ML20211A292

From kanterella
Jump to navigation Jump to search
Insp Repts 50-321/86-29 & 50-366/86-39 on 861115-21. Violation Noted:Overall Integrated Leak Rate for as-found Containment Condition Could Not Be Determined Due to Failure to Measure Change in Leakage Rate
ML20211A292
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 02/02/1987
From: Jape F, Witener H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20211A236 List:
References
50-321-86-39, 50-366-86-39, NUDOCS 8702190139
Download: ML20211A292 (8)


See also: IR 05000321/1986029

Text

.

p Kf20

UNITED STATES

g

9'o

NUCLEAR REGULATORY COMMISSION

y"

REGloN 11

3

g

j

101 MARIETTA STREET, N.W.

  • '-

'*

ATL ANTA, GEORGI A 30323

\\...../

Report Nos.:

50-321/86-39 and 50-366/86-39

Licensee: Georgia Power Company

P. O. Box 4545

Atlanta, GA 30302

Docket Nos.:

50-321 and 50-366

License Nos.: DPR-57 and NPF-5

Facility Name: Hatch 1 and 2

Inspection Conducted: November 15-21, 1986

Inspector: N.[ hb

/ - dB - 8 7

H.~ L. Whitener

Date Signed

Approved by:

A

%

Ab/ h

'

"

'

Date Signed

F.- Jape, Section ~ Chief .

Engineering Branch-

-

" Division of Reactor Safety'~

SUMMARY

.

p,

'

~

Scope: -This routine, announced inspection was in the area of containment leak

"

rate testing.

Results: . One violation was identified - The overall integrated leakage rate for

the "as is", (also called "as found") containment condition could not be deter-

mined due .to ,the failure to measure <the change in leakage rate which resulted

from ' repairs and adjustments made to' the containment boundary prior to the

integrated (Type A) leak rate test'.

%2]%3kb

p

G

'

I

.

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • D. S. Read, Plant Support Manager
  • L. Sumner, Manager of Operations

T. Powers, Manager of Engineering

  • A. Fraser, Acting QA Site Manager
  • R. D. Baker, Nuclear Licensing Manager, Corporate

G. Goode, Superintendent of Plant Engineering and Services

  • A. Huber, Senior Plant Engineer

.1. C. McWhorter, Engineer, Southern Company

Other licensee employees contacted included leak rate test personnel.

Other Organizations

Bechtel - Leak Rate Consultants

R. Blum

M. Burgess

H. Hill

B. Patel

A. Salley

Volumetrics, Inc.

l

D. Peyvan, Project Engineer

NRC Resident Inspector

  • G.

M. Nejfelt

  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on November 21, 1986,

with those persons indicated in paragraph 1 above. The inspector described

the areas inspected and discussed in detail the inspection findings.

No

dissenting comments were received from the licensee.

The following new

items were identified during this inspection.

Violation (50-366/86-39-01):

Failure to measure the change in leakage

rate due to repairs or adjustments to the containment boundary prior to

the Type A test makes the calculation of the "as found" containment

,

l

integrated leak rate indeterminable (paragraph 5.e).

l

,

<

.

2

Inspector Followup Item (50-366/86-39-02): Review the licensee's action to

identify and test the pressure restraining seals in the containment boundary

,

(paragraph 5.d).

The licensee did not identify as proprietary any of the materials provided

to or reviewed by the inspector during this inspection.

3.

Licensee Action on Previous Enforcement Matters

This subject was not addressed in the inspection.

4.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Containment Integrated Leak Rate Test - Unit 2 (70313, 70307, 70323)

The inspector reviewed and witnessed test activities to determine that the

primary containment integrated leak rate test (CILRT) was performed in

accordance with the requirements of Appendix J to 10 CFR 50, ANSI-N45.4,

test procedure 42SP-TET-003-2S " Prima ry Reactor Containment Integrated

Leakage Rate Test" and the criteria of BN-TOP-1, Revision 1 for a short

duration test.

Selected sampling of the licensee's activities which were inspected included:

(1) review of the test procedures to verify that the procedures were properly

approved and conformed with the regulatory requirements; (2) observation of

test performance to determine that test prerequisites were completed, special

equipment was installed, instrumentation was calibrated and appropriate data

were recorded; and (3) preliminary evaluation of leakage rate test results

to verify that leak rate limits were met.

Pertinent aspects are discussed in the following paragraphs.

!

a.

General Observations

The inspector witnessed and reviewed portions of the test preparation,

temperature stabilization and data processing during the period of

November 15-21, 1986.

(1) The test was conducted in accordance with an approved procedure.

Procedure changes and test discrepancies were properly documented

in the procedure.

(2) Test prerequisites selected for review were found to be completed.

(3) Selected plant systems required to maintain test control were

found to be operational.

