ML20210E255
| ML20210E255 | |
| Person / Time | |
|---|---|
| Site: | Braidwood |
| Issue date: | 09/10/1986 |
| From: | Miosi A COMMONWEALTH EDISON CO. |
| To: | Harold Denton Office of Nuclear Reactor Regulation |
| References | |
| 2085K, NUDOCS 8609220184 | |
| Download: ML20210E255 (85) | |
Text
)._
m
\\
ESSOR
} One Fwst Nemonal Plaza, CNoeDo, IEnois m
Address Reply to: Post Omco Box 767 Chce00.15nois 80000 - 0767 September 10, 1986 Mr. Harold R. Denton U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulatory Washington, DC. 20555
Subject:
Braidwood Station Unit 1 Responses to NRC Open Items from l
the Braidwood Fire Protection Inspection in August 1986 NRC Docket 50-456
Dear Mr. Denton:
Attached are Commonwealth Edison (CECO) responses to the various open items brought up by the NRC.during their fire protection audit'at Braidwood during the week of August 18 through August 22, 1986.
Responses to all open items are not included with this letter.
These responses commit CECO to perform certain actions.
to address the NRC concerns raised during the audit.
We have also included a short note addressing those items in which resolution has been reached with members of your staff.
Each of these responses was discussed with the members of your staff in a' telephone conference call on August 28, 1986.
This letter provides written confirmation of our commitments.
Should you have questions concerning this matter please contact this office.
One signed original and fifteen copies of this letter and enclosure are provided for your review.
Very truly yours, h
A.
D.
iosi Nuclear Licensing Administrator
/klj cc:
J. Stevens 2085K 8609220184 860910 h
PDR ADOCK 0500 6
g\\
G
NRC Open Items from Braidwood Fire Protection
-Inspection in August 1986 4
and CECO Responses
'K-3 Sprinkler system around the hatchway at' elevation 426' in the Auxiliary Building'outside the Laundry room was not considered adequate.
Also hatchway does not have a draft curtain.
4 CECO Response - New sprinklers will'be added at the hatchway opening prior to exceeding 5% power.
Existing sprinklers _that are. approx. 10 feet above the hatchway ~will remain in place.
By telecon on 8-28-86-the NRC has agreed to furnish CECO with the appropriate NFPA' reference to use for the design.of draft curtains if needed.
K-7 Steel plates over equipment hatches in,the curved wall area of the Auxiliary Building at elev. 426' -are not sealed to prevent the. passage of hot gasses.
CECO Response'- Gaps or openings in the existing steel plates 1~
will be sealed prior to exceeding 5% power.
Plates will be caulked into place with a fire resistant type of caulk.
4
(-
K-9 Need proofoof structural steel fireproofing adequacy.
UL listing and test data.
2 i
-CECO Response - Data on our design using Pyrocrete 102 given--to I
-the NRC for.their evaluation.
The NRC by telecon on 8-28-86 3
. informed CECO that they have closed this item.
K-11 Spare conduit seals are not adequate.
The NRC needs test data' l
to substantiate our design for sealing spare conduits.
l CECO Response - Test data will be submitted to'the NRC which' will show that conduits that are capped on both ends and sealed with fire resistant material will be an acceptable 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> t
barrier.
CECO will use that. configuration in the sealing of space conduits'.
That test data will be submitted to the NRC by-i Fuel Load.
K-12 NRC questioned the adequacy of the seals in the floor of the Upper Cable Spreading Room.
CECO Response - Data _was given to the NRC concerning these seals at the time of the audit.
The NRC by telecon on 8-28-86 informed CECO that they have closed this item.
4
{
l 1
4 K-18 The NRC considered the sprinkler installation around the stairwell and hatchway in the Auxiliary building at elev. 364' inadequate.
CECO Response - We will add sprinklers around this stairwell and hatchway prior to exceeding 5% power.
By telecon on 8-28-86 the NRC has agreed to furnish CECO with the appropriate NFPA reference to use for the design of draft curtains if needed.
K-19.
The NRC did not consider our justification for the separation of redundant RHR pumps and coolers adequate.
The NRC feels that our repair procedures are not an adequate compensatory measure for the separation afforded the RHR pumps.
This has been identified as Appendix R deviation A.8.
CECO Response - CECO will' upgrade one of the walls between the redundant RHR pumps to a barrier of substantial fire resistant quality.
The upgrade of the wall will be complete prior to exceeding 5% power unless material procurement difficulties preclude meeting that date.
Should difficulties like that.
arise the NRC will be notified and CECO will implement compensatory measures (such as roving fire watches) to provide protection.
K-21 The NRC questioned the fire protection measures to be used for-the propane gas line used to provide gas for burners in the rad-chem labs in the Aux. Bldg.
Ceco Response - CECO will abandon this gas line and system in place by Fuel Load.
K-22 The NRC questioned the adequacy of our sprinkler systems in various areas of the Aux. and Turbine Buildings due to physical obstructions.
CECO Response - The sprinkler systems at Braidwood have been reviewed by several consultants and have been found to be acceptable.
The consultants review letters are attached.
l l
-- K-24 The NRC questioned.the adequacy of fire protection measures for the Chemical Storage rooms adjacent to the Aux. Boiler Room.
CECO Response - M&M has reviewed this chemical storage area and has concluded that due to the substantial' fire resistant construction that conforms with-NFPA 30 no further fire protection features will need to be installed above the current design.
A fire hazards analysis for the storage area is attached for your review.
1 K-25 There are no hose stations in the valve rooms in the Main Steam tunnels.
The NRC considers detectors and hand extinguishers inadequate protection.
CECO Response - CECO will provide additional hose at a hose-station which can be used for one of the valve rooms prior to
~
exceeding 5% power.
S&L has verified that adequate pressures and flow will be available for the hose station (with the added hose) to fight a fire in the valve room.
The other valve room i
can be served by a hose from an outside hose house.
Operating will revise their pre-fire plans to account for the use of the 1
i hose stations prior to exceeding 5% power.
'here are several instances throughout the plant where hose A-11 T
stations and sprinklers protecting an area are fed from a common fire main header.
This is a violation of BTP requirements.
i' CECO Response - M&M has reviewed all instances of this
-arrangement in the plant.
Compensatory measures which include j
the use of adjacent hose stations outside of the area under consideration will have to be implemented.
Some additional hose from the portable fire brigade hose cart may have to be added to hose stations used as a compensatory measure.
Pre-fire plans will be changed as necessary to account for these cases prior to exceeding 5% power.
The only exception to the above is the case in the Containment where the hose stations and the charcoal filter deluge is on the same header.
l By agreement during the telecon on 8-28-86 the NRC considers the situation in the Containment to be acceptable as is.
i l
MEL/sm/8378b*
~~..
B/B AMENDMENT 9 are provided in this zone for access to other floor levels.
An elevator is also provided in this zone, and is enclosed by 12-inch thick hollow concrete masonry units walls which carry a 2-hour fire ratina.
Located within this zone between column-rows 12-16 and F-G is the 15,000 gallon turbine oil storage tank.
The floor slab in this area is a 9-inch clear cover of structural decking formwork which is supported by unprotected structural steel beams and columns.
This slab provides a resistance of 3-hours to the spread of fire to the Turbine Building floor level below.
Two 4-inch diameter floor drains (90 gpm capacity each) are provided to remove oil and fire protection water.
A 3-fcot high curb is provided around this area to contain an oil spill.
The ceiling slab at elevation 426 feet 0 inch is a 4-inch clear cover of structural reinforced concrete over 2-inch fluted steel decking formwork supported by unprotected struc-tural steel beams.
A chemical storage area is located against the wall of the heating steam boiler room near column row 6 between column rows C and E.
The chemical storage area consists of five separate rooms.
Each room has 3-hour rated fire walls, label A fire doors and 3-hour rated fire dampers in the ceiling and walls.
Each room has a 6-inch curb and ramp to contain spills.
Safetv-Related Reactor Shutdown and Cooling Ecuipment No safetv-related equipment is located in this zone.
Protection Criteria and Measures All walls are 3-hour rated except as discussed previously in Subsec tion 2.3.8.
A curb is provided around the turbine oil storage tank to contain a spill.
The chemical storage area rooms have 3-hour rated enclosures.
Each room has a separate ventilation system exhausting to the atmosphere.
The exhaust fans are Class I Division 2.
Fan running and differential pressure alarms are provided on a local panel with a common " trouble" alarm in the control room.
Lighting inside the rooms is-explosion proof. -Sprinkler protec-tion is not provided nor is it required by NFPA 30.
2.3-74
e B/B AMENDMENT 9 Combustible Materials The two station air compressors each contain approximately 56 gallons of lube oil.
The EHF reservoir contains 300 gallons of-phosphate ester (assumed equivalent.to lube oil in. heat content).
One gallon of oil is associated with_the remainder of the pumps.
The 15,000 gallon turbine oil storage tank is also present'in this zone, bringing the total to 15,413 gallons of lube oil present.- Also, there are 1110 gallons of lube oil conditioner in this zone.
There are 5,500 pounds of cable. insulation located in this zone.
The ductwork contains 137 pounds of casketing.
A transient loading equivalent to 550 gallons of lube oil is assumed.
None of the chemicals stored in the chemical storage area are classified as combustible or flammable liquids.
They are, there-fore, not included in the combustible material inventory.
Fire Loading 2
With a floor area of 40,602 ft the fire leading is 66,400 7
Btu /ft i
I l
l 2.3-74a
4
. A c _ >,,
M&M Protection Consultants A Resource of Marsh & McLennan April 10, 1986 Mr. D. Elias Project Engineer Commonwealth Edison Co.
P. O. Box 767 Chicago, IL 60690 RE:
BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE DETECTION SYSTEMS RESULTS OF THE MARCH 11, 1986 WALKDOWN
Dear Mr. Elias:
On March 11, 1986 a walkdown of the' fire protection systems for the Unit 1 and common areas of the Braidwood Nuclear Station was undertaken to resolve the possible deficiencies noted in the initial reviews of the systems.
Those present for this walkdown were:
Mr. J. Biggins M&M Protection Consultants Mr. J. Bruciak Commonwealth Edison Company Mr. L. Edwards Viking Fire Protection Co.
Attached is a summary of the items which were resolved and closed by the decision of those present.
Each item reviewed will be answered in greater detail at a later date when M&MPC will generate a letter for each system reviewed in order to close all open items from the reviews.
Sincerely, James B. Biggins Fire Protection Associate JBB/lw cc:
J. Deress J. Bruciak G. Jones M. Pietraszewski C. Tomashek B. Treece G. Kirchner R. Salsbury E. Fitzpatrick S. Chingo R. Rakowski T. Meyer D. Shamblin M. Balster M. Smith R. Rybak R. Kyrouac N. Kaushal 222 south Riverside Plaza + ChicTgp,1)hys@Wiear312-6484000 E. O' Donne 11 (JB5/2)
7-m M&M Protection Consultants
SUMMARY
OF FIRE PROTECTION ITEMS TO BE CLOSED AS A RESULT OF THE 3/11/86 WALKDOWN OF BRAIDWOOD SPRINKLER SYSTEMS M&MPC Review Item Protection Area Letter Dated Number Decision Reached 1-Y 11-11-85 6, 7 & 8 No action required.
Discharge of surrounding sprinklers and protection provided by hose stations and portable fire extin-guishers are considered to provide adequate area protection.
1-GG 11-26-85 No action required as a result of this review.
1-K 11-27-85 11 & 12 No action required.
Adequate area protection is provided by hose stations and portable fire extinguishers.
13 No action required.
Discharge of surrounding sprinklers is considered to provide adequate pro-tection to the area.
2-CC 12-1-85 No action required as a result of this review.
1-KK1 12-31-85 5
Valve is to be repaired.
7 Electrical installation is to be completed.
1-KK3 12-31-85 6
Covering over sprinkler is to be removed.
7 Electrical installation is to be completed.
1-KK4 12-31-85 4
Electrical installation is to be completed.
1-KK5 12-31-85 4
Electrical installation is to be completed, a
j M&M Protection Consultants M&MPC Review Item Protection Area Letter Dated Number Decision Reached 1-JJ 12-31-85 6
Covering over~ sprinkler is to be removed.
1-X 1-3-86 3
. Electrical installation is to be completed.
6 Branch line is to be dropped below HVAC duct.
7 Pendent style sprinklers are to be installed.
1-LL 2-9-86 5
Remaining hanger assemblies are to be installed.
6 Covering over sprinkler is to be removed.
7 Waterflow indicating device is to be installed.
10 & 11 Piping will be realigned so'that the deflectors of the sprinklers will be parallel to the ceiling.
1-W 2-25-86 3
A fire hose connection is to be provided at the main drain of the system.
4 Station will leave pull station in present location and develop procedures to address its utilization.
O
r e,.-
,_._-w.-_
2,.
y, s.
M&M Protection Consultants A Resource of Marsh & McLennan November 27, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Cox 767 Chicago, IL 60690 RE: BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEM RESULTS OF OCTOBER 22, 1985 WALKDOWN
Dear Mr. Elias:
On October 22, 1985 a walkdown of the fire protection systems reviewed by M&M Protection Consultants was undertaken to resolve the possible deficiencies noted in the initial review of the systems.
Those present for this walkdown were:
Mr. J. Biggins M&M Protection Consultants Mr. M. Pietraszewski Commonwealth Edison Company Mr. T. Gray Commonwealth Edison Company Mr. J. Bruciak Commonwealth Edison Company Mr. R. Kelm Commonwealth Edison Company Mr. L. Edwards Viking Fire Protection Company Attached is a summary of the items which were resolved and closed by the decision of those present. Each item reviewed will be answered in greater detail at a later date when M&MPC will generate a letter for each system reviewed in order to close all open items from the reviews.
For those items requiring piping changes, etc., please see Viking's l
letter of November 1, 1985.
I 222 South Riverside Plaza
- Chicago, Illinois 60606
- 312-648-6000 l
I
I o.,
c M&M Protection Consultants Mr. D. Elias Novesber 27. 1985 Page 2 If you have any stuestie.us or comments on this information, please contact us.
Sincerely.
,$.$=__, =,, -
James b. Biggins Fire Protection A*sceinte JBB/1w Attachment cc:
J. Deress
- 7. Bruciah G. Jones M. Piett:aszewski C. Tomashek B. Treece T. Gray R. Salubury R. kakowski E. Fitzpatrick R. Williane E. Crass T. Meyer S. Chingo M. Smith D. Shenblin R_. Smith, Jr.
M. Rybak M. Belster (JBl/10)
I
2..
?.
M&M Protection Consultants SIM1ARY OF FIE PROIECIION ITEMS TO BE CICSID AS A RESUI.T OF TEE 10/22/85 WAIX1G H OF B"AIDWOOD SPRINKLER SYSTEMS AIL M6MPC Item Decision Ref. No Protection Area Letter Dated Number Reached 100.3 1-BB 6-18-85 5
Item previously corrected.
7 No action required. Sprin-klers adequately protect the narrow beam pocket.
100.6 10 Ne action required. Dis-charge of surrounding sprinklers is considered to provide adequate pro-tection to the area.
1-J 6-24-85 No action required as a re-sult of this review.
1-F 7-19-85 No action required as a re-sult of this review.
104.6 1-H 8-2-85 9
No action required. Wall of restroom does not extend to ceiling as shown on design drawing. Station is to in-plement administrative pro-cedures to control combus-tibles in this area and sur-rounding protection pro-vided by sprinklers, hose stations and portable fire extinguishers is considered adequate.
104.10 20 No action required. Dis-charge of surrounding sprinklers is considered to provide adequate protection to the area.
104.11 21 No action required. Sprin-klers adequately protect the narrow beam pocket and coverage is satisfactory.
104.12 24 No action required. Further investigation showed sprin-kler to be above obstruction.
Page 1 of 3
l
't.
T.
i
. M&M Protection Consultants i
AIL M6hlPC Item Cecision Ref. No Protection Area letter Dated Nuisber Reached 104.17 1-H (cont'd) 8-2-85 35 No actica required. Statien is to implement administrative procedures to control toebuc=
tibles in this ares and sur-rounding prctection provided by,
sprinklers, hose stations and portable fire extinguishers le considered adequate.
104.20 38 No action required, Adequhte area protection is provided by hose stations and portable fire extinguishers.
104.22 40 No action required. It was felt that the type of fire postulated for this area w:uld be sufficient to actuate. sprin-klers as presently installed.
105.2 1-D 8-2-85 5
With both mariual pull stations located along the same eccess path, the area fira plans vill be updated to address fire fightics tactics.
