ML20207Q001

From kanterella
Jump to navigation Jump to search
Rev 2 to Sequoyah Element Rept, Questionable Concrete Repair (Grout)
ML20207Q001
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 01/12/1987
From: Nixon D
TENNESSEE VALLEY AUTHORITY
To:
Shared Package
ML20207P998 List:
References
313.06, 313.06-R02, 313.06-R2, NUDOCS 8701210044
Download: ML20207Q001 (15)


Text

i I

TVA EMPLOYEE CONCERNS REPORT NUMBER: 313.06 o

['

SPECIAL PROGRAM REPORT TYPE: Sequoyah Nuclear Plant Element REVISION NUMBER: 2 L

Jtionable Concrete Repair (Grout)

TIl E: y REASON FOR REVISION:

To incorporate TAS comments, SRP comments and SQN Corrective Revision 1 Action Plan.

To incorporate additional SRP comments.

Revision 2 PRRPARATION PREPARED BY:

D. E. Nixon 12-16-86 SIGNATURE DATE-REVIEWS

/Y,'

/ / /?/

l - E- ?? Y NATURE DATE

/S TAS'

<((W f

~ fh A

/

__ /

07 SIGNATURE DATE CONCURRENCES N

eCEG-H:s SRP:

M

/!/L/f/

SIGNATURE DATE SIGNATURF[ [

DATE APPROVED BY*

Y h

lYE*N N/A ECSP M'ANAGE'R DATE MANAGER OF NUCLEAR POWER DATE CONCURRENCE (FINAL REPORT ONLY)

  • SRP Secretary's signature denotes SRP concurrences are in files.

1241T n701210044 870113 PDR ADOCK 05000327 P

PDR

1 TENNESSEE VALLEY AUTHORITY EMPLOYEE CONCERNS TASK GROUP OPERATIONS CEG Subcate,ory: Niscellaneous Element: Questionable Concrete Repair (Grout)

Report Number:

313.06 - SQN Revision 2 IN-86-221-002 IN-86-221-003 Evaluator:

D. E. Nixon

////f7 D. E. N ron /

'Date Reviewed by:

// / $##'

/// f 7 -

OP CFg Mafaber

~ ' Date Approved by:

M 9 I y...ca,er,e..

1241T

Revision 2

1. Questionable Concrete Repairs (Grout)

Two of three concerns evaluated at Watts Bar Nuclear Plant (WBN) and included in Element Report 313.06 have been evaluated at Sequoyah Nuclear Plant (SQN). The concerns identified two specific concrete areas in the WBN Turbine Building that were not properly repaired.

In addition, the report. includes the results of a general evaluation of other civil areas including backfill installation, structural concrete placement and grouting, since there was a potential that similar problems may have existed in these areas as indicated in the WBN report. The protective coating area was not included since this area has been evaluated under Construction Employee Concerns Task Group (ECTG) Report C010300.

NOTE:

Concern IN-86-217-001 included in the same WBN Report (313.06) was not considered generic t.o SQN.

II. Specific Evaluation Methodology The employee concerns identified to Quality Te:hnology Company (QTC) for the specific concrete areas at WBN are as listed below:

(Note: The concerns are written as indicated on the K-Form.)

IN.86-221-002 Turbice Building, elevation 676', straight out of the elevator, down a set of steps, and to the right, CI stated that the concrete / grout used to install sleeves in the wall penetrations was improperly prepared and the forms were not installed correctly.

IN-86-221-003 Turbine Building, elevation 676', straight out of the elevator, c.ovn a set of steps, and to the left - a hole in the floor approximately 2 feet deep by 3 feet wide by 3 1/2-4 feet long was filled with grout, in lieu of concrete.

The following methodology was implemented during the evaluation of the above concerns:

A.

Expurgated files were reviewed to determine if additional information relative to the concerns could be obtained.

B.

Reviewed SQN FSAR and the TVA Topical Report for commitments.

