, Original signed by 0702250215 870217 Rajender Auluck, Acting Director ADOG 0500 BWR Project Directorate #1

$DR Division BWR Licensing Office of Nuclear Reactor Regulation cc: See next page DL:BWD1 DL: BWD D1 CJamersorh TRote11a:ac . uluck 02/M/87 , 02/d/87 02/p/87

l I

Mr. Dennis L. Farrar Quad Cities Nuclear Power Station i Comonwealth Edison Company Units 1 and 2 I cc:

Mr. B. C. O'Brien J President Iowa-Illinois Gas and Electric Company 206 East Second Averue Davenport, Iowa 52801 Mr. Michael I. Miller Isham, Lincoln & Beale Three First National Plaza Suite 5200 Chicago, Illinois 60602 Mr. Nick Kalivianakis Plant Superintendent Quad Cities Nuclear Power Station 22710 - 206th Avenue - North Cordova, Illinois 61242 Resident Inspector U. S. Nuclear Regulatory Commission 22712 206th Avenue North Cordova, Illinois 61242 Chairman Rock Island County Board of Supervisors Rock Island County Court House Rock Island, Illinois 61201 Mr. Michael E. Parker Division of Enaineering Illinois Department of Nuclear Safety 1035 Outer Park Drive, 5th Floor Springfield, Illinois 62704 Regional Administrator, Region III U. S. Nuclear Regulatory Comission 799 Roosevelt Road Glen Ellyn, Illinois 60137