1-J 8-16-85 No action required na a renuit of this review.
No action required as a result f
1-D 8-28-85 of this review.
2-HH 8-29-85 No action required as a result of this review, 112.20 &
1-M 9-13-55 10&11 No action required. Discharge 112.21 of surrounding sprinklers is considered to provide adequate protection to the area, i
Page 2 of 3
-w
/,;. ~
M&M Protection Consultants AIL EMPC Itse Decision
%g Protection Area letter Dated Number Reached
~11h 23 FM(coot'd) 9-13-85 15, 19 No action required.
U2.25 22 & 23 Surroanding protection 112.26 &
provided by sprink?.ers, 11L27 bose etstions and por-table fire extinguishers is considered adequate.
Not shcwn 18 At the discretion of the Ceco on AIL fire protection engineers spria-klar obstruction is cinteal and can te lef t as is, U2.10 1-L 9-13-85 6, 8
.No action required. Dischstge 112.11 9 & 11 of surrounding sprinklers is 112.12 &
considered to pfovide adeqvste 112.13 protectiop to the area.
117.6 &
1-G 9-13-85 9 & 13 No artice required, pischerse 132.7 of surro9nding sprinklers is concidered to provide adequate protection to the arsa.
114.$
1-E 9-25-25 4
Completed.
114.5 13 No action required. Station 2a to implea nt accinistrative srecedures to control combus-tibles in this area and sur-surrcunding protection prov11ed by hose stations and periable fire extinguisherr.
U/.10 &
15&l6 At tht ciserstion of the CECO 114.11 fire protection engineer, sprinkler obstmerion is sin-izal and can be left as is, u4.12 19 No action required. Oischarge of surrounding sprinklers is considered to provide adequate protection to the ares.
u4.14 27 Co pleted.,
129.3 1-P 9-30-85 3
Na action required. 7alve is to be utilized as an auxiliary drain.
(JF,1/10)
Page 5 of 1
s
.,e 6;
I November 1, 1985 V!t'ING FIPE PRCT!CT;0N COM5t NY f,PECfAt HAIARDS OtVtSICN 491 NO9TH7A7E PASiKWAY WHELLt*40 atttNOIS 60090 (3* 2l 453-ti990 Cocoonwealth Edison Cc:cpany R. R. 1 Bcx.61 Braceville, Illinois 60407 Attention:
Mr. Dan Sharablin Re: M&M Reccm endations and October.22, 1985 Walkdown Gent 3emen:
On October 22, 1985 ve attended a walkdown of certain fire protection systeas and reviewed the M&M cmaents. The following is the course of action decided by those present at the walkdown. Attendees were J.
Biggins (M&M Protection Consultants), T. Gray (CECO), Larry Edwards (Viking), M. Pietrazewski (CECO), Eob Kels (CECO) and J. Bructak (CECO).
We will list the M&M letter, iten number, and course of
- action, Copies of letters are attached.
EM letter, dated June 2&,1985. Protection Area 1-J:
5 & 7 - Jim Biggins will advise if flushing connections and test gauges are required by operations for normal maintenance.
No action by Viking at t.his time.
Aueust 16. 1985 letter. Protection Area 1-J Aucust 79, 1965 2etter. Protection Area 2HH Aucust 2,1985 letter. Protection Are.a 3D August 28, 1985 letter. Protection Area ID No action required by ' liking as a result of these letters.
October 11, 1985 letter, Protection Area Outdoor s
July 19, 1935 letter, Protection Area 1-F No action required by Viking as a result of these letters.
June 18 1985 letter, Protection Area 1-BB 2
5 - has been corrected. Pendent Sprinkler is installed.
7 -
No action necessery.
8 The outlet of the f f tting will be turned down ar.d a pendent sprinkler installed.
9 Same action as 8 10 - Same actica as 8 11 - No action necessary.
12 - Same action as 8
s y-VIKING FIRE PROTECTION COMPANY i
Mr. Dan Shamblin November 1,1985 Page 2 l
September 30, 1985 letter, Protection Area 1-P I
i 3-No action at this time.
If valve requires periodic inspections, l
Tom Gray will advise and Viking will remove.
4-Viking will install head guard.
1 September 13, 1985 letter, Protection Areas 1-M, 1-L and 1-6 Protection Area 1-M 7 - Station construction will advise if tamper switch is required.
8 - Viking to install waterflow switch.
10
. No action required by Viking.
11 - No action required by Viking.
13 - Turn outlet of fitting down and install pendent sprinkler.
15 - No action required by Viking.
16 - Turn outlet of fitting down and install pendent sprinkler.
19 - No action required by Viking.
22 - No action required by Viking.
23 - No action required by Viking.
Protection Area 1-L No action required by Viking.
6 No action required by Viking.
7 8 - No action required by Viking.
No action required by Viking.
9 11 - No action required by Viking.
Protection Area 1-6 9 - No action required by Viking.
13 - No action required by Viking.
August 2, 1985 letter, Protection Area 1-H 2 - Reinstall this line with three sidewall sprinklers.
7 - Remove sprinklers and install Firematic sprinklers with baffles.
9 - Walls above restroom are not extended to deck as shown on drawing. Discussion as if storage would occur on the deck or not.
CECO and M&M to investigate and advise if sprinklers are required.
12 - This comment is covered under the proposal for SLV-41.
~
, VIKING FIRE PROTECTIEN COMPANY Mr. Dan Shamblin November 1, 1985
~
Page 3 August 2,1985 letter, Protection Area 1-H - continued 14 Turn outlet of the fitting down and install
, pendent sprinkler.
19 Shorten sprig so deflector -is below pipe.
20 - No action required by Viking.
21 No action required by Viking, ~
24 No action required by Viking.
26 Turn outlet of fitting down and install pendent sprinkler.
32 Shorten sprig so that deflector is 1" to 4" below bottom of beam.
33, 34 & 35 - Provide additional sprinklers under duct 15' on center.
Do this while work is being performed on SLV-41 to keep cost at a minimum.
36 & 37 - Are to be completed under proposal for SLV-41.
38 No action required by Viking.
Remove 1 X h reducing coupling, install 1 X reducing 39 90' and install vertical sidewall sprinkler in the pendent. position.
40 No action required by Viking.
September 25, 1985 letter, Protection Area 1-E 3 - Reinstall sprinkler and piping as shown on drawing.
8 - Covering has been removed.
10 - Add a branch line on the side of the hatchway with sidewall sprinkler and drop one head over the mister unit. See attached sketch SK-1.
11 & 12 - Are to be completed under proposals for SLV-41.
13 - No action required by Viking.
15 - No action required by Viking.
16 - No action required by Viking.
19 - No action required by Viking.
26 - Lcwer sprinkler so that deflector is 1" below obstruction.
27 - Completed.
29 - Remove offset at top of riser nipple.
30 - No action required by Viking.
32 - To be completed under proposal for SLV-41, 34 - Lower sprinkler so deflector is approximately 1" below obstruction.
36 - Same as 34 37 - Straighten sprig so that it is straight up.
1.
- q
~
~'
, VIKING FIRE PR$TECTION COMPANY Mr.-D. Shamblin November 1,1985 Page 4 Please note that the above work is to be accomplished under CCA-47 on a T&M basis. This will include the independent inspection of this work.
Upon receipt of CCA for the SLV-41 proposal, Viking will proceed with these modifications.-
All of the above modifications (including SLV-41) will be performed by Viking and then "As Built" drawings will be submitted upon com-pletion.
Should you have any questions, please contact the undersigned.
Very truly yours, VIKING FIRE PROTECTION COMPA!Tl Y
(
Larry 'J. Edwards Project Manager Special Hazards Division LJE/j g enclosures cc:
J. Biggins (CECO) l Tom Meyer (CECO)
Tom Gray (CECO)
J. Bruciak (CECO)
R. Haffner (Viking Fire Protection Company)
D. Durr (Viking Fire Protection Company)
L. Wilson (Viking Fire Protection Company P
k I
L
?.,
p
~
id.
~
5 wo 3
4"
=3 85 o uo es OL T?3
'2
- w<J
~*6 o
oc *J a-5;:n 7
)
.trov3 lW bo E */
4 yd:i 6-i
- p., w.,
b o s
.ft 7
[gg[
tn u _
o F i
,a
- C 0 X t 'e 0Em
\\\\s 3
o 1
JS Q
.s so PJ s-O of 7
} $
24W O
O Q
v0 ow>
w
~
4 h h s 2.0 u
u
~
,2 5 2M
-7
<19 O3W T
/
3%dn o
W
/
y4 E
b7
/
o a oo s
O
/.
F d4 g
/
Tico
{W J
s c"". D 0 -
/
s.,
FL al
\\
m
/
\\
\\
/
/
N i
L
.\\
\\
\\
s
\\
/
/
/
- em g
/
l
/
s
/
N,/
a A,
/
\\
N
/
I e
p h
\\
,dt.-
2
\\
u
\\
\\
\\
20J l
f3
[
uJ t
& C.
I f -.
T l
s>
, ~,,,,
L-i p-
- n. vw.m l
.e
. 4' M&M Protection Consultants 5
A Resource of Marsh & McLennan March 4, 1986 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 RE:
BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEMS GENERAL REQUIREMENTS FOR SPRINKLER SYSTEMS
Dear Mr. Elias:
We have completed our walkdowns and reviews for the auto-matic sprinkler systems installed on the Unit 1 and common areas of the Braidwood Nuclear Station.
Enclosed is our review of the general requirements for these sprinkler systems.
This review supersedes our preliminary review on this subject dated August 5,1985.
This review outlines deficiencies which are generic in nature to all the sprinkler systems installed at Braidwood Nuclear Station, and it was felt that it would be more reasonable to deal with these separately and that the one resultion would apply to all systems as opposed to listing each deficiency and each resolution separately for every sprinkler system installed at Braidwood.
This evaluation is based on NFPA 13-1985, " Standard for the Installation of Sprinkler Systems",
completed on-site walkdowns of the systems and Viking Fire Protection Company drawings.
If you have any questions or comments concerning this review, please contact me.
Sincerely, Sh
~
James B. Biggins Fire Protection Associate JBB/lw cc:
J. Deress J. Bruciak G. Jones M. Pietraszewski C. Tomashek B. Treece T. Gray G. Kirchner R. Salsbury E. Fitzpatrick S. Chingo R. Rakowski l
T. Meyer R. Smith, Jr.
E. Crass l
D. Shamblin M. Balster M. Smith R. Rybak R. Kyrouac N. Kaushal (JB3/ll) i
~
222 south Riversde Plaza
- Chicago,lihnois 60606
- 312-648-6000
f..l M&M Protection Consultants General Requirements for Automatic Sprinklet Systems NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Gauges on systes risers shall have Gauges will be para. 2-9.2.2 a maximum limit not less than twice periodically surveilled the normal working pressure at the for accuracy.
point where installed. Gauges are 300 psi.
2.
NFPA 13-1985 Fittings used in sprinkler systems Further investigation para. 3-13.1.3 shall be extra heavy pattern where showed that fittings pressures exceed 175 pai.
seet or exceed NFPA requirements.
3.
NFPA 13-1985 The components of hanger assemblies Acceptability of hanger para. 3-15.1.2 which directly attach to the pipe assemblies were verified or building structure shall be by Sargent 4 Lundy listed.
(10-30-85 letter) and Viking Fire Protection Company (10-16-85 letter).
4.
NFPA 13-1985 Sprinklers shall not be used for System working pressures para. 3-16.2.3 system working pressures in ex-are not expected to ex-cess of 175 psi.
coed 175 psi.
5.
NFPA 13-1985 These shall be maintained on the An adequate supply of pers..M6.7 promises. A supply of spare sprin-spare sprinklers for all klers so that sprinklers that have Unit 1 and comanon areas operated or been damaged in any way are stored along with may be replaced. A special sprin-sprinkler wrenches in kler wrench shall also be provided.
the storeroom.
2hese items shall be stored in a cabinet located where the temperature j
will not exceed 100*F.
l I
(
Page 1 of 2
~
+*
M&M Protection Consultants General Requirements for Autcusatic Sprinkler Systems NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 6.
NFPA 13-1985 Deflectors of sprinklers in bays formed The beams form panels which para. 4-3.4.1 by members, such as beams fotied into.
will trap sufficient heat girders, resulting in panels up to 300 so that sprinkler operations sq. ft. shall be located 1-inch to 18-will not be impaired L/ the inches below roof or floor decks. In increased spacing.
order to achieve the desired, unobstructured sprinkler discharge patterns, it was nec-essary to locate some sprinklers greater than 18-inches below the ceiling. Beans greater than 24-inches in depth are used in various locations within the station and would obstruct the sprickler discharge if sprinklers were located no more than 18-inches from the ceiling.
7.
NFPA 13-1985 1he installer shall properly identify a Signs are to be provided para. 7-1.2 hydraulically designed sprinkler system once as-built hydraulle by a permanently attached placard indica-information is available, ting the location, and the basis of de-sign. Such signs shall be placcd at the controlling alarm valve for the system.
(NFPA2/19) i l
Page 2 of 2
M&M Protection Consultants PC A Resource of Marsh & McLennan December 31, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P.O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Automatic Fire Protection System Protection Area 1-JJ
Dear Mr. Elias:
Enclosed is our review of the fire protection system installed over the component cooling pumps located on elevation 364'-0" of the Auxiliary Building, protection area 1-JJ.
This is an automatic wet pipe sprinkler system utilizing ordinary hazard pipe sizing and spacing.
A total of 40 Viking 212*F rated sprinklers are provided for protection of the component cooling pumps and sur-rounding floor area.
It should be noted that the station is in the process of installing water spray shields for the component cooling pump motors (Braidwood AIL
- 54) with no set completion date.
This review is based on NFPA 13 - Standard for the Installation of Sprinkler Systems, Viking Fire Protection Company drawings and an on-sits walkdown of the installed system performed on December 2, 1985.
An evaluation of the hydraulic performance of the system will be com-pleted when as-built drawings of the system become available.
If you have any questions or comments concerning our review, please contact me.
Sincerely, h h%
ames B. Biggins Fire Protection Associate JBB/che cc:
J. Deress J. Bruciak G. Jones M. Pietrazewski C. Tomashek B. Treece T. Gray B. Williams R. Salsbury E. Fitzpatrick S. Chingo R. Rakowski T. Meyer R. Smith, Jr. 9 E. Crass D. Shamblin M. Balster 1l M M. Smith JB3/1 222 Soc 1 Riverside Plaza
- Chicago, Illinois 60606
- 312-648-6000
- - ~.. - _.. ~. -
M&M Protection Consultants Fire Protection Area 1-JJ Component Cooling Pumps 1
NFPA 13 - 1985
~
Standard for the In'stallation of Sprinkler Systems Item Reference Deficiency Rasolution 1.
NFPA 13-1985 Working plans shall be submitted for approval Determine correct valve J
para. 1-9.1 before any equipment is installed or remodeled.
numbers.
Deviation from approved plans requires per-mission. The control valve is label 0FP633 on Viking design drawing S3, valve is field tagged
- OFP630, 2.
NFPA 13-1985 The piping configurations for the branch lines Corect Viking drawing 93 para 1-9.1 located approximately 5 feet south of Column 20 to reflect actual install-is different from that sfiown on Viking design ation.
drawing 93.
3.
NFPA 13-1985 Underground mains and lead-in connections to MbMPC has reviawed flushing para. 1-11.1.1 system risers shall be flushed before connc-procedure FP-21 and is a-tion to sprinkler piping.
waiting flushing to be completed.
4.
NFPA 13-1985 All new systems including yard piping shall be Verify that the required para. 1-11.2.1 hydrostatically tested at 50 psi in excess of hydrostatic testing has the maximum system pressure for two hours. The been performed.
test pressure shall tJ read from a gauge located at the low elevation point of the in-dividual system or protion of the system being d
tested.
5.
NFPA 13-1985 Each system shall be provided with a listed The Anchor-Darling gate para. 3-14.2.1 indicating valve. The Anchor-Darling gate valve valve is manufactured to ASME is not a listed valve.
SA-105 and A-216 stand-ards and is ANSI Class l
150. This is considered l
adequate for this in-i stallation.
6.
NFPA 13-1985 Bass or coverings placed over sprinklers to Remove covering so elas para. 3-16.9.1 protect them form painting or other processes, sprinkler may actuate should be removed once the painting has been without undue delay.
{
finished. Sprinkler 1 on"the branch line located at Column 21 is covered by what appears to be a paper cup.
7.