C.

Interviewed a cognizant Quality Assurance (QA) engineer, the supervisor of the Mechanical Modifications Unit, and a cognizant civil engineer within the Modifications Unit to determine the following:

1.

Whether or not procedures existed in the areas of concrete repair, structural concrete placement and backfill.

Page 1 of 12

r Revision 2 2.

To what extent had there been concrete repair type work, structural concr(te' placement, and backfill placement at SQN within the Office of Nuclear Power (ONP) for both safety-related and nonsafety-related structures.

3.

Control of the following:

Correct concrete class and/or grout type for the specific a.

area being repaired.

b.

Substitution of grout for' concrete where concrete was required by the specification for a particular repair.

c.

Material preparation (mixing, etc.),

d.

Preinspection of form work, etc., before concrete / grout placement.

D.

Interviewed cognizant Quality Control (QC) personnel for information regarding control of modifications relative to civil installations.

E.

Reviewed applicable parts of Administrative Instruction (AI)-19, Part IV, R17. " Plant Modification After. Licensing."

F.

Reviewed Modifications & Additions Instruction (MLAI)-17. R5 and R6,

" Grouting of Support Baseplates or Sleeves," for compliance with' construction specifications.

G.

Reviewed Corrective Action Report SQ-CAR-86-04-022 for information.

H.

Interviewed the support craft general foreman to determine any repairs performed by ONP and craft familiarity with controlling 1

G-specifications.

I.

Performed a visual inspection of a portion of the concreto related items performed by ONP for apparent compilance with specifications.

J.

Reviewed civil portions of workplans 11952, 11910, 10821 and 11207 for compliance with G-specifications.

K.

Interviewed the Mechanical Modifications Unit supervisor to determine how concrete repairs would be controlled to meet specification requirements in nonsafety-related structures such as the Turbine Building.

III. Findings A.

Based on a review of expurgated files for the specific concerns, no additional information was provided.

B.

A review of the SQN FSAR and the Topical Report revealed the following:

Page 2 of 12 I

y a

Revision 2-

1. 'SQN FSAR, Volume _13, Section 17.2. Amendment 2, under the heading of " Quality Assurance for Station Operation," referred to Section 17.2 of TVA Topical Report TVA-TR75-1A, R8 for the description of the QA Program for operation of SQN.

2.

Paragraph 17.2.3.3 of TVA-TR75-1A, R8, in part states,

" Procedures and Instructions are developed and implemented.to assure that the design, construction, installation, inspection, and testing of modifications to the CSSC meet QA standards.at least equal to those of the original installation."

3.

SQN FSAR, Volume 4 Section 3.8, original amendment, revealed that Construction Specification G-2, " Plain and Reinforced Concrete," was the specification used for concreting operations during construction.

G-2 in turn specified that repair of concrete follow Construction Specification G-34. " Repair of Concrete."

Note:

The higher-tier criteria are specific to safety-related areas; however, G-2 applies to all permanent plant structures, i

C.

The following summarizes the results of interviews conducted with a cognizant QA engineer, the supervisor of the Mechanical Modifications Unit, and a cognizant civil engineer within the Mechanical Modifications Unit.

There are no Modifications and Additions Instructions for concrete repair, structural concrete placement, or backfill. However, an instructicn M&AT-17 has been in existence for grout installations.

Additionally, a procedure-for concrete placement and repair is in the process of being developed.

Concrete repair work within ONP has been limited to areas that had been core-drilled to install sleeves and those of cosmetic nature.

Five-star grout was used in all such repairs and performed'according to M&AI-17. The tapairs have predominately been in the Auxiliary Building with a very minimum amount having been necessary in the Turbina Building.