(4) Special test instrumentation was reviewed and found to be installed

and calibrated.

,

_

.__

_ _ _ .

_ _ _ .

._

-

.

. _ _

- . . -

.

3

(5) Controls for preventing pressurized air sources inside containment

or externally pressurized penetrations were established in the

test procedure.

(6)

Instructions and documentation for venting, draining and isolation

of systems were established in the test procedure.

(7) Problems encountered during the test were described in the test

~

event log.

(8) A containment temperature survey was performed for the no forced

flow test conditions.

(9) Temperature, pressure, humidity, and flow data were recorded at

15-minute intervals.

Data were assembled and retained for final

evaluation and analysis by the licensee. A final leak rate test

report will be submitted to the Office of Nuclear Reactor Regula-

tion pursuant to Paragraph V of Appendix J to 10 CFR 50.

b.

Test Performance - Unit 2 (70313)

(1) Method

The Bechtel computer program used for data analysis has the

capability for Total Time analysis in accordance with the

requirements of BN-TOP-1, Revision 1, for a short duration test

and Mass Point-Linear Regression analysis in accordance with the

recommendations of ANSI /ANS 56.8-1981 for a 24-hour test.

The

Appendix J acceptance limit of 0.75 La was met for the 95% Upper

Confidence Limit (UCL) for both the Total Time and Mass Point

analysis techniques.

A supplemental test was performed in

accordance with the specifications of Appendix C to ANSI N45.4 -

1972Property "ANSI code" (as page type) with input value "ANSI N45.4 -</br></br>1972" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. and BN-TOP-1, Revision 1 - 1972.

(2) Test Description

The absolute method as defined in ANSI N45.4-1972 was used in

determining the containment leakage rate.

Values bounding the

test conditions were as follows:

Containment Volume

257566 cubic feet

Accident Pressure (Pa)

57.5 Psig

Maximum Allowable Leakage (La)

1.2 wt.% per Day

System conditions for performance of the integrated leak rate test

were as follows:

(a) Reactor Vessel

Water level was between 53 and 60 inches,

and vented to the containment

'ww

-

P'

a

e

- - ' ' ' '

+ ' - -

t

'

.

4

(b) RHR System

One loop was operating in shutdown

cooling mode

(c) Containment Fans

Secured

Containment pressurization was initiated at 9:10 p.m.,

on

November 18, 1986. At 3:00 a.m.,

on November 19; pressurization

was secured; test pressure of Pa was verified; and, the stabiliza-

tion period was started. Temperature stabilization criteria were

met at 7:00 a.m., but the start of the Type A leak rate measurement

was deferred due to excessive containment leakage. The leakage

path was identified as a packing leak on valve No. 2T49-F001A and

was corrected to an acceptable Type A test limit. The Type A leak

rate measurement start time was established at 11:30 p.m.,

November 19, 1986. A twelve hour short duration test in accordance

with the criteria of BN-TOP-1, Revision 1 and Appendix J to 10 CFR 50 was performed followed by a six hour supplemental (verification)

test which was successfully completed at 6:45 p.m., on November 20,

1986.

c.

Test Results - Unit 2

(1) Type A Test

The Technical Specification allowable leakage (La) for Hatch 2 is

1.2 wt.% of the containment mass at accident pressure (Pa) per

day. The acceptable test leak rate limit of 0.75 La is therefore

0.9 wt.% per day. The calculated leakage rate and 95% UCL for the

Total Time and Mass Point Analyses are shown below for three

analyses performed on test data taken at 15 minute intervals

in the period 11:30 p.m. , November 19 to 11:30 a.m. , November 20,

1986. These are:

All data included in the analysis (49 data

Case I

-

sets analyzed in period 11:30 p.m., on 11/19

to 11:30 a.m., on 11/20).

Case II

-

Three data sets (Nos.

3, 6 and 7) deleted

frein the analysis (46 data sets analyzed in

period 11:30 p.m. on 11/19 to 11:30 a.m. , on

11/20).

Case III -

Test start time advanced to 1:15 a.m.,

on

11/20 which deletes the first seven data sets

'

(42 data sets analyzed in period 1:15 a.m. ,

to 11:30 a.m., on 11/20).

l

I

.

5

Mass-Point

Total Time

(wt. %/ day)

(wt.%/ day)

LSQF

UCL

LSQF

UCL

Case I

0.498

0.527

0.644

1.64

Case II

0.46

0.475

0.481

0.589

Case III

0.437

0.453

0.419

0.614

"LSQF" is the least square fit to the data and "UCL" is the

calculated 95% upper confidence limit for the respective

analysis method and case.

Review of test conditions indicated that Case II was the most

representative leak rate.

Case I contained three data sets

(Nos. 3, 6, and 7) which appeared to be affected by external noise

rather than actual changes in the containment atmospheric conditions.