NFPA 13-1985 Waterflow detecting devices, including the Verify that the required para. 3-17.6.3.
associated alarm circuits, shall be tested testing has been performed by an actual waterflow through use of a test connection.
Page 1 of 3
s M&M Protection Consultants Item Re ference De ficiency Rasolution 8.
NFPA 13-1985 Sprinklers should be so located and spaced No action required. Inter-para. 4-2.3 so that any interference is held to a ference is minimal and minimum. Sprinkler 2 on,the branch line sprinkler discharge will
' located 3 feet south of Column 15 is be adequate to protect partially obstructed by a cable tray and a area.
hanger support element. (Approximate location L-15)
Sprinkler 1 on the branch line. located approximately 9 feet north of Column 17 is partially obstructed by a hanger sup-port element. (Approximate location N-16)
Sprinkler 2 on the branch line located approximately 9 feet north of Column 17 is partially obstructed by a hanger support element and electrical junction box. (Approximate location M-16)
Sprinkler 3 on the branch line located 9 feet north of Column 17 is partially obstrut?.ed by a hanger support element and piping. (Approximate location M-16)
Sprinkler 2 on the branch line located ik feet south of Column 17 is partially obstructed by a cable tray and a hanger support element. (Approximate location M-17)
Sprinkler 1 on the branch line located approximately 5 feet south of Column 18 is partially obstructed by a hanger support element. (Approximate location L-18)
- Sprinkler 3 on the branch line located 6k feet north of Column 20 is partially obstructed by a hanger support element.
(Approximate location M-20)
Sprinkler 2 on the branch line located approximately 6 feet north of Column 20 is partially obstructed by HVAC duct work, and a cable tray. (Approximate location N-20)
Page 2 of 3
M&M Protection Consultants
~
Item Re ference Deficiency Resolution Sprinkler 1 on the branch line located approximately 5 feet south of Column 20 is partially obstructed by a cable tray.
(Approximate location N-20)
(JB3/1) l l
l i
r r
l t
1 4
Page 3 of 3
~
M&M Protection Consultants A Resource of Marsh & McLennan December 31, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 RE: Braidwood Station Fire Protection Program Review Automatic Fire Protection System Protection Areas 1-KK1, 1-KK3, 1-KK4 & 1-KK5
Dear Mr. Elias:
Enclosed is our review of the fire protection systems protecting the hatchways and central stairvell in the Auxiliary Building, protection areas 1-KK1, 1-KK3, 1-KK4 and 1-KK5.
These are hydraulically calculated wet pipe sprinkler systems designed to provide local protection to the open areas between elevations (fire zones) in the Auxiliary Building. The systems utilize Viking 212*F rated, firematic sprinklers with 5" baffles / water shields.
It should be noted that system 1-KK2 has been incorporated into the piping of system 1-KK3.
As a result P&ID drawing M-52, sheet 8 of 14 should be changed, deleting the connection from the Auxiliary Building ring header for system 1-KK2, as no connection is present.
This review is based on NFPA 13 - Standard for the Installation of Sprinkler Systems, Viking Fire Protection Company drawings and an on-site walkdown of the installed system performed on October 24, 1985.
An evaluation of the hydraulic performance of the systems will be completed when as-built drawings of the systems become available.
If you have any questions or comments concerning our review, please contact me.
Sincerely, 47._. 8 7 J mes B. Biggins Fire Protection Associate Enclosure JBB/che cc:
J. Deress J. Brucia%
G. Jones M. Pietraszewski C. Tomashek B. Treece T. Gray R. Williams R. Salsbury E. Fitzpatrick S. Chingo R. Rakowski T. Heyer R. Smith, Jr. $
E. Crass D. Shamblin M. Balster
[.4 M. Smith M. Rybak 222 South Rivers 4e Plaza
- Chicago, filinois 60606 + 312-648-6000 (JB3/3)
l M&M Protection Consultants -
Fire Protection Area 1-KK1 Auxiliary Building - Elevation 426'-0" Hatchway at Q-12 NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems Item Reference Deficiency Resolution 1.
NFPA 13-1985 Working plans shall be submitted for Correct Viking Drawing 87 para. 1-9.1 approval before any equipment is in-to reflect actual pipe stalled or remodeled. Deviation free routing.
approved plans requires permission.
Pipe routing from the control valve to the first sprinkler head is dif-ferent than shown on Viking design drawing 87.
2.
NFPA 13-1985 Viking design drawing 87 shows the Correct Viking drawing 87 para. 1-9.1 system control valve to be a 2" OS&Y to reficct change in valve.
sete valve. Installed is an ITI-Crinnell ball valve.
3.
NFPA 13-1985 Underground mains and lead-in con-M&MPC has reviewed flushing para. 1-11.2.1 nections to system risers shall be procedure FP-21 and is a-flushed before connection to sprinkler waiting flushing to be piping.
completed.
4 NFPA 13-1985 All new systems including yard piping Verify that the required para. 1-11.2.1 shall be hydrostatically tested at 50 hydrostatic testing has
(
psi in excess of the maximum system pres-been performed.
l sure for two hours. The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system being tested.
I 5.
NFPA 13-1985 Drain valves and test valves shall Make necessary repairs to para. 3-14.1.2 be of an approved type. The handle valve.
to the system test valve has been re-moved and valve is inoperable.
6.
NFPA 13-1985 Each systes shall be provided with The ITT-Crinnel ball valve para. 3-14.2.1 a list indicating valve. The ITT-is manufactured to ASME Crinnell ball valve is not a listed SA-105 and A-216 standards valve.
and is ANSI Class 150.
This is considered adeq-l uste for this installation.
l Page 1 of 2
~
M&M Protection Consultants Fire Protection Area 1-KK1 Auxiliary Building - Elevation 426'-0" Hatchway at Q-12 NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems J
Item Re ference Deficiency Resolution 7.
NFPA 13-1985 Electrically operated alarm attachments Complete electrical in-para. 3-17.6.1 shall be installed in secordance with stallation for this device.
applicable NFPA standards. The electri-cal wiring for the waterflow detecting device for this system is not complete.
8.
NFPA 13-1985 Waterflow detecting devices, including Verify that the required para. 3-17.6.3 the associated alarm circuits, shall testing has been performed.
be tested by an actual waterflow through use of a test connection.
9.
NFPA 13-1985 Sprinklers should be so located and Obstructions are minimal and para. 4-2.3 spaced so that any interference is held do not diminish protection af-to a minimum. Sprinklers are partially forded to the hatchway. How-obstructed by a cable tray.
ever conditions at Byron Sta-tion indicate that the area to the west of the hatchway is to be used for the storage of laundry. Consideration should be given to either ex-tending two sprinklers below the cable trays or administra-tively limiting the storage of combustibles / laundry free this area.
(JB3/3) g i
n Page 2 of 2
't M&M Protection Consultants Fire Protection Area 1-KK3 Auxiliary Building - Elevations 401'-0" and 426'-0" Stairwell and Hatchway at P-18 NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Working plans shall be submitted for para. 1-9.1 approval before any equipment is in-stalled or remodeled. Deviation from approved plans requires permission.
Pipe routing to inspector's test Correct Wiking drawing 89 connection is different than shown to reflect actual pipe on Viking deaign drawing 89.
routing.
2.
NFPA 13-1985 The pipe routing between sprinklars Correct Viking drawing 88 para. 1-9.1 1 and 2 on elevation 426'-0" is to reflect actual pipe different from the routing shown on routing.
Viking design drawing 88.
1 3.
NFPA 13-1985 Ifnderground mains and lead-in connec-M6MPC has reviewed flush-para, 1-11.1.1 tions to system risers shall be flushed ing procedure FP-21 and is before connection to sprinkler piping.
awaiting flushing to be completed.
4.
NFPA 13-1985 All new systems including yard piping Verify that the required para. 1-11.2.1 shall be hydrostatically tested at 50 hydrostatic testing has psi in excess of the seximum system been performe'.
pressure for two hours. The test pres-sure shall be read from a gauge located i
at the low elevation point of the in-dividual system or portion of the system being tested.
4 5.
NFPA 13-1985 Each system shall be provided with a The ITI-Grinnell ball valve para. 3-14.2.1 listed indicating valve. The ITT-Grinnell is manufactured to ASME ball valve is not a listed valve.
SA-105 and A-216 standards and is ANSI Class 150. This is considered adequate for this installation.
I Page 1 of 2
M&M Protection Consultants Fire Protection Area 1-KK3 Auxiliary Building - Elevations 401'-0" and 426'-0" Stairwell and Hatchway at P-18 NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems Item Reference Deficiency Rasolution 6.
NFPA 13-1985 Bass or coverings placed over sprinklers para. 3-16.9.1 to protect them from painting or other processes, should be removed once the painting has been finished.
Sprinkler 2 on ':he branch line located 5 Remove covering so that feet south of Column 14 is covered.
sprinkler may actuate with-out undue delay.
7.
NFPA 13-1985 Electrically operated alarm attachments Complete electrical instal-para. 3-17.6.1 shall be installed in accordance with lation for this device.
applicable NFPA standards. The electri-cal wiring for the waterflow detecting device for this system is not complete.
8.
NFPa 21-1985 Waterflow detecting devices, including the Verify that the required para. 3-17.6.3 associated alarm circuits, shall be tested testing has been performed.
by an actual waterflow through use of a test connection.
9.
NFPA 13-1985 Sprinklers should be so located and spaced No action required. System para. 4-2.3 so that any interference is held to a is to provide area pro-minimum.
tection to the stairvell and hatchway. Obstructions are minimal and do not The sprinklers on this system are all c:euse interference to partially obstructed by hanger support sprinkler operation over.
elements and/or conduit.
these areas.
- h Page 2 of 2
9 M&M Protection Consultants Fire Protection Area 1-KKA Auxiliary Building - Elevation 383'-0" Stairvell and Hatchway at P-18 NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Underground mains and lead-in connections M6MPC has reviewed flushing para. 1-11.1.1 to system risers shall be flushed before procedure FP-21 and is connection to sprinkler piping.
awaiting flushing to be completed.
2.
NFPA 13-1985 All new systems including yard piping shall Verify that the required para. 1-11.2.1 be hydrostatically tested at 50 psi in ex-hydrostatic testing has l
cess of the maximum system pressure for two been performed.
l hours. The test pressure shall be read fros l
a gauge located at the low elevation point i
of the individual system or portion of the system being tested.
3.
NFPA 13-1985 Each system shall be provided with a The ITT-Grinnell ball valve para. 3-14.2.1 listed indicating valve. The ITT-Grinnell is manufactured to ASME ball valve is not a listed valve.
SA-105 and A-216 standards and is ANSI Class 150.
This is considered ade-quate for this installation.
4.
NFPA 13-1985 Electrically operated alars attachments Complete electrical in-para. 3-17.6.1 shall be installed in accordance with stallation for this device.
applicable NFPA standards. The electrical wiring for the waterflow detecting device for this system is not complete.
5.
NFPA 13-1985 Waterflow detecting devices, including Verify that the required para. 3-17.6.3 the associated alarm circuits, shall be testing has been perforiced.
tested by an actual waterflow through use of a test connection.
6.
NFPA 13-1985 Sprinklers should be so located and para. 4-2.3 spaced so that any interference is
(
held to a minimum.
The sprinkler surrounding the hatchway No action required. System that are north of Column 19 are part-is to provide area pro-ially obstructed by hanger support ele-tection to the hatchway.
ments.
Obstructions are minimal and do not cause an in-terference to sprinkler operation over this area.
Page 1 of 1
_._o
F M&M Protection C:msultants Fire Protection Area 1-KK5 Auxiliary Building - Elevation 364'-0" Stairwell and Hatchway at P-18 NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Underground mains and lead-in connections H&MPC has reviewed flush-para. 1-11.1.1 to rystem risers shall be flushed before ing procedure FP-21 and is connection to sprinkler piping.
awaiting flushing to be completed.
2.
NFPA 13-1985 All new systems including yard piping Verify that the required para. 1-11.2.1 shall be hydrostatically tested at 50 hydrostatic testing has psi in excess of the maximum system been performed.
pressure for two hours. The test pres-sure shall be read from a gauge located at the low elevation point of the in-dividual system or portion of the system being tested.
3.
NFPA 13-1985 Each system shall be provided with The IIT-Crinnell ball para. 3-14.2.1 a listed indicating valve. The ITT-valve is manufactured to Grinnell ball valve is not a listed ASME SA-105 and A-216 valve.
standards and is ANSI Class 150. This is con-sidered adequate for this installation.
4.
NFPA 13-1985 Electrically operated alarm attachments Complete electrical in-para. 3-17.6.1 shall be installed in accordance with stallation for this device.
applicable NFPA standards. The electrical wiring for the waterflow detecting device for this system is not complete.
5.
NFPA 13-1985 Waterflow detecting devices, including Verify that the required para. 3-17.6.3 the associated alarm circuits, shall testing has been performed.
be tested by an actual waterflow through use of a test connection.
6.
NFPA 13-1985 Spr;nklers should be so located and para. 4-2.3 spaced so that any interference is held to a minimum.
The hatchway sprinkler located 10' east No action required. System is of Column N and 7'-10\\" sou-5 of Column designed to provide area 18 is partially obstructed by a hanger protection to the hatchway, support element.
Obstruction is minimal and does not cause interference (JB3/3)
Page 1 of 1 k
M, &, M
... m..
,,.. c._,,....
C A Resource of Marsh & McLennan December 11, 1985 Mr. D. Elias Project Engineer Comonwealth Edison Coupany P.O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Automatic Fire Protection Syst m
_ Protection Area 2-CC
Dear Mr. Elias:
Enclosed is our review of the fire protection system installed for the security diesel generator and 500 gallon diesel oil storage tank rooms, protection area 2-CC.
The security diesel generator and 500 gallon diesel oil storage tank are located in two adjoining 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> rated roms. 'Ihe roms are protected by a single wet pipe sprirkler systs, designed to provide a sprinkler discharge density of 0.3 gpm/sq. ft. for the entire area of both rooms.
A total of 9 Viking 212*F rated sprinklers are utilized in this systs.
This review is based on NFPA 13 - Standard for the Installation of Sprinkler Systems, Viking Fire Protection Coupany drawings md an on-site walkdown of the installed syst e performed on October 22, 1985.
An evaluation of the hydraulic performance of the system will be com-pleted when as-built drawings of the systs became available.
If you have any questions or conments concerning our review, please contact me.
I Sincerely, l
W j
James B. Biggins y
j Fire Protection Associate V
Enclosure JBB/1w w
I cc:
J. Deress J. Bruciak G. Jones l
M. Pietraszewski C. Tomashek B. Treece T. Gray R. Salsbury R. Rakowski E. Fitzpatrick R. Williaus E. Crass T. Meyer S. Chingo M. Smith D. Shanblin R. Smith,Jr.g.
M. Rybak l
222 South Rwerside Plaza + Chicago, Illinois 60606
- 312-648-6000
7 s
..a M&M Protection Consultants Fire Protection Area 2-CC Security Diesel Generator for Oil Tank Rooms NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Underground mains and lead-in connections MinMPC has reviewed flush-para. 1-11.1.1 to system risers shall be flushed before ing procedure FP-21 and connection to sprinkler piping.
is waiting for the results of the flush.
2.
NFPA 13-1985 All new systema including yard piping Verify required hydrostatic para. 1-11.2.1 shall be hydrostatically tested at 50 psi testing has been performed.
in excess of the maximum system pressure for two hours. The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system being tested.
3.
NFPA 13-1985 Waterflow detecting devices, including the Verify the testing has para. 3-17.6.3 associated alara circuits, shall be tested been performed.
by an actual waterflow through use of a test connection.
(JB3/2)
m M&M Protection Consultants A Resource of Marsh & McLennan Noverber 26, 1985 Mr. R Elias Pre..:t Engineer Ca monwealth Edison C mpany P.O. Bax 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Autmatic Fire Protection System Protection Area 1-GG
Dear Mr. Elias:
We have empleted our review of the fire protection system installed to protect the 1,000 gallon waste oil storage tank rom, protection area 1-GG.
This is a small hydraulically calculated, wet pipe sprinkler system, utilizing 4 Viking 212' F rated sprinklers to provide area protection to the room and storage tank.
This review is based on NFPA 13 - Standard for the Installation of Sprinkler Systerr_s, Viking Fire Protection Cmpany drawmgs and an on-site walkdown of the installed system perfomed on Novernber 25, 1935.
An evaluation of the hydraulic performance of this system will be empleted when as-built drawings of the system becme available.
If you have any questions or caments conceming our review, please contact me.
