Forwards Insp Repts 50-348/86-28 & 50-364/86-28 on 861202- 04.No Violations or Deviations Noted.Estimated Date of Completion of Actions Licensee Plans to Take Re Identified Exercise Weaknesses Requested within 30 Days of Ltr Receipt
ML20210U159
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 12/30/1986
From: Verrelli D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Mcdonald R
ALABAMA POWER CO.
Shared Package
ML20210U162 List:
References
NUDOCS 8702180403
Download: ML20210U159 (2)


See also: IR 05000348/1986028

Text

. _

,_ ._ .. . . . .

'

.-

Docket Nos.. 50-348, 50-364

License Nos. NPF-2 and NPF-8

AlabamajPower Company

ATTN:vMr. R. P. Mcdonald

Senior Vice President

P. O. Box 2641.

Birmingham, AL 35291'

Gentlemen:

SUBJECT: NRC INSPECTION REPORT NOS. 50-348/86-28 AND 50-364/86-28

This refers to the Nuclear Regulatory Commission (NRC) inspection conducted by

A. L.- Cunningham on December 2-4, 1986. The inspection included a review of

activities authorized for your Farley facility. At the conclusion of the

inspection, the findings were discussed with those members of your staff

identified in the enclosed inspection report. .

Areas examined during the inspection are identified in the report. Within these

areas, the inspection consisted of selective examinations 'of procedures and

representative records, interviews with personnel, and observation of activities

in progress.

Within the scope of the inspection, no violations or deviations were identified.

Your attention is directed to the exercise weaknesses identified in the report

enclosed herein. Please advise us within 30 days of the date of this letter

actions you plan to take showing the estimated date of completion regarding the

subject findings.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, '

Title 10, Code of Federal Regulations, a copy of this letter and its enclosure

will be placed in the NRC Public Document Room.

Should you have any questions concerning this letter, please contact us.

N'

s Sincerely,

David M. Verre111, Chief

Reactor Projects Branch 2

Division of. Reactor Projects

Enclosure:

Inspection Report .

cc w/ enc 1: (Seepage 2)

' I

8702180403 861230

$" # 9'o$' TE0l

_ _ - _ _ _ - _ - .. ,

Alabama Power Company 2

c w/ enc 1:

p. O. Whitt, Executive Vice President

/J'. D. Woodard, General Manager - l

/ Nuclear Plant

/ . G. Hairston, III, General Manager -

Nuclear Support

J. W. McGowan, Manager-Safety Audit

/ and Engineering Review

JJ. K. Osterholtz, Supervisor-Safety

Audit and Engineering Review

bec w/ enc 1:

State of Alabama

, Document Control Desk

v yRC Resident Inspector

V . Reeves, Project Manager, NRR

. Rankin, DRSS

I

1

RII RII RII

g

h

ACunningham TDec er

RIJ

GW W

HDance

DCollins

12/// /86 12/tD/86 p12/ft/86 12/8)/86

7

)

L