ML20210J526
| ML20210J526 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 02/10/1986 |
| From: | Garde B GOVERNMENT ACCOUNTABILITY PROJECT |
| To: | NRC OFFICE OF ADMINISTRATION (ADM) |
| References | |
| FOIA-86-84 NUDOCS 8604030476 | |
| Download: ML20210J526 (2) | |
Text
1 i
o GOVERNMENT ACCOUNTABluTY PROJECT 1555 Connecticut Awnue, N.W., Suite 202 (202)2324550 Washington, D.C. 20036 February 10, 1986 FREEDOM OF INFORMATION ACT REQUEST p. rno.i OF INFORMAltON or gt !t3T o-FoIA %- F V Director Office of Administration g
E'/!"[h Nuclear Regulatory Commission Washington, D.C.
20555 To Whom It May Concern:
Pursuant to the Freedom of Information Act ("FOIA"), 5 U.S.C.
5552, the Government Accountability Project
(" GAP")
requests copies of any and all agency records and information, including but not limited to notes, letters, memoranda, drafts, minutes, diaries, logs, calendars, tapes, transcripts, summaries, interview reports, procedures, instructions, engineering analyses, drawings, files, graphs,-charts, maps, photographs, r
agreements, handwritten notes, studies, data sheets, notebooks, books, telephone messages, computations, voice recordings, computer runoffs, any other data compilations, interim and/or final reports, status reports, and any and all other records developed subsequent to the issuance of the August 30, 1985, OIA report about the T-shirt incident including but not limited to any memoranda, comments, etc., submitted to OIA from Region IV, EDO, NRR, ELD, or any other branch of the NRC.
This request includes all agency records as defined in 10 C.F.R.
$9.3a(b) and the NRC Manual, Appendix 0211, Parts 1.A.2 and A.3 (approved October 8, 1980) whether they currently exist in the NRC official, " working", investigative or other files, or at any other location, including private residences.
If any records as defined in 10 C.F.R. $9.3a(b) and the NRC Manual, supra, and covered by this request have been destroyed and/or removed after this request, please provide all surrounding records, including but not limited to a list of all records which have been or are destroyed and/or removed, a description of the action (s) taken relevant to, generated in connection with, and/or issued in order to implement the action (s).
B604030476 060210 PDR FOIA QARDE86-B4 PDR
. GAP requests that fees be waived, because " finding the information can be considered as primarily benefitting the general public," 5 U.S.C. }552(a)(4)(a).
GAP is a non-profit, non-partisan public interest organization concerned with honest and open government.
Through public outreach, the Project promotes whistleblowers as agents of government accountability.
Through its Citizens Clinic, GAP offers assistance to local public interest and. citizens groups seeking to ensure the health and safety of their communities.
The Citizens Clinic is currently assisting several citizens groups, local governments and intervenors in Texas concerning the constraction of the Comanche Peak nuclear power plant.
We are requesting the above information as part of an ongoing monitoring project on the adequacy of Region II and the NRC's efforts to protect public safety and health at nuclear power plants.
For any documents or portions that you deny due to a specific FOIA exemption, please provide an index itemizing and describing the documents or portions of documents withheld.
The index should provide a detailed justification of your grounds for claiming each exemption, explaining why each exemption is relevant to the document or portion of the document withhold.
This index is required under Vaughn v.
Rosen (I), 484 F.2d 820 (D.C. Cir. 1973), cert. denied, 415 U.S. 977 (1974).
We look forward to your response to this request within ten days.
Sincerely, D
$b w
Billie Pirner Garde Director Environmental Whistleblower Clinic