Sincerely,
?^
>?
fi n r gp
~
na.-
James B. Biggins Fire Protection Associate JBE/1w c:
J. Deress J. Bruciak G. Jones M. Pietraszewski C. Tomashek B. Treece T. Gray R. Salsbury R. Rakowski E. Fitzpatrick R. Williams E. Crass T. Meyer S. Chingo M. Smith D. Shanblin R. hith, Jr. t%-
M. Balster M. Rybak
((XXM/50) 222 South Riverside P:aza
- Chicago, Illinois 60606
- 312-648-6000 L
k M&M Protection Consultants Fire Protection Area 1-GG Auxiliary Building 1,000 Gallon Weste Oil Tank NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Working plans shall be submitted for Correct Vizing drawing 49 to para. 1-9.1 approval before any equipment is in-reflect actual installation.
stalled or remodeled. Deviation from approved plans requires permission.
Viking design drawing 49 shows the system control valve to be a 2 -inch, flanger OS&Y valve. An ITT Grinnell ball type valve is installed.
2.
NFPA 13-1985 IJnderground mains and lead-in connections M&MPC has reviewed flushing pro-para. 1-11.1.1 to system risers shall be flushed before cedure. FP-21 is waiting for re-connection to system piping.
sults of flushing.
3.
NFPA 13-1985 All new systems including yard piping shall Verify that the required hydro-para. 1-11.2.1 by hydrostatically tested at 50 pai in ex-static teating has been performed cess of the maximum system pressure for two hours. The test pressure shall be read from a gage located at the los elevation point of the individual system being tested.
4.
NFPA 13-1985 Each system shall be provided with a listed The ITT - Grinnell ball valve para. 3-14.2.1 indicating valve so located as to control all are manufactured to ASME SA-105 sources of the water supply. The ITI-Grinnell and A-216 standards and are ball type valve, utilized as the system control ANSI Class 300. This is con-valve, is not listed, sidered adequate for this in-stallation.
5.
NFPA 13-1985 Waterflow detecting devices, including the Verify that the required testing para. 3-17.6.3 associated alarm circuits, shall be tested has been performed.
by an actual waterflow through the use of a test connection.
6.
NFPA 13-1985 Deflectors of sprinklers in bays shall be para. 4-2.4.6 at a sufficient distance from the beams to avoid obstruction to the sprinkler dis-charge pattern.
The sprinkler located 5\\' west of column M is No action required. Present in-is partially obstructed by a team, sta11ation will provide adequate protection to the storage tank and room.
UB1/15)
Page 1 of I h
A Technical Service of Marsh & McLennan July 19, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Automatic Fire Protection Systems Protection Area 1-F
Dear Mr. Elias:
Enclosed is our review of the fire protection system installed in the Clean and Dirty 011 Tank Room, Area 1-F.
This system is a wet pipe automatic sprinkler system, with sprinklers located at the ceiling and at the underside of the tanks. Twenty-six Viking 212*F rated, upright sprinklers are used, providing an area of coverage of 68.4 square feet i
per sprinkler. An evaluation of the hydraulic performance of the system will be made at a later date.
If you have any questions or comments concerning our review, please call.
Sincerely, Sh&
James B. Biggins Senior Fire Protection Specialist JBB/pcm Enclosure cc:
J. Deress J. Bruciak G. Jones M. Pietrazewski C. Tomashek B. Treece T. Gray W. Vahle R. Salsbury J. Gudac R. Williams R. Rakowski T. Meyer S. Chingo E. Crass D. Shamblin R. Smith, Jr.
(JB2/11) 222 South Riverside Plaza, Chicago, Illinois 60606, Telephone 312 6484000
' f -
t.
M&M Protection Consultants Fire Protection Area 1-F Clean and Dirty 011 Tank Room NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1
NFPA 13-1985 Undergrotmd mains and lead-in connectior.s IEMPC has reviewed para. 1-11.1.1 to system rivers shall be flushed before flushing precedure FP-21 connection to sprinkler piping, and is awaiting ravised procedure.
2 NFPA 13-1985 All new systems including yard piping shall Verify required hydro-para. 1-11.2.1 be hydrostatically tested at 50 psi in excess static testing has been of the maximum systes pressure for two hours.
performed.
The test pressure shall be read from a gauge located at the low elevation point of the individus1 system or portion of the system being tested.
3 NFPA 13-1985 Waterflow deteeting devices, including the Verify the testing has para. 3-17.6.3 associated alarm circuits, shall be tested been performed.
by an actual waterflow through use of a test connection.
t., -.
u
(
1 o
M&M Protection Consultants A Resource of Marsh & McLennan November 11. 1985 Mr. D, Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Automatic Fire Protection System Protection Area 1-Y
Dear Mr. Elias:
We have completed our review of the fire protection system installed in the Peceiving Building and Receiving Building Warehouse. Protection Area 1-Y.
This is a single wet pipe sprinkler system providing protection to these two adjoining buildings.
The Receiving Building contains general storage of Class II and Class III combustibles. This portion of the sprinkler system is installed utilizing ordinary hazard pipe sizing and spacing, i
The Receiving Building Warehouse contains storage of Class II and Class III combustibles in a double row rack storage arrangement.
The aisles between the racks are eight feet wide and the maximum neight of storage is 20 feet. This portion of the system is an hydraulically calculated, gridded sprinkler system that is designed to provide a sprinkler discharge density of 0.33 gpm/ square foot over the hydraulically most remote 3,000 square feet protected by the system.
A mezzanine level has been installed in the southeast corner of the Receiving Building Warehouse. Presently, only noncombustible bar stock is stored below the mezzanine level and installation of additional sprinkler protection below the mezzanine level is not needed at this time. However, if storage arrangements change and combustible storage is placed below the mezzanine level, additional sprinkler protection should be provided.
Thie review is based on NFPA 13 - Standard for the Installation pf_
Sprinkler Systems, NFPA 231c - Standard for Rack Storage of Materials, Viking Corporation drawings and an on-site walkdown of the installed system performed on October 22, 1985. An evaluation of the hydrau-lic performance of the system will be ccepleted when as-built drawings of the system become available.
222 South Riverside Plaza a Chicago,lilinoes 60606
- 312448-6000 J
M&M Protection Consultants Mr. D. Elias November 11, 1985 Page 2 If you have any questions or comments concerning cur review, please contact me.
Sincerely.
ssA?k c
n-James B. Biggins Fire Protection Associate JBB/pem Enclosure cci J. Deress J. Bruciak G. Jones M. Pietrazewski C. Tomashek B. Treece T. Gray W. Vahle R. Salsbury J. Cudae R. Williarss R. Rakowski T. Meyer S. Chingo E. Crass D. Shamblin R. Smith, Jr.
M. Smith M. Rybak M. Balster (JB2/38) t
W.M Protection Consultants 4
Jire Prntection Area 14 Receiving; Building and Receiving Building Warehouse NFPA 13-1985 Stond.ard for the Installation of $prinkler Systeas NFPA 231c-1980 Standard for Rack Storage of Materials Ites Petereng gficiency Resolution 1
NFPh 13.1985 Ebrki+g plans shall show locations Correct Viking drawing 29 para 1-9.2 of us11s and partitions. 1he wall along to show location of well.
coltann $1 between columns C and E is not stcnc on Viking drawing 29.
2 ttFTA 13-1955 Viking drawing 29 shows 160'F rated upri,ht Use of 212'F rated sprin-para. 1-9.2 style sprinsters installed in the receiving klers is acceptable for building, 212'T rated upright style sprin-this loc.atten. Correct Viking kirts are instelled.
des".g 29 *s reflect actual installation.
3 NFPA 1.1-1985 Underground gains and lead-in connections MMPC has reviewed flushing psta. 1-11.1.1 to spa n :isers shall be flush *1 befsre procedure FP-21 and is await-cosncetion to systes nioir ;.
In ; completion of rystem a
flushir.g.
A rFPA 13-1985 All new syste:ss including yard piping shall Verify that the required p o r s, 1-11.2.1 be hydrostatically tested at 50 poi in hydrostatic testing has been extems of the taxistse systern pressure for perforced.
two h2urs. 1he test stessure shall be reed frt s e gauge located at the Icw elevation poht of the individual systes teing tested.
5 NFFA 13-1985 Esterflow detecting devices, including the Verify th.at t'.4e required pra. 3-17.6.3 m:isociated alsts circuits, shall be tested testing has been perfomed.
by an actual wterflow through mee of a test connection.
frTA 13-1H5 Sprinklers shos1d be so located and spaced 6
r para. 4 2/J so that any interference is held to a minimas.
SprinLIer.s 2, 3 sad 4 os the branch line Reroute conduit or install installes 61/4 feet nurth of colu:rt B are pendent style sprbklers so obatructed by conduit. Opprox!aate loca-that interference to sprinkler tien B 51) discharge is minimized.
. o..
i M&M Protection Consultants Tsen Reforence Deficiency Resolution i
7 NFPA 13-1985 Sprinkler 5 on the branch line installed Install pendent style sprin-pers. & 2.3 61/4 feet north of c?len 13 i'. e6structed kler so that interference to by an electrical junction boa. (Approminate sprinkler discharge is loc.ation 3-50) minimised.
8
.NFPA 13-1985 R e sprinkler' located 12*S" east of column a Raise sprinkler to a position para. 4-2.3 and 5' south of column F ic the Ret.eiving so that the deflect 0r is even Building Warehosse is obstru.:ted by a with the bottom line of the banger support element.
bem located to the north of the sprinkler.
L 9
NFPA 231C-1980 Aisle widels shall be meintained clear and Care should be taken to limit pera. 4-4.2 free of congestion caused by starsee of storage of consodities in the esemodities in the ais3es.
atales between racks.
10 NFPA 231C-1980 seeking shall be strictly prohibited, eacept Post No Smoking" signs in the para. 9-3 in locations prominently designeted as smoking Receiving Building and areas, and "No Smoking" signs shall be posted Receiving Building Warehouse.
in prohibited areas.
11 NFPA 231C-1980 Fire walls, fire doors and floorp shall be Asmove plywood sheets and pers. 9-4 asintained in good repair at all times. 2he provide a suitable doorway doorway between the Receiving Building and f6r this opening.
the Receiving Building Warehouse is closed off by sheets of plywood.
(JB2/38a)
L
M&M Protection Consultants A Technical Service of Marsh & McLennan September 30, 1985 i
Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEM PROTECTION AREA 1 - P
Dear Mr. Elias:
Enclosed is our review of the fire protection system for the Diesel Fire Pump Room, Protection Area 1 - P, located in the Lake Screenhouse. This is an automatic wet pipe sprinkler system consisting of one upright and six sidewall Viking, 212*F rated, sprinklers. The system protects the 575 gallon diesel oil storage tank and diesel driven fire pump which are located within the room. The system is designed to provide a water application density of 0.3 gpm/ square foot over the 27 square foot area of the room.
If you have any questions or comments concerning our review, please cc,1 tact me.
Sincerely.
W Ja d 'Biggins Fire Protection Associate JBB/1w Enclosure cc:
J. Deress J. Bruciak G. Jones M. Pietraszewski C. Tomashek B. Treece T. Gray W. Vahle R. Salsbury J. Gudac R. Williams R. Rakowski T. Heyer S. Chingo E. Crass D. Shamblin R. Smith, Jr.
M. Smith H. Rybak H. Balster (JB2/34)
. 222 South. Riverside Plaza, Chicarp, Illinois 60606, Telephone 312 6484000 _
M&M Prokction Consultants Fire Protection Area 1-P Lake Screen House - Diesel Fire Pump and Oil Storage Tank NFPA 13-1985 Standard for the Installation of Sprinkler Systems i
Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Working plans shall be submitted for para. 1-9.1 approval before any equipment is in-stalled or remodeled. Deviation from approved plans requires permission.
Control valve is labeled OFP224 on Viking Determine whether Viking drawing 35, the n 1ve is field tagged 0FP232A drawing 35 or field tagging of valve is in error and make necessary corrections.
2.
NFPA 13-1985 The piping for the sprinkler for the under-Correct Viking drawing 35 para. 1-9.1 side of the tank and inspector's test con-to show actual installation.
nection is installed in a different config-uration than is shown in the drawing.
3.
NFPA 13-1985 A valve is installed at the position of the Valve can be removed or left para. 1-9.1 original pipe routing to the underside of as an auxiliary drain valve.
the tank.
Correct Viking drawing 35 to reflect decision.
4.
NFPA 13-1985 The sprinkler at the underside of the tank The use of a guard is de-para. 1-9.1 is shown to have a headguard on Viking sirable but not necessary, drawing 35. No guard is installed.
Either install guard as shown on Viking drawing 35 or change drawing to show actual installation.
5.
NFPA 13-1985 Underground mains and lead-in connections M6MPC has reviewed flushing para. 1-11.1.1 to system risers shall be flushed before procedure FP-21 and is connection to sprinkler piping.
awaiting flushing to be completed.
6.
NFPA 13-1985 All new systems including yard piping shall Verify that the required l
para. 1-11.2.1 be hydrostatically tested at 50 psi in ex-hydrostatic testing has l
cess of the maximum system pressure for two been performed.
hours. The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system being tested.
I l
l l
l I
i Page 1 of 2
'~~~~
M&M Protection Consultants Item Re ference Deficiency Resolution 7.
NFPA 13-1985 Waterflow detecting devices, including the Verify that the required para. 3-17.6.3 asso:iated alarm circuits, shall be tested testing has been performed.
by an actual waterflow through use of a test connection.
8.
NFPA 13-1985 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a minimum.
Sprinkler 2 on branch line 2 is partially No action required. Inter-obstructed by conduit.
ference to sprinkler dis-charge is minimal and accept-able.
(JB2/35) i i
l l
i l
l i
l Page 2 of 2
77s A Technical Service of Marsh & McLennan September 13, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEMS PROTECTION AREAS 1-M, 1-L AND 1-G
Dear Mr. Elias:
Our reviews of the fire protection systems installed on the various elevations of the Service Building storeroom (Protection Areas 1-M, 1-L and 1-G) have been completed. These are three wet pipe sprinkler systems each providing protection to a single floor of the storeroom which are supplied by a single sprinkler riser. The systems have been designed to actuate and alarm independently.
The storeroom at elevation 401', protection area 1-M, is protected by a sprinkler system utilizing ordinary hazard pipe sizing and spacing. The adjoining paint and oil storage room is protected by the same system, however, extra hazard pipe sizing and spacing is utilized due to the amount of flammable and combustible liquids stored within the room.
Coverage per sprinkler is 79.0 square feet in the storeroom and 69.2 square feet in the paint room. Sixty-five Viking 212*F rated sprinklers of various styles are installed.
The sprinkler system installed in the storeroom at elevation 417',
protection area 1-L utilizes 48 Viking 212*F rated sprinklers to achieve of coverage per sprinkler of 77.8 square feet. The sprinkler system at elevation 433', protection area 1-G, utilizes 68 Viking 212*F rated sprinklers to provide a coverage per sprinkler of 76.2 square feet. Both systems are designed using ordinary hazard pipe sizing and spacing.
222 South Riverside Plaza, Chicago, Illinois 60606, Telept.one 312 6484000_ _ _ _ _ _
M&M Protection Consultants Mr. D. Elias September 13, 1985 Page 2 This review te based on NFPA 13 - Standard for the Installation of Sprinkler Systers, Viking Corporation drawings and an on-site walkdown of the installeo systems. An evaluation of the hydraulic performance of the systems will be completed when as-built drawings of the systems become available.
If you have any questions or comments concerning our review, please contact me.
Sincerely,
~gTA-w (V W James B. Biggins Fire Protection Associate JBB/1w Enclosure cc:
J. Deress J. Bruciak G. Jones M. Pietraszewski C. Tomashek B. Treece T. Gray W. Vahle R. Salsbury J. Gudac R. Williams R. Rakowski T. Meyer S. Chingo E. Crass D. Shamblin R. Smith, Jr.
M. Smith M. Rybak M. Balster (JB2/21)
M&M Prot:rtion Censultants Fire Protection Area 1-M Service Building Storeroom and Paint Roon Elevation 401' NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1
NFPA 13-1985 Working plar.s shall be submitted for para. 1-9.1 approval before any equipment is installed or remodeled. Deviation from approved plans requires permission.
Sprinkler 1 on the branch line located Correct Viking drawing in the paint room 3" south of column 43 18 to reflect actual is shwon as an upright style sprinkler installation.
on Viking drawing 18. A pendent style sprinkler is installed. (Approximate location A-43) 2 NFPA 13-1985 An alarm horn is installed in place of the Current Viking drawing para, 1.9.1 the alarm bell shown on Viking Drawing 18.
