Rev. OL-24 to Final Safety Analysis Report, Chapter 17, Quality Assurance
ML20209A014
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/13/2019
From:
Ameren Missouri, Union Electric Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML20209A098 List: ... further results
References
ULNRC-06547
Download: ML20209A014 (2)


Text

CALLAWAY - SP TABLE OF CONTENTS CHAPTER 17.0 QUALITY ASSURANCE Section Page 17.1 QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION........... 17.0-1 17.2 QUALITY ASSURANCE DURING THE OPERATIONS PHASE .................. 17.0-1 17.0-i

CALLAWAY - SP CHAPTER 17.0 QUALITY ASSURANCE 17.1 QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION This section is not applicable to an FSAR.

17.2 QUALITY ASSURANCE DURING THE OPERATIONS PHASE The Operational Quality Assurance Program for the Union Electric Company's Callaway Plant is described in the Operational Quality Assurance Manual (OQAM). The Quality Assurance Program description, formerly maintained in this section of the FSAR, is now maintained in the OQAM as a separate licensing document. The OQAM will be maintained in accordance with the requirements of 10 CFR 50.54.

17.0-1 Rev. OL-13 5/03