Those interviewed could only recall four areas where concrote had been placed and inspected by ONP personnel. These areas were curbs in the Auxiliary Building, missile protective concrete on the ERCW, and conduit encasements in unit 1 and 2 Reactor Buildings. The installations were performed under workplans 11910, 11207, 11899 and 11882 respectively. Additionally, one backfill operation had been performed during the ERCW modlfication under workplan 11207.

i-4 i

Page 3 of 12

m.

s Revision 2-

Note:

Other pours had been made since SQN had gone into' operation;-

however, construction' personnel performed and documented.the inspections while they were still onsite. Additionally, those interviewed did not recall any' concrete placements

. having been performed in the Turbine Building. However, a Turbine Building concrete repair was noted during the inspection noted in Section III.I of this report. This-repair was not at or near those identified in the concerns.

According to the interview, instructions were given in the workplans for the above~1n lieu of developing procedures. Additionally, QC hold points with reference to appropriate criteria including

- G-specifications and Construction lIs (Inspection Instructions) were referenced. Inspection documentation was a part of the workplan and inspection data sheets included as applicable.

t Based on-the interview with the aforementioned personnel within the Modifications Unit, the correct-class and/or grout type for a specific. area repaired would have been controlled according to the requirements of Construction' Specification G-34 and Field Change Requests.(FCRs) would have been written where grout was substituted for a repair area that required replacement concrete. Additionally, it was noted that the engineer did not previously require a QC hold point within the workplan for grout mixing. However, this condition had been documented on Corrective Action Report (CAR) number SQ-CAR-86-04-022.

QC hold points for verification-of form work an.d embedments have been required by the workplans for installations relative to concreting activities.

i D.1' Based on an interview with a cognizant QC shift supervisor, civil-related activities had been minimum since SQN had gone into operation. Also, up unti1 approximately 1-1/2 years ago, any

~

inspections relative to concrete were performed by construction.

i Inspections by both construction and those conducted by ONP QC j

personnel were documented-in the workplan based on hold points noted by the responsible engineer. Additionally, inspection data sheets were included in the workplan where required.

i i

It was noted that since obtaining inspectors with a background in the concrete and soils area and a civil engineer in the Modifications Unit, improvements in the civil area had been i

implemented.

(Example: NEAI-17-had been revised to include in-process tests according to Construction Specification G-51.

l These tests were not previously required by the instruction.

Note: This instruction did not meet the requirements of Paragraph 17.2.3.3 of TVA-TR75-1A, Revision 8 (Refer to IR2 Section III.B.2).

The current revision (revision 6) is I

still inconsistent with construction specifications.

i l

I Page 4 of 12 i

- - -+,

e. vm m

..-,----m..-m e, - -

--r.w

,,..-,.-y,-----3--+.--me..r.-a-.--.e,-.

.----r-r---.--r~+-.---.m-.

-~~-.-m-mme-

7

~

Revision 2.

s D. '2 JAccording to conversation with a cognizant' civil QC inspector within ONP the use of grout in repair arest inspected by.

their unit and those previously performed by construction for ONP had been within G-34 dimensional criteria that would:

permit the use of grout. Structural concreting operations 1 (noted in Paragraph C) were delayed until equipment was

-purchased to perform the required physical tests.

Additionally, during the backfill placement (as noted in Paragraph C), an inspector was borrowed from the WBN Project since SQN did not have certified inspectors. Documentation of these items was a part of the workplan.-

-E.

A review of Administrative Instruction,'AI-19, Part IV R17, revealed that N&AIs are required to ensure modifications to the. plant moet-st.

i

~ 1 east the specification to which the plant was originally built. The NEAIs are required.to be consistent with the construction,

'G-specifications. However,'N&AIs are not required for a workplan if the appropriate level'of detail is placed into the workplan detailed.

~

. instructions. Additionally, specific-G-specifications needed for any i

modification are required to appear by reference in the workplan.

L Based on the above and conversations with a supervisor within the Plant-Operations Review Staff and a cognizant QA engineer,-SQN was within program requirements by documenting inspections'in the.workplan in lieu i

of having N&AIs for concreting and backfill activities.