18 to show installation of an alarm horn in place of the alarm bell.
3 NFPA 13-1985 Working plans shall show ceiling construc-Correct Vikir.d drawing 18 para. 1-9.1 tion. A hatchway is shown on Viking drawing to show actual ceiling 18 at location B-40.
H ere are no hatchways construction.
in the storeroom.
4 NFPA 13-1985 Underground mains and lead-in connections IEMPC has reviewed flushing to system risers shall be flushed before procedure FP-21 and is connection to sprinkler piping.
awaiting revised procedure.
5 NFPA 13-1985 All new systems including yard piping shall Verify that the required para. 1-11.2.1 be hydrostatically tested at 50 psi in excess hydrostatic testing has been of the maximum system pressure for two hours.
- perforwd, h e test pressure shall be read from a gauge located at the low elevation point of the I
individual system or portion of the system being tested.
6 NFPA 13-1985 A test pipe not less than 1 inch in diameter Verify that the orifice plate para. 3-9.1.1 terminating in a smooth bore corrosion installed in this line is
& 1-9.1 resistant orifice giving a flow equivalent 1/2 inch in diameter and to one sprinkler shall be provided. ne correct Viking drawing 18 test line for this system is piped to reflect. actual instal-directly into a floor drain downspout.
- lation, j
ne line is supplied with a fitting for
)
an orifice plate.
j Page 1 of 4 os em
M&M Prot:cti:n Censultants
)
Item Re ference Deficiency Resolution 7
NFPA 13 1985 Valves on connections to water supplies Station plans to lock all para. 3-14.2.3 shall be supervised open. Control valve valves into position before OFP224A at sprinkler riser has no super-
' fuel receipt. Install vision. Tamper switch shown on Viking tamper switch to comply drawing 18 is not installed, with commitments in the Station Fire Protection Report.
8 NFPA 13-1985 The alarm apparatus for a wet pipe system Install waterflow device para. 3-17.3.1 shall consist of a listed waterflow as shown on Viking drawing detecting alarm device with the necessary 18.
attachments. The waterflow detecting device shown on Viking drawing 18 (D.1-41) is not installed.
9 NFPA 13-1985 Waterflow detecting devices, including the Verify that the required para. 3-17.6.3 associated alarm circuits, shall be tested testing has been performed.
by an actual waterflow through use of test connection.
10 NFPA 13-1985 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a minimum.
Sprinkler 3 on the branch line 5'2" west Sprinkler is installed under of column D.1 is obstructed by conduit.
a besa. Install pendent style (Approximate location D.1-41) sprinkler to eliminate interference to dis-charge pattern.
11 NFPA 13-1985 Sprinklers 4 and 5 on branch line 2 Raise sprinklers 4 inches para. 4-2.3 are obstructed by hanger support elements.
to minimize interference to the sprinkler discharge pattern.
12 NFPA 13-1985 Sprinkler 1 on branch line 2 is partially No action required, inter-para. 4-2.3 obstructed by an HVAC duct.
ference to sprinkler dis-charge is minimal and discharge pattern is adequate.
t 13 NFPA 13-1985 Sprinkler 2 on the branch lines located Reroute conduit so that para. 4-2.3 4'3" and 12'9" west of column B are interference to sprinkler obstructed by conduit. (Approximate discharge is minimized.
location A-41)
(1 foot laterally or 3 inches vertically) 14 NFPA 13-1985 Sprinkler 1 on the branch line 5'7" east No action required, inter-para. 4-2.3 of column A is partially obstructed by a ference to sprinkler dis-light fixture. (Approximate location charge is minimal and I
A-43) discha ge pattern is adegaate.
I l
i l
f Page 2 of 4 c,,
[
M&M Pr:t:ction Censultants Item Re ference Deficiency Resolution 15 NFPA 13-1985 Sprinkler 1 on the branch line 5'7" east Raise sprinkler 4 inches para. 4-2.3 of column A is obstructed by a hanger so that interference support. (Approximate location A-41) to sprinkler discharge is minimited.
16 NFPA 13-1985 Sprinkler 1 on the branch line located Cut support element so para. 4-2.3 12'9" unst of colu n B, is installed so it Goes not extend over that the deflector is less than 1 inch sprinkler deflector, below a hanger support element.
(Approximate location B-37) 17 NFPA 13-1985 Sprinkler 3 on the branch line located No action required, inter-para. 4-2.3 4'3" west of column B is partially forence to sprinkler dis-obstructed by a ceiling heater, charge is minimal and dis-(Approximate location B-39) charge pattern is adequate.
18 NFPA 13-1985 Sprinkler 4 on the branch line located Install a pendent style para. 4-2.3 4'3" west of column B is obstructed by a sprinkler and reroute hanger support and conduit. (Approximate conduit so that interference location B-39) to sprinkler discharge is minimized.
19 NFPA 13-1985 Sprinkler 1 on branch line 5 is Raise sprinkler 6 inches para. 4-2.3 obstructed by a hanger support element.
to minimise interference to sprinkler discharge pattern.
20
.NFPA 13-1985 Sprinkler 2 on branch line 6 is No action required, inter-para. 4-2.3 obstructed by a light fixture, forence to sprinkler is minimal and discharge pattern is adequate.
21 NFPA 13 1985 Sprinkler 3 on branch lines 4 and 5 No action required, inter-para. 4-2.3 are partially obstructed by a light ference to sprinkler dis-fixture.
charge is minimal and dis-charge pattern is adequate.
22 NFPA 13-1985 Sprinkler 4 on branch line 4 is Raise sprinkler 4 inches to para. 4-2.3 obstructed by conduit.
minimise interference to sprinkler discharge pattern.
23 NFPA 13-1985 Sprinkler 5 on branch lines 4 and 5 Replace upright style sprin-para. 4-2.3 and sprinkler 4 on branch line 6 are klers with a pendent style obstructed hanger support elements sprinkler to minimise inter-and conduit. Also deflectors are less ference to sprinkler dis-than 1 inch below bottom of beam, charge pattern.
Page 3 of 4
s e
M&M Prot:ction Censultants Ites Reference Deficier.cy Resoltition 24 NFPA 13-1985 Deflectors of sprinklers in bays shall para. 4-2.4.6 be at a sufficient distance from the beams to avoid obstruction to the sprinkler discharge pattern.
Sprinkler 1 on branch line 6 is installed No action required, although 3 inches above the bottom line of a discharge will be obstructed beam located less than 1 foot away.
by beam, the sidewall sprin-kler on branch line 5 will provide adequate sprinkler coverage to area.
(JB1/3) f l
Page 4 of 4
M&M Prot:ction Censultants Fire Protection Area 1-L Service Building Storeroom - Elevation 417' l
NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution 1.
NFPA 13-1985 Working plans shall be submitted for para. 1-9.1 approval before any equipment is in-stalled or remodeled. Deviation from approved plans requires permission.
An alars horn is installed in place of Correct Viking drawing 19 the alarm bell shown on Viking drawing 19.
to show installation of an alarm horn in place of the alars bell.
2.
NFPA 13-1985 Working plans shall show ceiling construction.
Correct Viking drawing 19 para. 1-9.2 A hatchway is shown on Viking drawing 19 at to show actual ceiling location B-40.
There are no hatchways in the construction.
storeroce.
3.
NFPA 13-1985 Underground mains and lead-in connections M6MPC has reviewed flushing para. 1-11.1.1 to system risers shall be flushed before procedure FP-21 and is connection to sprinkler piping.
swaiting revised procedure.
4.
NFPA 13-1985 All new systems including yard piping shall Verify that the required pa ra. 1-11. 2.1 be hydrostatically tested at 50 psi in exce se hydrostatic testing has of the maximum systes pressure for two hours.
been performed.
The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system being tested.
5.
NFPA 13-1985 Waterflow detecting devices, including the Verify that the required para. 3-17.6.3 associated alarm circuits, shall be tested testing has been performed.
by an actual waterflow through use of a test connection.
6.
NFPA 13-1985 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a mini-WW.
Sprinkler 1 on branch line 16 is obstructed Raise sprinkler 6 inches by a hanger support element.
so that the obstruction to the sprinkler discharge is minimized. -
Page 1 of 2
M&M Prot:ction Consult:nts Item Re ference Def!:lency Rasolution 7.
NFPA 13-1985 Sprinkler 2 on branch line 16 is partially No action required, fixture para. 4-2.3 obstructed by a light fixture.
causes only minimal ob-struction and discharge pat-tern of sprinkler is adequate.
8.
NFPA 13-1985 Sprinkler 4 on branch line 16 is ob-Raise sprinklers 5 inches para. 4-2.3 structed by a hanger support element so that obstruction to and conduit.
sprinkler discharge is minimized.
9.
NFPA 13-1985 Sprinklers 3 and 4 on branch line 12 Raise sprinkler 5 inches para. 4-2.3 is obstructed by a hanger support ele-so that obstruction to ment and conduit.
sprinkler discharge is minimized.
10.
NFPA 13-1985 Sprinkler 4 on branch line 19 is partially No action required, only para. 4-2.3 obstructed by a hanger support element and minimal obstruction occurs and conduit.
and sprinkler discharge pattern is adequate.
11.
NFPA 13-1985 Deflectors of sprinklers in bays shall be at a sufficient distance from the beams to avoid obstruction to the sprinkler discharge pattern.
Sprinkler 1 on branch line 17 is 1 inch above A horizontal side wall the bottom line of a beam 6 inches away.
sprinkler should be in-stalled at this location to protect stairway.
(JB2/26)
I i
1 l
l Page 2 of 2 pe.
f*'
M&M Prot:ction Consultants
~
Fire Protection Area 1-G Service Building Storeroom - Elevation 433' NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference De ficiency Resolution 1.
NFPA 13-1985 Working plans shall be submitted for para. 1-9.1 approval before any equipment is in-stalled or remodeled. Deviation from approved plans requires permission.
Sprinkler 8 on branch line 31 is shown Correct Viking drawing 20 on drawing as a pendent style sprinkler.
to show actual instal-An upright style sprinkler is installed.
lation.
2.
NFPA 13-1985 Sprinkler 1 on branch line 29 is shown on Correct Viking drawing para. 1-9.1 drawing as an upright sprinkler. A pen-20 to reflect this dent style sprinkler is installed.
installation.
3.
NFPA 13 1985 Sprinkler 2 on branch lines 23 and 24 are 11se of pendent style para. 1-9.1 shown as upright sprinklers on plans, sprinklers is necessary Pendent style sprinklers are installed, due to location below beam. Correct Viking drawing 20 to reflect this installation.
4.
NFPA 13-1985 h o additional sprinklers were added to Correct Viking drawing 20 para. 1-9.1 tranch line 22 to provide protection be-to show additional sprinklers.
Iow ventilation duct.
S.
NFPA 13-1985 An alarm horn is installed in place of the Correct Viking drawing 20 para. 1-9.1 alarm bell shown on Viking drawing 20.
to show installation of an alars horn in place of the alars bell.
6.
NFPA 13-1985 11nderground mains and lead-in connections M&MPC has reviewed flushing para. 1-11.1.1 to system risers shall be flushed before procedure FP-21 and is connection to sprinkler piping.
awaiting revised procedure.
Page 1 of 2
' ', ~ ',
M&M Prot:ction Censult:nts e
Item Re ference Deficiency Resolution 7.
NFPA 13-1985 All new systems including yard piping shall Verify that the required para. 1-11.2.1 be hydrostatically tested at 50 pai in excess hydrostatic testing has been of the maximum system pressure for two hours.
performed.
The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system being tested.
8.
NFPA 13-1985 Waterflow detecting devices, including the Verify that required testing para. 3-17.6.3 associated alars circuits, shall be tested has been performed.
by an actual waterflow through use of a test connection.
9.
NFPA 13-1985 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a minimum.
Sprinkler 1 on branch line 21 is partially Raise sprinkler 6 inches obstructed by a hanger support.
so interference is min-inised.
10.
MFPA 13-1985 Sprinkler 2 on the branch lines located 3'11" No action required, only para. 4-2.3 and 11'9" west of column B are partially ob-minimal cbstruction occurs structed by hanger supports. (Approximate and sprinkler discharge location B-41) is adequate.
11.
MFPA 13-1985 Sprinkler 2 on the branch lines located 6" No action required, only para. 4-2.3 and 9'7" east of column A are partially ob-minimal obstruction occurs structed by hanger supports and light fia-and sprinkler discharge tures. (Approximate location A-41) is adequate.
12.
NFPA 13-1985 The sprinklers on the branch line located No action required. Spray para 4-2.3 4'%" from column D.1 are partially obstructed pattern from present instal-by hanger supports. (Approximate location lation will provide adequate D.1-37 to 41) coverage.
13.
MFPA 13-1985 Deflectors of sprinklers in bays shall be at para. 4-2.4.6 a sufficient distance from the beams to avoid obstruction to the sprinkler discharge pattern.
Sprinkler 5 on branch line 31 is installed 3 Install pendent style sprin-inches above the bottom of a beam 1 foot away.
klar to minimize interference to sprinkler discharge pattern.
(JB2/22)
Page 2 of 2 is
pummmmmersmimmrr on consms A Technical Service of Marsh & McLennan August 29, 1985 Mr. D. Elias
)
Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Automatic Fire Protection Systems Protection Area 2-HH
Dear Mr. Elias:
Enclosed is our review of the fire protection system installed in the Waste Treatment Building, Protection Area 2-HH.
This is a partial wet pipe sprinkler installation protecting the curbed area surrounding the 1,000-gallon waste oil tank located in the building. The system con-sists of three 212*F rated Viking upright sprinklers, two located above the tank at the ceiling and one located at the underside of the tank.
The system is designed to provide a water application density of 0.3 gpm/sq. ft.
This review was based on NFPA 13 - Standard for the Installation of Sprinkler Systems, Viking Corporation drawings and an on-site walkdown of the installed system. An evaluation of the hydraulic performance of the system will be made when as-built drawings of the system are available.
If you have any questions or comments concerning our review, please contact me.
l l
Sincerely, S ?' W ames B. Biggins Fire Protection Associate JBB/pem Enclosure cc:
J. Deress D. Shamblin H. Smith M. Pietrazewski M. Balster R. Smith, Jr.
T. Gray J. Bruciak C. Jones R. Rybak C. Tomashek B. Treece J. Gudac W. Vahle R. Salsbury T. Meyer R. Williams R. Rakowski S. Chingo E. Crass (JB2/23) 222 South Riverside Plata, Chicago, Illinois 60606, Telephone 312 64843000
M&M Protection Conudtants v
.l Fire Protection Area 2-1B Weste Treatment Building NFPA 13-1985 Standard for the Installation of Sprinkler Systems
- Item Re ference Deficiency Resolution i
'1 NFPA 13-1985 Working plans shall be submitted for approval.
Present installation is advisable.
para. 1-9.1 Deviation from approved plans requires permission.
Correct Viking drawing number 63 to Sprinkler at the underside of the tank is shown as reflect actual installation.
a pendent style sprinkler on drawings, an upright sprinkler is installed.
i 2
NFPA 13-1985 Underground asins and lead-in connections to IEMFC has reviewed flushing procedure
{
para. 1-11.1.1 system risers shall be flushed before connection FF-21 and is awaiting revised to the sprinkler piping.
procedure.
3 NFPA 13-1985 All new systems including yard piping shall be Verify that the required hydrostatic para. 1-11.2.1 hydrostatically tested at 50 poi in excess of hydrostatic testing has been performed.
the maximum systes pressure for two hours.
The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system l
being tested.
j 6 NFPA 13 1985 Each system shall be provided with a listed this is a 600 poi rated, forged steel, para. 3-14.2.1 indicating valve so located as to control globe style valve manufactured to ASTM all sources of water supply. No approval Standard A-105. This valve is considered
?
listing can be located for the two-inch acceptable for this installation.
Rockwell Edwards valve, OFF532A, figure 848y type.
I NFPA 13-D85 Waterflow detecting devices, including the Verify that that the required testing para. 3 17.6.3 associated alarm circuits, shall be tested has been performed.
by an actual waterflow through use of a test connection.
)
I i
I i
P i
052/23)
I r
i M&M Protection Consultants A Technical Service of Marsh & McLennan June 18, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Automatic Fire Protection Systems Protection Area 1-BB
Dear Mr. Elias:
We have begun our review of the various fire protection systems installed at the Braidwood Nuclear Station. We will be evaluating each system separately and the review of each system will be forwarded to you upon its completion, in order that any necessary changes can be made without undue delay. The evaluations are made in accordance with the appropriate NFPA Standards and are based on Viking Corporation drawings and on site walkdowns of the installed systems. The appropriate NFPA Standards used to evaluate each system will be listed at the beginning of each review.
