Responds to 860724 Request for Antitrust Info Per Reg Guide 9.3.Util Currently Has Excess in Generating Capacity Resources Not Expected When Texas Municipal Power Agency Became Permittee of Unit 1 CP
ML20211D039
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/06/1986
From: Tartt B
FULBRIGHT & JAWORSKI, TEXAS MUNICIPAL POWER AGENCY
To: Funches J
Office of Nuclear Reactor Regulation
References
CON-#190-9851, RTR-REGGD-09.003, RTR-REGGD-9.003 A, NUDOCS 8610220085
Download: ML20211D039 (3)


Text

?

.s F U L B R I G H T & J AWO R S K I 1301 McKinney Street Hous:on Houstors Texas 17010 Washingtors D.C Austin Telephone: 713 661,5151 San Anterno Telen: 76-2829 Deltas

~,

london Zurich October 6, 1986 Re:

Comanche Peak Steam Electric Station, Unit I, Docket No. 50-445A; Antitrust Operating License Review.

Mr. Jesse L. Funches, Director Planning and Program Analysis Staff Office of Nuclear Reactor Regulation Nuclear Regulatory Commission 1717 H Street, N.W.

Washington, D.

C.

20036

Dear Mr. Funches:

In accordance with your letter of July 24, 1986, the following is Texas Municipal Power Agency's response to your request for information under Regulatory Guide 9.3:

a.

Anticipated excess or shortage in gen-erating capacity resources not expected at

'the construction permit stage.

Reasons for the excess or. shortage along with data on how the excess will be allocated, distrib-

uted, or otherwise utilized or how the shortage will be obtained.

Texas Municipal Power Agency (TMPA) currently finds itself with an excess in generating capacity resources not expected at the time it became one of the permittees of the Unit I

construction permit.

This' excess occurred because the cities which created TMPA have not grown at the rate projected at the time TMPA became a

permittee.

TMPA estimates that if either Unit 1 or Unit 2 are not completed, it will need additional power by 1994.

8610220085 861006 PDR ADOCK 05000445 M

PDR

'n

'v o

i a

Mr. Jesse L. Funches, Director October 6, 1986 Page 2 b.

New power pools or coordinating groups or changes in structure, activities, poli-cies,.

practices, or

. membership. of power pools or coordinating groups in which the licensee was, is, or will be a participant.

No significant changes have occurred since TMPA became a permittee.

c.

Changes in transmission with respect to (1) the nuclear plant, (2) interconnections, or (3) connections to wholesale customers.

Unit 1 did not become operational in late 1981, as TMPA was led to believe when it purchased its interest in the plant.

Otherwise, no significant changes have occurred since TMPA became a permittee.

d.

Changes in the ownership or contractual allocation of the output of the nuclear facility.

Reasons

~ and basis for such changes should be included.

No significant changes have occurred since TMPA became a permittee.

e.

Changes in

design, provisions, or conditions of rate schedules and reasone :or such changes.

Rate increases or decreases are not necessary.

No significant changes have occurred since TMPA became a permittee.

f.

List of all (1) new wholesale custo-

mers, (2) transfers from one rate schedule to
another, including copies of schedules not previously furnished, (3) changes in licensee's service. area, and (4) licensee's acquisitions. or c:ergers.

No significant changes have occurred since TMPA became a permittee.

' 4 g

Mr. Jesse L. Funches, Director

. October 6, 1986 Page 3 g.

List of those generating capacity addi-tions committed for operation of the nuclear

facility, including ownership rights or power output allocations.

No significant changes have occurred -since TMPA became a permittee.

h.

Summary of requests or indications of interest by other electric power wholesale or retail distributors, and licensee's re-sponse, for any type of electric service or cooperative venture or study.

TMPA routinely receives requests from other elec-tric utilities concerning participation in cooperative ventures.

These requests are evaluated on. a case by case basis.

Since~TMPA has become a permittee, TMPA has not' elected to participate in any such offer.

We apologize for the delay in getting this information to you.

Please let us know if there is any other information you need.

4 Very truly yours, SW Blake Tar t BT:dc l