I' F. -A review of N&AI-17. R5 and R6, " Grouting of. Support-Baseplates or Sleeves,". revealed that portions of the procedure were not consistent e

i with Construction Specification G-51 and G-34 requirements, j

Specifically, both revisions reviewed, allowed core-drilled holes to be grouted without scarifying the surface. Additionally, the procedures l

allowed the engineer to reduce and/or waive 12-hour surface wetting requirements before grouting. Up until' revision 6 of the instruction, the physical tests required by Construction Specification G-51 were not l

implemented in the instruction. Based on an interview with cognizant.

i QC personnel, the' physical ~ testing had not been conducted, i

Note:

Filling of gaps for surface mounted plates that fall within the criteria of Construction Specification G-32 does not require i

l testing of the grout / mortar for expansion, compressive strength, and, etc. Additionally, saturation with water is t

only required just before the application of mortar. However, according to conversations with the cognizant engineer in the Modifications Unit, a cognizant QC inspector and the craft l

general foreman, grouting of baseplates had been performed according to Construction Specification G-51 in that they were formed, and the gap was normally approximately 1-inch.

In this case, the in-process tests and the 12-hour saturation requirements according to Construction Specification G-51 would have been required.

Page 5 of 12

m Revision 2 U

G.

As.noted previously,LCorrective' Action Report SQ-CAR-86-04-022=had been written.to document.that N&AT-17 had not been followed to mix grout-according'to the' manufacturer's recommendations. The CAR documented that water content had~not been previously measured in performing i

grouting. operations.

-The~ CAR remains open, pending an evaluation to determine the maximum i

allowable variation of water to grout. and obtain required strength.

- It:was noted _that corrective action is being ' tracked by ONP-QA based on the fact that.a portion of the initial response-to the CAR was rejected

~

4 l>_

by them. Initiation of the CAR resulted in a revision to NEAI-17 to I

-include documenting mix proportions-and in-process test requirements-required by G-51.

-H.

Based on an interview with the support craft general foreman, all 4

grouting of baseplates had been accomplished-by forming before i

installing-the grout.

He, additionally, stated that there had been very little repair work conducted in nonsafety-related areas. Most a

repairs had been limited to sleeves for mechanical and electrical 1

penetrations.

I'c was noted that craftsman performing concrete-related activities L

depended primarily on the engineer and instructions given in the

-workplan and did not maintain familiarity with'the G-specifications.

7 f

I.

With the. assistance of the support craft general foreman, several areas relative to concrete work that had been performed by ONP-were visually inspected for apparent conformance with requirements. Specific items l'

observed were as follows:

1.

Observed two sets of baseplates that had been grouted in the

['

Turbine Building and Auxiliary Building. The gap thickness ranted from approximately 1/2-inch to 1 1/2-inches. -According to conversation with the cognizant general foreman, the areas were

' formed and 5-star grout was used. No problems were noted based on the visual inspection; however, in-process tests according to G-51 l

would have been required.

(

2.

Observed a concrete repair around a structural steel column base in the Turbine Building. Replacement concrete was used in the repair-as required by Construction Specification G-34, therefore, the installation was acceptable.

i l

3.

Observed several repairs around mechanical sleeves and electrical i-penetrations in the Auxiliary Building that had been grouted by ONP. With the exception of one sleeve, the use of grout was acceptable based on repair dimensions.

It was later determined that the grout used'in lieu of replacement concrete for this sloove in particular was authorized by FCR 3065 as included in workplan 11309. Therefore, it was acceptable to use grout in all sloove and/or penetration repairs observed, based on apparent dimensions.

i Page 6 of 17 t

~

.e

-Revision 2 i

L J.

The' following sununarizes the results of the workplans reviewed in the civil area for compliance with G-specifications. Protective coatings-were exempt from the review'since this area has been evaluated under Construction ECTG Report C010300.

l 1.