Case III represents deletion of four data sets which appear to be

valid in addition to data sets 3, 6, and 7 due to advancing the

test start time from 11:30 p.m. on November 19 to the first data

set after the noise affected data which was 1:15 a.m.,

on

November 20.

Case III is included here principally to show

the consistency of the leak rate trend with respect to time.

Exclusion of data sets 3, 6, and 7 from the leak rate analysis was

based on the following information:

(a) The character of the perturbations, affecting principally the

RTD measurements and to a lesser extent the dew cells for

data points 3, 6 and 7, gave the appearance of external noise

,

in that there was a sudden departure from and return to a

-

.

stabl a trend; the deflections occurred at the same time and

in the same direction on all RTDs; and, the deflections were

I

about five times larger than the typical random noise.

$

(b) No c,orresponding change in total containment pressure

occurred.

Pressure instrumentation has no RTDs associated

'

with the circuitry. The containment pressure showed a stable

l

decreasing trend of 0.002 psi per data set.

An actual

.

'

I

decrease in temperature of 0.3 F would have resulted in a

I

pressure decrease of 0.04 psi; an order of magnitude larger

f

,

t

than that observed.

'

,

(c) The probable noise source was traced to the use of radio

communicators near the containment and instrument room.

A

'

g

review of the security log showed that radios had been used

I

in the vicinity of the instrumentation at the time the

perturbations of the RTD signals occurred.

Subsequent to

7

the test, the licensee verified that keying a radio in the

r

-

t

vicinity of the RTD instrumentation does induce noise in the

[

data similar to that observed early in the test.

l

l

. _-

...

-

_

-

.

6

The inspector concluded that the licensee had a reasonable basis

for . deletion of data points 3, 6, and 7 from the total time

analysis. The resulting total time 95% UCL in accordance with

BN-TOP-1, Revision 1, of 0.59 wt.%/ day is well below the acceptable

limit of 0.9 wt.%/ day.

(2) Supplemental Test

Appendix J requires that a supplemental test be performed to

verify the accuracy of the Type A test and the ability of the

CILRT instrumentation to measure a change in leak rate.

An

acceptable supplemental test method is described in Appendix C

of ANSI-N45.4 - 1972, as follows:

A known leak rate (Lo) is imposed on the containment and the

measured composite leak rate (Lc) must equal, within 10.25 La,

the sum of the measured Type A leak rate (Lam) plus the known

leak rate (Lo).

The acceptance criteria is expressed as:

Lo + Lam - 0.25 La < Lc < Lo + Lam + 0.25 La

A six hour supplemental test was performed by the imposed leak

rate method described in Appendix C to ANSI-N45.4-1972 and in

accordance with the requirements of BN-TOP-1, Rev. 1.

The

following values in units of wt. %/ day were obtained using both

mass point and total time analyses.

Mass Point

Total Time

Lam

0.479

0.460

Lc

1.623

1.643

Lo

1.153

1.153

0.25 La

0.3

0.3

Using the above values, Lc must fall within the limits in wt.%/ day

as follows:

,

1

Mass Point

Total Time

!

Upper Limit

1.913

1.932

Lc

1.623

1.643

Lower Limit

1.313

1.332

i

As indicated, Lc is within the specified limits for both analysis

techniques.

!

l

l

,

l

.

7

-d.

Containment Integrated Leak Rate Test - Status

At 7:00 a.m., on November 19, 1986, the four hour temperature stabili-

zation criteria were met. At this time the containment was leaking in

excess of the allowable 0.75 La (0.9 wt.%/ day) limit. The start of the

Type A test was delayed and a search for the leakage path was initiated.

In the period 7:00 a.m.,

to 2:00 p.m., on November 19, the containment

leak rate tended to stabilize at 1.1 wt.%/ day with a UCL of 1.7 wt.%/ day

by total time calculations. The major source of leakage was identified

as a packing leak on valve No. 2T49-F001A. This valve is outside of

the containment and inboard from the isolation valve of the hydrogen

recombiner system.

The measured UCL of 1.7 wt.%/ day and leak rate of 1.1 wt.%/ day both

exceed the Appendix J acceptance limit of 0.9 wt.%/ day. Consequently,

the CILRT was classified as a failed Type A test in accordance with

Paragraph III.A.1.(a) of Appendix J to 10 CFR 50. This is considered

the first failed Type A test on Unit 2.

Pursuant to the requirements

of Paragraph III. A.6.

of Appendix J to 10 CFR 50, the licensee will

submit the test schedule applicable to subsequent Type A tests for NRC

review and approval. Based on an integrated leak rate established over

a period of about seven hours before repair of valve 2T49-F001A packing

leakage and the integrated leak rate over a period of about 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

after the repair, the corrected leakage was 0.62 wt.%/ day from the

least square fit data and 1.1 wt.%/ day from the UCL data using the

total time analysis method.