After our evaluation of all the individual systems is complete, we will issue a review of the items which pertain to the entire plant (such as stock of spare sprinklers, etc.).
Enclosed is the review for the fire protection system installed in the Unit 1 Auxiliary Boiler Room. Area 1-BB.
This system is a wet pipe automatic sprinkler system utilizing extra hazard pipe sizing and spacing. Thirty-eight Viking 212*F rated, upright sprinklers are used, providing an area of coverage of 63.1 square feet per sprinkler. An evaluation of the hydraulic performance of the system will be made af ter all necessary changes in the piping layout are made. Additionally, since the system is installed and operational, the temporary sprinklers and piping located under the ducts in front of the boiler can and should be removed.
If you have any questions or comments concerning our review, please l
call.
Sincerely, n $ S.-* a.
Yv James B. Biggins Senior Fire Protection Specialist JBB/pcm Enclosure cc J. Deress T. Meyer R. Williams B. Treece M. Pietrazewski D. Shamblin S. Chingo R. Salsbury T. Gray C. Tomashek R. Smith, Jr.
R. Rakowski J. Gudac W. Vahle G. Jones E. Crass T?,outh Riverside Plan, Chicago, Illinois 60606, Telephone 312 6484000
M&M Protection Consult:nts Fire Frotectioa Area 1-BB Unit One Auxiliary Boiler Room NFPA 13-1985 Standard for the Installation of Sprinkler Systees Iten Re ference De ficiency Resolution 1
NFPA 13-1985 Underground mains and lead-in connections y has reviewed para. 1-11.1.1 to system risers shall be flushed before f1phing procedure FP-21 connection to sprinkler piping.
and is awaiting revised procedure.
2 NFPA 131985 All new systems including yard piping shall Verify required hydro-para. 1-11.2.1 be hydrostatically tested at 50 psi in excess static testing has been of the maximum system pressure for two hours.
performed.
The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system i
being tested.
3 NFPA 13-1985 2he inside sprinkler piping shall be installed Repair or replace valve para. 1-11.2.2 in such a manner that there will be no visible to stop leaking.
leakage when the system is subjected to the hydrostatic pressure test. Valve OFP250A is leaking.
4 NFPA 1319d5 A protective coating shall be applied to Paint pipe as needed.
para. 310.2.1 all unprotected surfaces of the sprinkler system to resist corrosion. Sprinkler piping under duct is not painted.
NFPA 13 1985 Sprinklers shall be installed in accordance Reinstall sprinkler in para. 3-16.2.1 with their listing. Sprinkler number 2 on correct manner.
branch line 10 is an upright sprinkler 4
installed as a pendent sprinkler.
6 NFPA 13 1985 Waterflow detecting devices, including the Verify the testing has para 3 17.6.3 associated alarm circuits, shall be tested been done.
by an actual waterflow through use of a test connection.
7 NFPA 131985 Deflectors of sprinklers shall be at suffia Reinstall sprinklers so para. 4 2.4.6 cient distances from structural members to that the deflectors are avoid obstruction to the sprinkler discharge no more than 1 inch pattern. The following sprinklers are above the bottom of the located so that their flow pattern is parti-
- bese, ally obstructed and should be relocated so that the top of the deflector. All sprinklers on branch lines 8 and 9 are located less than two feet from the beam running along the sixth line and the deflectors are more than one inch above the bottom of the bese.
, es es
.. +.
M&M Prot:ction Ccnsult:nts Item Re ference De ficiency Resolution 8
NFPA 13-1985 Sprinkler number 2 on branch line 2A Reinstall sprinkler so that para. 4-2.4.6 is installed approximately 6 inches the top of the deflector is laterally from a 4-inch beam.
no higher than the bottom of the beam.
9 NFPA 13-1985 Sprinkler number 3 on branch line 6 Reinstall sprinkler so that para. 4-2.$.6 is located 4 inches laterally from the top of the deflector is a hanger for the heating duct.
no higher than the bottom the hanger.
10 NFPA 13-1985 Sprinkler number 1 on branch line 11 Reinstall sprinkler so that para. 4-2.4.6 is installed 3 inches from a besa, the top of the deflector is no higher than the bottom of the beam.
11 NFPA 13-1985 Sprinkler number 1 on branch line 6 Reinstall sprinkler so that para. 4-2.4.6 installed on the inside of an 8-inch the top of the deflector is pipe elbow in such a manner that its no higher than 1 inch above flow will be restricted.
the bottom of the piping.
12 NFPA 13-1985 Deflectors of sprinklers shall be Reinstall sprinklers so that para. 4-3.1 located 1 inch to 12 inches below at itsee 1 inch of clearance noncombustible smooth ceilings.
is provided.
Sprinklers 2 and 3 on branch line 7 are located less than 1 inch below heating duct which is con-sidered e amooth ceiling by the code.
83 44
YE.5d5EEEE E
A Technical Service of Manh & McLennan September 25, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Compana P. O. Box 767 Chicago, IL 60690 Ret BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEM PROTECTION AREA 1 - E
Dear Hr. Elias:
We have completed our review of the fire protection system installed on the unit one mezzanine level of the Turbine Building, Protection Area 1
- C.
This is a wet pipe sprinkler system having a spacing of 100 square feet per sprinkler at a density of 0.3 gpm/sq. ft. for any 3000 sq. ft. area and 0.2 gpm for any 10,000 sq. ft. area. The system was designed utilizing 318 Viking 212' F rated, sprinklers to obtain the designed coverage.
This review is based on NFPA 13 - Standard for the Installation of Sprinkler Systems, Viking Corporation drawings and an on-site walkdown of the installed system. An evaluation of the hydraulic performance of the system will be completed when as-built drawings of the system become available.
If you have any questions or comments concerning our review, please contact me.
l Sincerely, es *-
ames B. Biggins Fire Protection Associate Enclosure JBB/1w Enclosure cci J. Deress J. Bruciak G. Jones H. Pietraszewski C. Tomashek B. Treece T. Gray W. Vahle R. Salsbury J. Gudac R. Williams R. Rakowski T. Heyer S. Chingo E. Crass D. Shamblin R. Smith, Jr.
H. Smith H. Rybak H. Balster (JB2/36) 222 South Rivenide Ptara, Chicago, Illinois 60606, Telephone 312 6484000
M&M Protection Comultants Fire Frotection Area 1-E furbine Building Elevation 426' (Unit 1)
NFPA 13-1935 standard for the Installation of sprinkler Systems Ites Reforonce Deficiency Resolutton 1.
NTPA 13-1945 Working plans shall be submitted for pera. 1-9.1 approval before any equipment is in-stalled or remodeled. Deviation from approved plans requires permission.
The cross main piping located along the correct Wiking drawings 69 &
column 12 line is not installed as shown 70 to reflect actual instal-on drawings.
lation.
2.
NFPA 13-1985 Branch lines 76 and 77 are is installed Present installation is para. 1-9.1 in an arrangement other than that which acceptable. Correct Viking is shown on drawing 69.
drawing 69 to reflect in-stallation.
3.
NFPA 13-1989 Sprinkler 1 on branch line 65 is not in-Install sprinkler as shown para. 1*9.1 stalled.
on Viking drawing 69.
4.
NFPA 13-1985 The branch lines located 2'7%" south of Install branch lines with para. 1 9.1 column 14 between columns C and J (numbers vertical side well sprin-
$1 and 61) shown on Viking drawing 69 and klers along column 14. This 70 are not installed. Installation would will provide protection to be directly under an open hatchway.
both the hatchway and the feedwater pumps located be-low the hatchways.
MFPA 13 1945 Underground mains and lead in connections MIN C has reviewed flushing para. 1 11.1.1 to systen risers shall be flushed before procedure FF-21 and is connection to system piping.
awaiting revised procedure.
4.
NFPA 13-1985 All new systems including yard piping shall Verify that the required para. 1-11.2.1 be hydrostatically tested at $0 pei in en*
hydrostatic testing has been cess of the maximum system pressure for two performed, hours. The test pressure shall be read from a sage located at the low elevation point of the individual system being tested.
7.
NFPA 131985 Valves on connections to water supplies shall Station is to lock valve open para. 3-14.2.3 be supervised open. System control valve prior to fuel receipt. In-th 51A is not supervised, stall temper switch to comply with station fire protection report.
N
M&M Protection Consultants Item Re ference Deficiency Resolution 8.
NFPA 13-1985 Bass or coverings placed over sprinklers para. 3-16.9.1 to protect them from painting or other processes,'should be removed once the painting has been finished, j
Sprinkler 2 on the branch line located 5%
Remove covering so that feet south of column 14 is covered.
sprinkler may actuate with undue delay.
9.
NFPA 13-1985 Waterflow detecting devices, including the Verify that the required para. 3-17.6.3 associated alarm circuits, shall be tested testing has been performed.
by an actual waterflow through use of a test connection.
10.
NFPA 13-1985 2he basic requirements for spacing, location When buildings or portions of para. 4-1.1 and position of sprinklers are specified in buildings are of combustible this chapter and are based on the following construction or contain com-principles:
bustible material, standard (a) Sprinklers installed throughout the premises, fire barriers should be pro-(b) Sprinklers located so as not to exceed vided to separate the areas maximum protection area per sprinkler, which are sprinkler protec-(c) Sprinklers positioned and located so as to ted from adjoining unsprin-optimize performance with respect to acti-klered areas. All openings vation time and distribution.
should be protected in accor-(d) And er specified herein.
dance with applicable stan-dards.
Additional protection is needed over the oil Provide one additional sprin-hazards associated with the feedwater pumps.
klar over oil conditioning units and desister units for feedwater pumps ifw01PB and 1FWO1PC.
11.
NFPA 13-1985 Additional protection is needed over Provide one additional para. 4-1.1 the Seal Oil Vapor Exchanger Unit due sprinkler over the unit.
to the combustible oil contained with-in the unit.
12.
NFPA 13 1985 The sprinklers in the area surrounding The system should extend at para. 4-1.1 the Hydrogen Seal 011 Unit should be least 20 feet beyond the extended to provide a greater degree of Hydrogen Seal 011 Unit.
protection.
13.
NFPA 13-1985 A cement " blockhouse" has been built as Provide sprinklers above para. 4-1.1 an office and is a permanent structure.
this structure.
The area above this structure is un-sprinklered. (Approximate location F-2 to J-2)
Page 2 of 5
M&M Protcction Consultants s
l Item Re ference Deficiency Resolution 14 NFPA 13-1985 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a minimum.
Sprinklers 2 and 5 on the branch line located No action required. Inter-16'5 " south of column 3 are partially ob-forence to sprinkler dis-structed by piping. (Approximate location charge is minimal and F-3) acceptable.
15.
NFPA 13-1985 Sprinkler 2 on branch line 86 is obstructed Replace with a pendant style para. 4-2.3 by a hanger support element.
sprinkler to eliminate in-terference.
16.
NFPA 13-1985 Sprinklers 3 and 4 on branch line 86 are Raise sprinklers to a posi-para. 4-2.3 obstructed by piping.
tion where deflectors are installed one inch below the ceiling.
17.
NFPA 13-1985 Sprinkler 3 on branch line 85 is partially No action required, inter-para. 4-2.3 obstructed by a hanger support element.
forence to sprinkler dis-charge is minimal and acceptable.
18.
NFPA 13-1985 Sprinkler 1 on branch line 84 is partially No action required, inter-pera. 4-2.3 obstructed by piping.
forence to sprinkler dit,-
charge is minimal and accep-table.
19.
NFPA 13-1985 Sprinkler 2 on the branch line located 5'3" Raise sprinkler 4 inches so para. 4-2.3 north of column 4 is obstructed by a hanger that interference to sprin-support element. (Approximate location C-4) kler discharge pattern is minimized.
20.
NFPA 13-1985 Sprinkler 1 on branch line 38 is partially No action required. Inter-para. 4-2.3 obstructed by a cable tray.
forence to sprinkler dis-charge is minimal and spray pattern is adequate.
21.
NFPA 13-1985 Sprinkler 1 on branch line 47 is No action required. Inter-para. 4-2.3 partially obstructed by a pipe.
farence to sprinkler dis-charge is minimal and ac-ceptable.
22.
NFPA 13 1985 Sprinkler 3 on the branch line lo-No action required. Inter-para. 4-2.3 cated 5'3 " north of column 18 is ference to sprinkler disa partially obstructed by a cable charge is minimal and ac-tray.
ceptable.
23.
NFPA 13-1985 The branch lines located 5'34" north No action required. Intera para. 4-2.3 of column 16, between columns E and H ference to sprinkler dis-are partially obstructed by cable tray.
charge is minimal and ac-captable.
Page 3 of 5
M&M Protection Consultants Item Reference Deficiency Resolution 24.
NFPA 13-1985 The sprinklers on branch lines 54 and No action required. Inter-para. 4-2.3 55 are partially obstructed by cable forence to sprinkler dis-trays.
charge is minimal and spray pattern is adequate.
25.
NFPA 13-1985 Sprinkler 1 on branch line 56 is par-No action required. Inter-para. 4-2.3 tially obstructed by a cable tray.
ference to sprinkler dis-charge is minimal and accept-able.
26.
NFPA 13-1985 Sprinkler 2 on the branch line located Lower sprinkler to a position para. 4-2.3 5'6" north of column 16 is obstructed where the top of the deflec-by a hanger support element. (Approx-tor is even with the bottom inste location K-16) line of the support element.
27.
NFPA 13-1985 Sprinkler 3 on branch line 64 is ob-Install a pendent style sprin-para. 4-2.3 structed by a hanger support element.
kler to eliminate inter-farence to sprinkler dis-charge pattern.
28.
NFPA 13-1985 Several sprinklers on the branch lines No action required. These para. 4-2.3 located between columns 5 and 12 and obstructions are considered columns J and K are partially obstructed minimal and discharge pat-by piping, cable trays and/or other tern is adequate to provide equipment.
protection for this area.
29 NFPA 13-1985 Sprinkler 2 on the branch line located Move sprinkler approximately para. 4-2.3 4 ' south of column 6 is obstructed by 1 foot north to minimize a pipe hanger support element. (Ap-interference to sprinkler proximate location K-6) discharge.
30 NFPA 13-1985 Sprinkler 2 on the branch line located No action required. Inter-para. 4-2.3 15'10" north of column 4 is partially ference to sprinkler dis-obstructed by a pipe. (Approximate charge is minimal and accep-location K-4) table.
31 NFPA 13-1985 Sprinklers on the branch lines between No action required. Inter-para. 4-2.3 columns 3 and 4 located appreaimately ference to sprinkler dis-l 3 feet west of column F are partially charge is minimal and ac-obstructed by cable trays.
ceptable.
32.
NFPA 13-1985 Sprinklers on the branch lines installed Install additional sprin-para. 4-2.3 between columns 4 and 12 and columns E klers to provide protection and F are obstructed by the side-by-side to area below cable trays.
cable trays east of column E.
Page 4 of 5
... ~
M&M Protection Consultants e
Item Referen:e Deficiency Resolution 33.
NFPA 13-1985 The sprinklers installed between columns No action required. These para. 4-2.3 8 and 10 and columns E and G are partially obstructions are considered obstructed by piping.
einimal and the discharge pattern is adequate to provide protection for this area.
34 NFPA 13-1985 Sprinkler 3 on branch line 32 is obstructed Lower sprinkler to a position para. 4-2.3 by a hanger support element.
where the top of the deflec-tor is even with the bottom line of the support element.
35.
NFPA 13-1985 Sprinkler 3 on the branch lines located from No action required. Inter-para. 4-2.3 4'1 a north of column 14 to 15'10h" north of ference to sprinkler dis-coltaan 18 between columns E and F are par-charge is minimal and accep-tially obstructed by a cable tray.
36.
NFPA 13-1985 Deflectors of sprinklers in bays shall be at para. 4-2.4.6 a sufficient distance from the beams to avoid obstruction to the sprinkler discharge pattern.
(In order to achieve'the desired, unobstructed discharge patterns it may be necessary to re-locate some sprinklers so that they are a dis-tance greater than 18 inches from the ceiling.
This is in conflict with paragraph 4-3.4.1 of the standard but is considered acceptable due to the size of some of the beams encountered in the plant. These beams form panels that will trap sufficient heat so that sprinkler operations will not be impaired by the increased spacing).