Workplan 11952 included the installation of grouted anchors.

Hold ll points for QC verification were included and the applicable l-G-specification referenced (G-32).

Hold points-included verification of hole size, depth and visual roughness, anchor i

fabrication, installation, curing, and anchor testing..In addition L

to documenting the inspection in the workplan, inspection data sheets from N&AI-10 and 17 were included to document anchor installation and testing.

2.

Workplan 11910 included concrete placement of two curbs in the Auxiliary Building. -Necessary QC hold points for the concreting-j operation were included. These hold points for the concreting operation were dimensional tolerances, scarifying, vendor batch plant inspection, placement, curing, form removal, and concrete testing.

A discrepancy was noted in that the workplan specified that the concrete surface be wet sacked for 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> before concrete placement. This is contrary to the requirements of Construction Specification G-2, Paragraph 14.2.1.

This paragraph stipulates that Section 7.3 for cleaning lift joints and bonding new concrete to old j

shall apply to all horizontal. construction joints.

Paragraph 7.3.8 of Section 7.3 in turn stipulates that superior bonding is obtained If the surface of the lift in place is dry.

i Contrary to the requirements of AI-19, Paragraphs 4.1.2.13.b. the necessary G-specification was not referenced in the workplan.

However, this is not considered a problem since the Construction IIs L

were referenced which'in turn references the appropriate 1

j G-specification (s).

I l

The workplan additionally specified that any visible volds after l

placement of the concrete be repaired according to M&AI-17. Based on f

a review of R6 of this instruction, it does not incorporate or give reference to Construction Specification G-34 which is the controlling specification for concrete repair.

l.

[

3.

Workplan 10821 was written to install a L-shaped concrete shield wall in the Auxiliary Building.

(Note: This installation was conduc'ad while construction was still on site; therefore, the l

Inspection was conducted by them.) With the exception of the following, the workplan included sufficient instructions and i

reference to Construction IIs (Inspection Instructions) to acceptably perform the concrete installation, including the installation of form work and reinforcing steel.

i l

Page 7 of 12

((

m a

h Revision 2-

.The plan stipulated surface wetting for'12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> before a.

concrete placement. Additionally, the concrete repair made according to FCR 2013 in the workplan required this step.

(See J.2 above for criteria discrepancy.)

b.

Post-placement repair criteria gave reference to make any necessary repales according to N&AI-17 in lieu of G-34. '{See-J.2 above.)

4. -Based on a general review of workplan 11207 written to install backfill and a concrete missile shield slab, no problems were noted. Specific criteria including Construction Specification G-9, drawings and Construction IIs were referenced and/or included-in the workplan.

j K.

Based on an. additional interview with the supervisor of the Mechanical Modifications Unit, the only distinction that would be made in repairs performed in a nonsafety-related structure and a safety-related I

structure is that engineering would perform any necessary inspections in lieu of QC.

Conclusion f

With the exception of the grout preparation discrepancy which had previously been identified by CNP, the' issues presented by concern numbers IN-86-221-002 and IN-86-221-003 were not considered a problem at SQN. The discrepancy identified by ONP was documented on Corrective Action Report SQ-CAR-86-04-022 which has not been closed.

There were no indications that grout had been used in the Turbine Building or safety-related structures where replacement concrete would have been i

required unless approved by a FCR. Additionally, preinstallation inspections such as form work were performed and documented in the

[

workplan. Backfill installation had been limited to one area and based on a review of the workplan, no discrepancies were noted.

However, discrepancies were noted when similar conditions were evaluated in the areas of structural concrete placement and grouting. The discrepancies noted were as follows:

A.

As noted in Section III.F of this report, portions of M&AI-17 are not consistent with the requirements of Paragraph 3.2.1 of G-34 and Paragraph 3.1 of G-51 in that core-del 11ed holes are not required to be scarified before installation of the repair material. Additionally.

l the 12-hour surface wetting criteria is allowed to be reduced or waived which is contrary to G-34 and G-51 requirements where grout or drypack mortar is used.