Excessive leakage through the containment boundary raises a question

regarding the adequacy of the local leak rate testing program.

For

the hydrogen recombiner system, pressure for the Type C test is applied

between 2T49-F001A and the isolation valve in order to test the isola-

tion valve in the correct direction.

In this test configuration the

valve packing on 2T49-F001A is not exposed to local test pressure. The

rroblem was identified and corrected as a result of the Type A test;

therefore, the hydrogen recombiner system leakage is considered accept-

able for the current operating cycle for Unit 2.

The licensee will look at this problem in an ongoing leak rate test

evaluation program. This matter is identified for followup inspection

as follows:

IFI (50-366/86-39-02):

Review the licensee's action to identify

and test all pressure restraining seals in the containment pressure

boundary,

e.

Review Of the "As Found" Containment Leak Rate

The inspector reviewed the controls established by the licensee to

ensure that where repairs or adjustments were made to the containment

boundary prior to the Type A test, the change in leak rate due to these

repairs or adjustments was quantified in order to determine the "as

found" containment integrated leak rate.

__

_.

.

8

The inspection findings in this area are discussed below:

Unit 2

From discussions with management and personnel involved with the local

leak rate test program, the inspector determined that the licensee had

implemented controls to obtain local leakage rate measurements before

any repairs or adjustments to the containment boundary.

The outage

Work Planning Group coordinated the control through the maintenance

work order (MWO) system.

For those MW0s which affected containment

leakage barriers an instruction sheet was inserted into the work

package which required verification that a local leak rate was

performed prior to making repairs or adjustments. There were three

instances where a breakdown in implementation of the controls occurred.

As a result, repairs or adjustments were made to the containment

boundary prior to the Type A test without determining the change in

leak rate due to these repairs or adjustments. The conditions were as

follows:

(1) Two equipment hatches, penetrations IA and 18, were removed

without first obtaining the as found local leak rate for the

seals. On reinstallation of these hatches to perform the Type A

test, new seals were installed. Consequently, the change in leak

rate due to this repair could not be determined.

(2) A limitorque valve actuator on valve 2P42-F052 was reworked and

the seating torque values reset without first obtaining the local

leak rate.

Consequently, the change in leak rate due to this

repair and adjustment could not be determined.

The regulations regarding determination of the "as is" (also called "as

found") containment integrated leak rate are:

Paragraph III. A.1(a) of Appendix J to 10 CFR 50 and Paragraph 4.2 of

ANSI-N45.4 require, in part, that no repairs or adjustments shall be

made to the containment boundary prior to the Type A test in order to

determine the "as found" leakage condition of the containment.

Paragraph III.A.1(a)

in conjunction with Paragraph III.a.1(b) of

Appendix J to 10 CFR 50, permit repairs and adjustments to the

containment boundary prior to the Type A test, as necessary, provided:

(1) the change in leak rate resulting from any repairs or adjustments

is determined using local leakage testing methods; and (2) the

corrective action taken, the change in leak rate determined by local

tests, and the "as found" containment integrated leak rate determined

from the local tests and Type A test results are obtained and are

included in the report to the Commission.

Failure to determine the change in leak rate resulting from repairs or

adjustments to the above containment boundary components was identified

as a violation as follows:

m

._

~

,...

9

Vio1'ation (50-366/86-39-01): Contrary to the above' regulations, during

the 1986 Unit 2 refueling outage, repairs or adjustments were made to-

equipment hatches IA and 18 and to valve 2P42-F052' prior to the Type A

te st .' The- change in leakage rate as a result of .these repairs or

adjustments was not determined using local leakage test methods.

Failure to determine the change in leakage rate resulting from these

repairs or adjustments to the containment boundary renders 'the cal-

culation of the "as found" containment integrated-leak rate indeter-

minable.

While failure to determine the "as found" containment leak rate with

the plant in a shutdown condition is not an immediate safety problem,

the "as found" leak rate information is necessary to permit.the licen-

see to periodically assess the ability of the containment isolation

system to perform its safety function over a surveillance cycle.

Unit 1

The inspector reviewed the final calculation of the "as found" contain-

ment integrated leak rate for the Unit 1 Type A test performed

April 18-19, 1986.

The licensee's analysis shows . an "as found"

containment integrated leak rate of 1.538 wt.%/ day. This value exceeds

the . Appendix J to 10 CFR 50 limit of 0.75 La which is 0.9 wt.%/ day.

The inspector concluded that the April 1986 Unit 1 "as found" contain-

ment integrated leak rate test is a " failed" test. This is the first

failed test on Unit 1.

Pursuant to Paragraph III.A.6(a) of Appendix J

to 10 CFR 50, the licensee's proposed Type A test schedule and correc-

tive actions will be reviewed during review of the . leak rate test

report in the Region Office.

!

L

!