Sprinkler 1 on the branch line located 5 ' south Lower sprinkler so that the of column 14 is obstructed by a beam 1 foot top of the deflector is even away laterally. (Approximate location E-14) with the bottom line of the beam.
37.
NFPA 13-1985 Deflectors of sprinklers shall be Reinstall sprinkler so that para. A-2.4.7 parallel to ceilings. Sprinkler 3 the deflector is parallel on the branch line located 5'3 "
to the ceiling.
north of column 18 is installed at approximately a 45' angle.
(JB2/32)
Page 5 of 5
.~.
M&M Protection Consultants A Resource of Marsh & McLennan February 19, 1986 Mr. D. Elias Project Engineer Camonwealth Edison Capany P.O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Autmatic Fire Protection Systs Protection Area 1-11
Dear Mr. Elias:
We have cmpleted our review of the fire protection systs installed in the Unit One, Contaiment Pipe Penetration Area (Area 5), Protection Area 1-11.
This is an autmatic set pipe sprinkler syste designed using the extra hazard pioe sdbedule for pipe sizin6 and spacing. 'Nenty Viking 212*F rated sprinkler heads are utilized in this syst e.
'Ihis review is based on NFPA 13, " Standard for the Installation of Sprinkler Systces", Viking Fire Pro!cetion Capany drawings and an on-site wall,iown of the installed syste performed on J 24, 1986.
An evalcation of the hydraulic performance of the systm 11 be cm-pleted when as-built drawings of the syst s become available.
If you have any questions or cements concerning our review, please contact me.
I Sincerely, Wgi: ::=
James B. Liggins Fire Protection Associate JBB/lw cc:
J. Deress J. Brucisk G. Jones M. Pietrazewski C. Tuna. chek B. Treuce T. Gray G. Kirchner R. Sal @ury E. Fitzpatrick S. thiago R. 'takowski T. Meyer R. hith, Jr.
E. Jrtas D. Shamblin M. Balstel M. Smith R. Rybak R. Kyrouac H. Kaush21 l
(JB2/40) 1 222 South Rive skfe plaza e Cnecagw Ilknois 60606
- 312448A00
M&M Protection Consultants Fire Protection Area 1-LL linit One Containment Pipe Penetration Area Area 5 - Auxiliary Building, Elevation 364' NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Reference De ficiency
_ Resolution 1
NFPA 13-1985 Working plans shall be submitted for para. 1-9.1 approval before any equipment is installed or remodeled. Deviation from approved plans requires permission.
Pipe rcnting and arrangement is different Installed piping arrangement than what is shown on Viking design is acceptable. Correct Viking drawing 94.
design drawing 94 to reflect actual installation.
2 NFPA 13-1985 Viking drawing 94 shows the system control Correct Viking drawing 94 para. 1.11.2.1 valve as an 0.S.En Y gate valve. Installed to reflect change in valve.
valve is an IIT - Crinnel valve.
3 N7PA 13-1985 All new systers including yard piping shall Verify that the required para. 1-11.2.1 be hydrostatically tested at 50 psi in ex-hydrostatic testing has cess of the maximum system pressure for two been performed.
hours. The test pressure shall be read from a gauge located at the low elevation point of the individual systes or portion of the system being tested.
4 NFPA 13-1985 Each system shall be provided with a listed The IIT-Crinnel ball valve para. 3-14.2.1 indicating valve. The ITT-Crinnel ball valve is manufactured to ASML is not a listed valve.
SA 105 and A-216 standards and is ANSI Class 300.
This is considered adequate for this installation.
5 NFPA 13-1985 On branch lines, there shall not be less than Install hanger assemblies para. 3-15.5.1 one hanger for each length of pipe. Hangers as shown on Viking design are partially inctalled for this piping. Piping drawing 94 is partially supported by wire.
6 NFPA 13-1985 Bafs or coverings placed over sprinklers to Remove covering so that the pare. 3-16.9.1 protect ther from painting shall be removed sprinkler may actuate with-once the painting has been finished. The out undue delay.
sprinkler located at approximately columns V.9 and 13 is covered by paper and tape.
Page 1 of 1
' '.. <k M&M Protection Consultants Fire Protection Area 1-LL i
Unit One Containment Pipe Penetration Area Area 5 - Auxiliary Building, Ilevation 364' NFPA 13-1985 Standard for the Installation of Sprinkler Systema i
Item Reference Deficiency Resolution 7
NFPA 13-1985 local waterflow slama shall be pro-Install waterflow indica-para. 3-17.2 vided on all sprinkler systems having tor as shown on Viking more than 20 sprinklers, design drawing 94.
3 NFPA 13-1985 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a minimum.
The sprinkler located approximately 6k' No action required. Ob-east of Column X and 34' north of Column struction is minimal and 13 is partially obstructed by a cable sprinkler discharge is
- tray, adequate to protect area.
h sprinkler located approximately 2-3/4' I
east of Column V and 7' north of Column 15 is partially obstructed by a pipe.
h sprinkler located l' west of Column X.9 and 7' north of Column 15 is partially i
obstructed by piping.
9.
NFPA 13-1985 Deflectors of sprinklers in bays shall be at No action required. Ob-f l
para. 4-2.4.6 a sufficient distance from the beams to struction is minimal and j
avoid obstruction to the sprinkler discharge sprinkler discharge is pattern.
adequate to protect area.
i h sprinkler located approximately 10 3/4' i
north of column 15 and 14%' east of column l
I I is partially obstructed by a beam.
10.
NFPA 13-1985 Deflectors of sprinklers shall be parallel to Rainstall sprinkler so the para. 4-2.4.7 ceilings. h sprinkler located approximately deflector is parallel to S' east of Column V and 9 3/4' north of Column the ceiling.
15 is installed on an angle to the ceiling.
1 11.
NFPA 13 1985 h branch line located approximately 4 feet Reinstall branch line so para. 4-2.4.7 west of column Y is installed on an angle to that sprinkler defelectors the ceiling.
are parallel to the ceiling.
(JB2/41)
Page 2 of 2
)
I
s M&M Protection Consultants A Resource of Marsh & McLennan November 27, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEM PROTECTION AREA 1-K
Dear Mr. Elias:
We have completed our review of the fire protection system installed in the basement of the Turbine Building, elevation 369'-0" (Unit One),
protection area 1-K.
This is a hydraulically calculated wet pipe sprinkler system designed to provide a sprinkler discharge density of 0.25 spa /sq. ft. and an area of coverage per sprinkler of 69.4 sq. ft.
This review is based on NFPA 13 - Standard for the Installation of Sprinkler Systems. Viking Fire Protection Company drawings and an on-site walkdown of the installed system performed on October 14, 1985.
An evaluation of the hydraulic performance of the system will be com-plated when as-built drawings of the system become available.
If you have any questions or comments concerning our review, please contact me.
Sincerely,
\\
~
gr "m_
James B. Biggins Fire Protection Associate i
JBB/1w cc J. Deress J. Bruciak G. Jones M. Pietraszewski C. Tomashek B. Treece T. Cray R. Salsbury E. Fitzpatrick R. Williams R. Rakowski T. Meyer S. Chingo E. Crass D. Shamblin R. Smith, Jr.
M. Smith M. Rybak M. Balster
,ffeff0 (JB1/11) 222 South Arvertde Plaza e Chicago, Illinois 60606
- 312 648 6000
w M&M Protection Consultants Fire Protection Area 1-K 2brbine Building - elevation 369' - 0" (Unit One)
NFPA 13-1935 Standard for the Installation of Sprinkler Systems Ites Reference Deficiency Resolution 1
NFPA 13-1985 Working plans shall be submitted for para. 1-9.1 approval before any equipment is installed or remodeled. Deviation from approved plans requires permission.
f l
Piping and four sprinkler heads have been Correct Viking design drawing l
dropped from the crossoain at the ceiling 11 to reflect this instal-to provide protection around the 3,000 lation.
q gallon lube oil storage tank at K-11.
i 2
NFPA 13-1945 The branch lines of sidewall sprinklers Correct drawings to show pare. 1-9.1 installed approximately 16' south of branch lines only once.
j of column 10 is shown on Viking design drawings 11 and 12 and again on drawing 14.
3 NFPA 13-1985 Sprinkler 2 on branch line 44 and sprinkler Use of pendent style sprinkler para. 1 9.1 3 on branch line 46 are pendent sprinklers.
is necessary due to ceiling Drawing shows upright sprinklers. (Approximate configuration. Correct Viking location H-10) desving 14 to reflect actual installation.
4.
NFPA 13 1985 The pipe routing for branch lines 84 and 85 Correct Viking drawing 12 to re-para. 1-9.1 is different than that shown on Viking drawing flect actual pipe routing.
- 12. (Approminate location F 12) l S.
NFPA 13 1985 The pipe routing to sprinkler 1 on branch line Correct Viking drawing 12 to re-i para. 1 9.1 89 is different than that shown on Viking flect actual pipe routing.
i drawing 12. (Approximate location 3-14) 6.
NFPA 13 1985 Underground asins and lead in connections M6MPC has reviewed flushing para. 1-11.1.1 to system risers shall be flushed before procedure FP 21 and is awaiting j
connection to sprinkler piping.
results of flushing.
l j
7.
NFPA 13 1985 All new systems including yard piping shall be Verify required hydrostatic j
para. 1 11.2.1 hydrostatically tested at 50 poi in excess of testing has been performed.
i the manimum system pressure for two hours.
The test pressure shall be read from a gauge 4
]
located at the low elevation point of the in-1 dividual systes or portion of the system being j
tested.
1 l
1 of 4 i
M&M Protection Consultants Item Re ference Deficiency Resolution 8
NFPA 13-1985 Bags or coverings placed over sprinklers para. 3-16.9.1 to protect them from painting or other processes, should be removed once the painting has been finished.
Masking tape is covering the sprinkler Remove tape so that sprinklers head located approximately 7k' west of may actuate without undue delay, column J and 13' south of column 10.
9 hTPA 13-1985 Waterflow detecting devices, including the Verify the testing has been para. 3-17.6.3 associated alarm circuits, shall be tested performed.
by an actual waterflow through use of a test connection.
10 NFPA 13-1955 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a minimum.
Sprinkler 2 on branch line 44 and the sprin-No action required. Adequate ares klers on branch line 45 are partially ob-protection provided at the floor structed by a large pipe. (Approximate lo-by surrounding sprinklers, cation K-18) hose stations and portable fire extinguishers.
Sprinkler 2 on branch line 34 is partially ob-structed by a drain pipe. (Approximate lo-cation K-12)
Sprinkler 1 on branch line 25 is partially ob-structed by piping. (Approximate location L-11)
Sprinkler 1 on the branch line located 12 '
south of column 10 and Sk' west of column L is partially obstructed by a hanger support element.
Sprinkler 2 on the branch line located 11 2/3' south of column 12 is partially obstructed by piping. (Approximate location H-12)
The sprinklers located between columns 5 and 12 and columns J and L are obstructed by piping, cable trays, hangers and various other equipment installed below the sprinklers.
2 of 4
M&M Protection Consultants Item Reference Deficiency Restlution Sprinklers 1 and 2 on branch line 5 are partially obstructed by con-duit. (Approximate location J-4)
The sprinklers on branch lines 30 and 31 are partially obstructed by a cable tray. (Approximate location H-6)
Sprinkler 2 on branch line 32 is partially obstructed by a pipe.
(Approximate location J-6)
Sprinkler 3 on branch line 32 and sprinkler 2 on branch line 34 are partially obstructed by a cabic tray. (Approximate location H-7)
The sprinklers on branch lines 36 and 37 are partially obstructed by piping. (Approximate location H-7)
Sprinkler 2 on branch line 40 is pattially obstructed by piping.
(Approximate location J-8)
Sprinkler 2 on the branch line located approximately 11k' south of column 12 is partially obstructed by a pipe.
(Approximate location H-12)
The sprinklers on branch lines 77 and 78 are partially obstructed by cable trays. (Approximate location H-16)
Sprinkler 3 on branch line 86 is partially obstructed by a hanger support element. (Approximate location G-12)
Sprinkler 2 on branch lines 86 and 88 is partially obstructed by piping.
(Approximate location G-14) 3 of 4
.>3 M&M Protection Consultants Item Reference Deficiency Resolution The sprinklers on the branch line lo-cated approximately 4 3/4' north of column 18 are obstructed by piping.
(Approximate location E-18)
The sprinklers on branch line 96 are partially obstructed by piping.
(Approximate location G-18)
The sprinklers on the branch lines (48,49,77,78,90,and 91) located ap-proximately 6' north of :olumn 16 are partially obstructed by side-by-side cable trays. (Approximate location E-16 to J-16)
Sprinkler 2 on branch lines 32 and 36 and sprinkler 1 on branch line 34 are partially obstructed by a cable tray. (Approximate location J-12 to J-14)
Sprinkler 4 on branch line % is partially obstructed by a 4' wide HVAC duct. (Approximate location F-16) 11 NFPA 13-1985 Sprinkler 1 on branch lines 32 and 36 are Raise sprinklers to a po-para. 4-2.3 obstructed by a hanger support element sition above the obstruc-(Approximate location J-12) tion.
12.
NFPA 13-1985 Sprinkle-1 on branch line 46 is ob-Lower sprinkler to a po-para. 4-2.3 structea by piping. (Approximate sition below the pipe where location J-10) obstruction will be elim-insted.
13.
NFPA 13-1985 Sprinkler 1 on branch line 72 is ob-Install a pendent style para. 4-2.3 structed by a hanger support element.
sprinkler to reduce inter-(Approximate location H-12) ference to sprinkler dis-charge.
(JB1/12) 4 of 4
'T its i
A Technical Service of Marsh & McLennan l
August 30, 1985 i
Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re: Braidwood Station Fire Protection Program Review Automatic Fire Protection Systems Protection Area 1-H
Dear Mr. Elias:
In reference to my letter of August 2, 1985 regarding our review of the fire protection system installed in Protection Area 1-H the following information is being provided to clarify and resolve items number 36 and 37 of our review. This information is based upon as-built conditions at the Byron Station which we recently reviewed for applicability to conditions present at Braidwood Station.
Additional sprinklers are necessary in order to provide sufficient sprinkler coverage to the area between columns G and J and columns 11 and 15 under the two large (greater than 4 feet wide) ducts. This may be accomplished by extending the additional sprinklers required by item 36 along the length of each duct.
To summarize, additional sprinklers should be provided below the ducts between columns G and J.
These sprinklers should extend from column 11 to a position 5 feet south of column 14.
If you have any questions or if further clarification is needed, please contact me.
Sincerely, e 8 d=4 2--=:-
iv James B. Biggins Fire Protection Associate JBB/1w cc:
J. Deress D. Shamblin S. Chingo M. Pietrazewski M. Balster R. Smith, Jr.
T. Gray J. Bruciak G. Jones R. Rybak C. Tomashek B. Treece J. Gudac W. Vahle R. Salsbury T. Meyer R. Williams R. Rakowski M. Smith E. Crass (JB2/28) 222 South Riverside Plaza, Chicago, Illinois 60606, Telephone 312 6484000
t' a
M&M Protection Consultants A Technical Service of Marsh & McLennan August 2, 1985 Mr. D. Elias Project Engineer Commonwealth Edison Company P.O. Box 767 Chicago, IL 60690 RE: BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEMS PROTECTION AREA 1-H
Dear Mr. Elias:
Enclosed is our review of the fire protection system installed in the Turbine Building, elevation 401'0" - Unit 1. Area 1-H.
This is a wet pipe automatic sprinkler system utilizing 559 upright and 24 sidewall Viking 212*F rated, sprinkler heads, as designed. The system protects a floor area of 40,602 sq. ft. with a fire loading of 62,200 BTU /sq. ft.
The system has e spacing of 100 square feet per sprinkler at a density of 0.3 gpm/sq. ft. for any 3000 sq. ft. area and.0.2 gpm for any 10,000 sq. ft. area.
An evaluation of the hydraulic performance of the system will be performed at a later date. Additionally, for identification purposes.
all sprinkler piping should be painted.
If you have any questions or comments concerning our review, please call.
Sincerely, James B. Biggins Senior Fire Protection Specialist JBB/th Enclosure cc:
J. Deress M. Balster R. Smith, Jr.
M. Pietrazewski J. Bruciak G. Jones T. Gray C. Tomashek B. Treece R. Rybak W. Vahle K. Salsbury J. Gudac R. Williams R. Rakowski T. Meyer S. Chingo E. Crass Shamblin 82h* Rim 64 AGkmJMaicMTeb@emM8@0046
M&M Pratsction Consultants Ie (s. I en j Fire Protection Area 1-H Iurbine Building Elevation 401' (Unit One) i l
NFPA 13-1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Rasolution 1.