I~

Page 8 of 12 i

1

if Revision 2 B.

Even though implementation.of in-process testing according to G-51, Section 8.0, was a part of the corrective action given in Corrective Action Report SQ-CAR-86-04-022, the impact as to the affect in regards

.to quality has not been addressed for those installations conducted previously where the in-process testing was not performed.

C.

Based on the workplans reviewed, there were indications that engineering personnel were not familiar with specific requirementsaof Construction Specifications G-2 and G-34.

This is based on the requirements stipulated in workplans 11910 and 10821 where wetting of the surface was required before placing the concrete.

Note: This is not considered a problem detrimental to quality since the workplans revealed that surfaces were scarified. Even though superior bonding may have not been obtained, acceptable bonding should have occurred if all surface water was removed.

4 i

Additionally, the above workplans specified that voids (if any) be repaired-i according to M&AI-17. This instruction does not incorporate or give reference to Construction Specification G-34 which is the controlling concrete repair specification.

Since A, B and C above reflect deviations from specification requirements, the conseque'nces should be evaluated by SQN. This will determine any safety significance relative to the issues. Even though specific ONP instructions did not exist for all civil areas, this was not considered a problem. This was allowed by AI-19 and Construction IIs (Inspection Instructions) were referenced in the workplans which were reviewed by the Plant Operations Review Committee (PORC).

Additionally, it was noted that actions to improve areas relative to concrete had started. This was exemplified in that a recent revision to MLAI-17 incorporated in-process testing requirements, and an instruction l

for concrete placement and repair has been initiated, i

l IV. Root Cause Areas relative to the specific concerns were not deemed a problem at l

l SQN, therefore; root cause is not applicable. However, discrepancies l

l were noted when similar conditions were evaluated in the areas of l

structural concrete placement and grouting. The failure of ONP lR2 to comply with the specifics of construction specifications appears l

to be caused by an unfamiliarity of the provisions of the QA Topical l

Report on the part of personnel involved in preparations and review l

of the workplans and M&AI-17.

l Page 9 of 12

9 Revision 2 V. Generic Applicability Generic applicability has been established in WBN Report 313.06.

(Refer to Section I)

I VI. References 1.

WBN Element Report 313.06 2.

SQN FSAR, Volume 13 Section 17.2. Amendment No. 2 3.

SQN FSAR, Volume 4, Section 3.8, Original Amendment 4.

TVA Topical Report, TVA-TR75-1A, Revision 8. Section 17.2 5.

ONP Instructions:

NAI-17, R5 and R6 NAI-10, RIO AI-19, Part IV R17 AI-12, R22 6.

IVA General Construction Specification G-34 R3 7.

TVA General Construction Specification G-2, R5 8.

TVA General Construction Specification G-51, R2 9.

TVA General Construction Specification G-32, R11 10.

Workplan numbers:

11910 11207 11899 l

11309 11952 10821 11.

Corrective Action Report SQ-CAR-86-04-022 12.

Construction ECTG Report C010300 l

13.

FCR 3065 14.

FCR 2013 l

l Page 10 of 12 l

l l

O Revision 2 VII.

Immediate and Long-Term Corrective Actions Sequoyah's Corrective Action Plan, as documented on Corrective Action Tracking Documents (CATD) is as follows:

CATD 31306-SON-01 Revisions have been made to M&AI-17 to clarify roughening requirements for core-drilled holes and to remove the section which allows a waiver of wetting criteria. These changes have been approved by DNE and will prevent future violations of G-34 and G-51 requirements.

CATD 31306-SON-02 A lack of in-process testing on past installations is not considered detrimental to the quality of those installations for the following reasons.

1.