NFPA 13-1985 Working plans shall be submitted for approval Use of pendant style para. 1-9.1 before any equipment is installed or remodeled.
sprinkler is advisable for Deviation from approved plans requires per-ceiling configuration.
mission.
Qiange plans to reflect this installation.
Sprinkler 2 on the branch line located 6 feet south of coluen 16 is a pendant sprinkler but is shown as an upright style sprinkler on the plans. (Approximate location C-16) 2.
NFPA 23-1985 The number 3 sidewall sprinkler on the branch Install sprinkler as shown para. 1-9.1 line 1 foot north of column 6 is shown on elft on the plans.
plans but is not installed. (Approximate location E-6) 3.
NFPA 13-1985 The arrangement of the feed main is not as shown Correct plans to reflect para. 1-9.1 on the plans. (Approximate location between actual installation.
columns F and G and columns 16 and 18.
4.
NFPA 13-1985 Additional sprinklers were added to the branch Correct plans to reflect para. 1-9.1 lines located 3 and 7 feet north of column 12 present installation.
to provide protection to the fan room.
(Approximate location C-12) 5.
NFPA 13-1985 Underground mains and lead-in connections M6MPC has reviewed para. 1-11.1.1 to system risers shall be flushed before flushing procedure FP-21 connection to sprinkler piping.
and is swaiting revised procedure.
6.
NFPA 13-1985 All new systems including yard piping shall Verify required hydro-para. 1-11.2.1 be hydrostatically tested at 50 psi in excess static testing has been of the maximum system pressure for two hours.
performed.
The test pressure shall be read from a gauge located at the low elevation point of the individual system or portion of the system being tested.
7.
NFPA 13-1985 Sprinklers under open gratings should be Provide some type of para. 3-16.8 provided with water shields. Approximately water shield-for 15 sprinklers are installed below open grates sprinklers without water shields. (Approximate locations C-7 to 11 and J-4 to 11) 3 **
a #f e M&M Prstictinn Censultants (9
i 1
t
- Item Reference Deficiency Aesolution l
8.
NFPA 13-1985 Waterflow detecting devices, including the Verify the testing has para. 3-17.6.3 associated alarm circuits, shall be tested been performed by an actual waterflow through use of a test connection.
9.
NFPA 13-1985 The distance from the walls to the end sprink-Install one additional para. 4-2.1.5.1' 1ers on the branch lines shall not exceed one-sprinkler on each branch half of the allowable distance between sprink-line.
lors on the branch lines.
One additional sprinkler is needed at the end of the branch lines located 5'5" south and 3'4" north of column 14.
(Approximate location L-14) 10.
NFPA 13-1985 Sprinklers should be so located and spaced para. 4-2.3 so that any interference is held to a minimum.
Sprinklers located on the branch line 5'6" No action required. Mini-south of column 3 are installed above cable mal interference will occur trays. (Approximate location E-3) with present installation.
11.
NFPA 13-1985 Various sprinklers located between columns No action required. Ob-I para. 4-2.3 12 and 16 and columns C and D are installed structions caused by piping i
near piping.
are considered minimal and will not affect system per-formance.
12.
NFPA 13-1985 Cable trays are installed below sprinklers Install sprinklers below para 4-2.3 located above the aisle between columns E cable trays over aisle.
and F from columns 6 through 12.
13.
NWA 13-1985 Sprinklers on the branch line located 5 feet No action required. Ob-para. 4-3.3 south of column 18 between columns F and G are structions caused will be installed above cable trays.
minimal and protection pro-vided adequate.
I 14.
NFPA 13-1985 Sprinkler 2 on the branch line located 5 feet Replace upright sprinkler para. 4-2.3 north of column 18 is obstructed with pendant type to elin-i by a pipe % inch away laterally.
inste obstruction.
(Approximate location K-18) 15.
NFPA 13-1985 Sprinklers 1 and 2 on the branch line located No action required. Present para. 4-2.3 4'10" north of column 12 are installed above installation is adequate, cable trays. (Approximate location L-12) obstructions are minims 1.
16.
f NFPA 13h.985 Sprinkler 2 on the branch lines located 3'11" No action required. Present para. 4r2.3 and 19'6" north of column 7 are installed installation is adequate, J
above cable trays. (Approximate location K-7) obstructions are minimal.
k 43.4 4 t
-+-
eu,-v+m-m w---
e y
y-ye,---y
-w-e--i---
w-r
--r'-
s y'
~ ' '
~
M&M Protecti:n Consultants fff Ites Re ference Deficiency Rasolution 17.
NFPA 13-1985 Cable trays are installed below the sprinklers No action required. Clear-para. 4-2.3 located above the aisle between columns J and ance from sprinklers to K from columns 6 through 18.
cable trays is adequate, ob-structions are minimal.
18.
NFPA 13-1985 Cable trays are installed below the sprinklers No action required. Clear-para. 4-2.3 located above the aisle between columns F and C ance from sprinklers to columns 12 through 18.
cable trays is adequate, ob-structions are minimal.
19.
NFPA 13-1985 Sprinkler 1 on the branch line located 13' Move sprinkler head to a para. 4-2.3 10 " south of column 5 is partially ob-position 1 foot south of structed by a pipe. (Approximate location J-5) present location.
20.
NFPA 13-1985 Deflectors of sprinklers in bays shall be at para. 4-2.4.6 a sufficient distance from the beses to avoid obstruction to the sprinkler discharge pattern.
(In order to achieve the desired, unobstructed discharge patterns it any be necessary to re-4 locate some sprinklers so that they are a dis-tance greater than 18 inches from the ceiling.
This is in conflict with paragraph 4-3.4.1 of the standard but is considered acceptable due to the size of scoe of the beams encountered in the plant. These beams form panels that will trap sufficient heat so that sprinkler operations will not be impaired by the increased spacing).
Sprinkler 3 on branch line 20 is located Relocate sprinkler so that 3 inches from beam used as a hanger support.
the top of the deflector is i
(Approximate location H-1) no higher than the bottom of the besa.
21.
NFPA 13-1985 Both sprinklers on the branch line located 4'3" Relocate sprinklers so that para. 4-2.4.6 north of column 6 are installed approximately the top of the deflectors 18 inches above the bottom of a beam 4k feet are no more than 7 inches away. (Approximate location E-6) above the bottom beam.
22.
NFPA 13-1985 Two sprinklers provided near the flaah tank lo-No action required. Present para. 4-2.4.6 cated at F-7 are installed above the bottee of arrangement will provide a besa location less than 1 foot away.
adequate water distribution to area, while these sprinklers will cover tank exposure.
23.
NFPA 13-1985 Sprinkler 1 on the branch line located 6 feet No action required. Ace-para. 4-2.4.6 south of column 16 is installed 9 inches above quate coverage will be pro-the bottom line of a beam 1 foot away.
vided as installed.
(Approximate location C-16)
V
, C{/
M&M Prot 2ction Consultants U
Item Reference Deficiency Resolution 24 NFPA 13-1985 Sprinkler 1 on the branch line located 13' Raise sprinkler so that the para.4-2.4.6 7 " south of column 12 is installed between top of the deflector 6 in-pipe hanger supports. (Approximate location ches above the tops of the E-12).
hanger supports.
25.
NFPA 13-1985 Sprinkler 1 on the branch line located 6 feet No action required. Present para. 4-2.4.6 south of column 16 is installed greater than piping arrangement will pro-1 foot above the bottom line of a beam 2 feet vide adequate sprinkler away. (Approximate location E-16) coverahe.
26.
NFPA 13-1985 Sprinkler 3 on the branch line located 4' 7 "
Raise sprinkler 2 inches.
para. 4~-2.4.6 south of column 16 is installed 1 inch laterally from a pipe hanger. (Approximate location H-16) 27.
NFPA 13-1985 Sprir.kler 1 on the branch lines located 6'1" No action required, para. 4-2.4.6 and 16'3" south of column 12 are installed 6 in-Sprinklers protect a narrow ches above the bottom line of a beam located 3 beam pocket and system feet away. (Approximate location J-12) provides adequate protection as installed.
28.
NFPA 13-1985 Sprinkler 2 on the branch lines located 5' and No action required.
para. 4-2.4.6 15' north of column 10 are installed 2 feet Sprinklers protect beam above the bottom line of a beam installed 4 pocket and system provides feet away. (Approximate location K-10) adequate protection as installed.
29.
NFPA 13-1985 Sprinkler on cross main located 5' 10" north of No action required.
para. 4-2.4.6 column 5 is installed 4 inches above the botton Coverage from sprinkler line of a beam located 2 feet away.
is acceptable.
(Approximate location J-5) 30.
NFPA 13-1985 Sprinkler 1 on the branch lines located 4'3" and No action required.
para. 4-2.4.6 and 12'9" south of column 4 are installed 1 foot Sprinkler installa-above the bottom line of a beam located 2 feet tion provides adequate away. (Approximate location L-4) coverage.
31.
NFPA 13-1985 Sprinkler 1 on branch lines located 5'3" and No action required.
para. 4-2.4.6 15'9" south of column 2 are installed 6 inches Sprinklers protect beam above the bottom line of a beam located 2 feet pocket and system pro-t away. (Approximate location J-2) vides adequate protec-tion as installed.
32.
NFPA 13-1985 Deflectors of sprinklers under beams shall be Reposition sprinkler so para. 4-3.4.2 located 1 inch to 4 inches below such beams.
that the top of the pen-Sprinkler 2 on the branch 1*ne 5'3" north of dant is 1 to 4 inches column 2 is less than 1 in'.h below the beam.
below the beam.
(Approximate location F-2i 33.
NFPA 13-1985 Sprinklers shall be insta. led below ducts over Install one additional para. 4-4.13 4 feet wide. Sprinklers en the branch line sprinkler below duct.
located 5'1\\" north of colmen 2 is installed above a duct over 4 feet wide.
(Approximate location E-2)
p m
J 4
5 4.
d
.A es s
..,h emgoa % A,44..
g 4 g.
q 4
gg4,,,p+;
c y,- S o ( I
- h M&M Pr:tscti n Consultants 1
Item Reference Deficiency Resolution 34 NFPA 13-1985 Sprinkler 1 on the branch line located 4 feet Provide additional para. 4-4.13 north of colum 12 is installed above a duct sprinkler below duct.
]
over 4 feet wide.
1 (Approximate location E-12) 35.
NFPA 13-1985 Sprinklers on the branch line located 3% feet Provide two additional para. 4-4.13 south of colusn 11 are installed above a duct sprinklers for coverage greater than 4 feet wide.
below duct.
(Approximate location D-12)
- 36.
NFPA 13-1985 Sprinkler 2 on the branch line located 5'5" Provide additional para. 4-4.13 south of column 14 is installed above a duct sprinkler below duct.
greater than 4 feet wide.
(Approximate location G-14) 37.
NFPA 13-1985 The sprinklers located between col ens 11 and Provide additional para. 4-4.13 12 and columns G and J are obstructed by two sprinklers and branch large ducts.
lines below ducts to protect main turbine lube oil conditioner atd sur-rounding floor area (elevation 387 ').
38.
NFPA 13-1985 bprinkler 1 on the branch line located 10'7 "
Provide additional para. 4-4.13 north of column 6 is installed above a duct sprinkler below duct.
over 4 feet wide.
(Approximate location L-6) 39.
NFPA 13-1985 Installation of sidewall sprinklers other than Move sprinkler or para. 4-5 beneath smooth ceilings requires special con-conduit so obstruc-siderations. Beams or other obstructions in-tion is eliminated.
terfere with proper distribution and sprinklers should be spaced with regard to such obstruc-tions.
The third sidewall sprinkler on the branch line located just south of colun 7 is obstructed by a piece of conduit.
40.
NFPA 13-1985 Sidewall sprinkler deflectors shall be located Reposition sprinklers para. 4-5 no more than 6 inches from the ceiling so that to within 6 inches of heat can efficiently actuate the sprinklers.
beam or provide them with The sprinklers located at K column between heat collectors.
4 and 5 are located 1 foot below beam.
(NFPA2/7)
V
M & M Protection Consultants O
A Resource of Marsh & McLennan l
J January 3, 1986 Mr. D. Elias Project Engineer Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Re:
BRAIDWOOD STATION FIRE PROTECTION PROGRAM REVIEW AUTOMATIC FIRE PROTECTION SYSTEM PROTECTION AREA 1 - X
Dear Mr. Elias:
We have completed our review of the fire protection system installed in the Radwaste area of the Radwaste/ Service Building Complex, protection area 1-X.
This area is protected by an automatic wet pipe sprinkler system, designed to provide a sprinkler discharge density of 0.25 gpm/ square foot over the most remote 3,000 sq. ft.
area protected by the system.
This review is based on NFPA 13 - Standard for the Instal-lation of Sprinkler Systems, Viking Fire Protection Company drawings and an on-site walkdown of the installed system performed on January 6,
1986.
An evaluation of the hy-draulic performance of the system will be completed when an as-built drawing of the system becomes available.
If you have any questions or comments concerning our review, please contact us.
Sincerely,
$m & /S f
7 1' James B. Biggins Fire Protection Associate JBB/lw cc:
J. Deress J. Bruciak G. Jones M. Pietraszewski C. Tomashek B. Treece T. Gray R. Williams R. Salsbury E. Fitzpatrick S. Chingo R. Rakowski T. Meyer R. Smith, Jr.
E. Crass D. Shamblin M. Balster M. Smith M. Rybak (JB3/6) 222 South Rwerside Plaza + Chicago,Ithnois 60606 + 312-6484000 t
M&M Protection Consultants Fire Protection Area 1 - X Radweste/ Service Building Complex - Elevation 401'-0" i
NFPA 13 - 1985 Standard for the Installation of Sprinkler Systems Item Re ference Deficiency Resolution
~
1.
NFPA 13-1985 Underground mains and lead-in connections M&MPC has reviewed flush-para. 1-11.1.1 to system risers shall be flushed before ing procedure FP-21 and connection to system piping.
is awaiting corsletion of system flushing.
2.
NFPA 13-1985 All new systems including yard piping Verify that reqsired hydrostatic para. 1-11.2.1 shall be hydrostatically tested at 50 poi testing has been performed.
in excess of the maximum system pressure for two hours. The test pressure shall be read from a gauge located at the low elevation point of the individual system being tested.
3.
NFPA 13-1985 Electrically c;erated alarm attachments Complete electrical instal-para. 3-17.6.1 shall be ins;alled in accordance with lation for this device.
applicable NFPA standards. The electri-cal wiring for the waterflow detecting device for this system is not complete.
4.
NFPA 13-1985 Waterflow detecting devices, including the Verify that the required para. 3-17.6.3 associated alarm circuits, shall be tested testing has been performed.
l by an actual waterflow through use of a test connection.
5.
NFPA 13-1985 Sprinklers should be so located and spaced No action required. Inter-
]
para. 4-2.3 so that interference is held to a minimum.
forence to sprinkler dis-l charge is minimal and man-ual protection is provided at the floor by hose sta-tions and portable fire ex-tinguishers.
Sprinkler 2 on branch line 29 is partially obstructed by conduit. (Approximate lo-i cation H.4-39)
I Sprinkler 2 on branch line 21 is partially obstructed by an HVAC fan unit. (Approx-imate location K-41) l l
l.
l Page 1 of 2
~
M&M Protection Consultants Item Reference Deficiency Resolution Sprinkler 2 on branch line 17 is par-tially obstructed by an H E C fan unit (Approximate location K-43)
Sprinklers 1,2,3 and 4 on branch line 22 are partially obstructed by an HVAC duct. (Approximate location H-41).
The sprinklers on branch lines 12 and 13 are partially obstructed by an HVAC duct, cable trays and/or piping. (Approximate location H-37 through H-41).
Sprinkler 1 on branch line 11 is partially obstructed by a cable tray (Approximate lo-cation G.1-37).
6.
NFPA 13-1985 The sprinklers on brarich line 14 are obstruc-Drop branch line below para. 4-2,3 ted by an HVAC duct. (Approximate location the duct in order to H.4-39).
eliminate obstruction.
7.
NFPA 13-1985 Sprinkler 2 on branch line 27 and sprinkler 3 Replace upright style para. 4-2.3 on branch line 28 are obstructed by conduit.
sprinklers with pen-(Approximate location L-39).
dent style sprinklers to eliminate interfer-ence.
(JB3/7)
-_