MLAI-17 has historically required the use of Five-Star grout or equal and the "or equal" option has never been exercised.

2.

Qualification-test results from Singleton Materials Engineering lR2 Laboratory-indicate acceptability of the material over a wide range of water contents (B46 860808 001 and B46 860718 001).

A lack of indications of grout failure from reviews of maintenance history and visual inspections is sufficient evidence to conclude acceptability of past installations (S02 860808 931, S02 860825 801).

CATD 313.06-SON-03 (Surfaces were wet sacked when specifications stipulated a dry surface for superior bonding)

This requires no additional action since no problems detrimental to quality were identified. However, the addition of civil inspectors and the active involvement of the Modifications civil engineer in these types of activities give confidence that our work performance will continue to improve.

CATD 31306-SON-04 Repairs to be performed by the workplans (11910 and 10821) would be considered cosmetic in nature and would have been performed using grout. No indications of repales were found; thus, no actions are required. References to General Construction Specification No. G-34 are included in Modifications and Additions Instruction M&AI-21 (concrete placement and repair), which is currently in the revision cycle.

4 Page 11 of 12

b-i Revision 2 VII.

Inunediate and Long-Term Corrective Actions (continued)

Additionally, a memorandum has been sent to DNE (S02 861023 969) requesting clarification / revision of Construction Specifications to account for problems encountered with operating plant conditions.

Future installations of grout will be improved because of revisions to M&AI-17 and better coordination with DNE.

1 i

\\

1 i

i i

j Page 17 of 12 i

f CJ 1

TENNESSEE VALLEY AUTHORITY PAGEs

-. L3L CEFERENCE

- ECPS120J-ECPS121C

_RUN: TIME

  • 12:57 OFFICE OF NUCLEAR PDHER f

FCEQUENCY

- REQUEST EMPLOYEE CONCERN PROGRAM SYSTEM (ECPS)

RUN DATE *12/02!

l ONP - ISSS - RitM LIST OF EMPLOYEE CONCERN INFORMATION i

l CATEGORY: OP PLANT OPER. SUPPORT SUBCATEGORY: 31306 QUESTIONABLE CONCRETE REPAIR (GROUT)

KEYHORD A-S GENERIC KEYHORD B H

APPL QTC/NSRS P

CONCERN SUB R PLT BBSN INVESTIGATION S

CONCERN KEYHORD C NUMBER CAT CAT D LOC FL0B REPORT-R DESCRIPTION KEYHORD D IN 221-002 OP 3I306 N HBN YNYY NO TURBINE BUILDING, ELEV. 676', STRAIG CONST PROCESS T50200 F STEPS, AND TO THE RIGHT - CI-STATE

' NONCONFORMANCE HT DUT OF THE ELEVATOR, DOWN A SET 0 REPORT CIVIL-D THAT THE CONCRETE / GROUT USED TO IN GROUTING STALL SLEEVES IN THE HALL PENETRATIO.

NS HAS IMPROPERLY PREPARED AND THE F ORMS HERE NOT INSTALLED CORRECTLY.

HUC. P0HER DEPT. CONCERN. CI HAS NO ADDITIONAL INFORMATION.

t IN 221-005 OP 31306 N HBN YNYY NO TURBINE BLDG, EL. 676', STRAIGHT OUT CONST PROCESS OF THE ELEVATOR, DOHN A SET OF STEP SCHEDULE TS013; REPORT S, AND TO THE LEFT - A HDLE IN THE F CIVIL LODR APPROX. 2' DEEP BY 3' HIDE X 3 GROUTING 1/2-4' LONG HAS FILLED WITH GROUT, IN LIEU OF CONCRETE. NUC PHR. DEPT.

CONCERN. CI HAS NO ADDITIONAL INFO RMATION. NO FOLLOH UP REQUIRED.

2 CONCERNS FOR CATEGORY OP SUBCATEGORY 3I306 s

I I

'll


n

_.. _