CD&L

^

Carolina Power & Light Company HARRIS NUCLEAR PROJECT

[o P.O. Box 165 New Hill, NC 27562

[O' January 9, 1987 File Number:

SHF/10-13510 Letter Number: HO-870338 (0)

Document Control Desk NRC-524 United States Nuclear Regulatory Commission Washington, D.C. 20555

Dear Sirs:

Carolina Power & Light Company (CP&L) hereby commits to the following training plan in'regards to Emergency Operating Procedures (EOP's). EOP revisions recently made will be further evaluated to determine additional appropriate training. The training will be provided consistent with the above evaluation as follows:

In plant training in the form of shift drills for procedure use will commence in February 1987 in accordance with procedure OMM-1.

Classroom training will be conducted on a priority basis as part of the annual requalification program which commences in March 1987.

Simulator training as required will be conducted on a priority basis during annual simulator requalification training to commence in June 1987.

The above training will be completed and evaluated by August 1987.

If you have any questions regarding this matter, please contact me at your convenience.

Yours very truly, 0701130394 870109ApOCK 05000400 R. A. Watson PDR PDR Vice President Harris Nuclear Project MW/cge cc:

Dr. J. N. Grace (NRC)

Messrs. B. C. Buckley (NRC)

C. Maxwell (NRC - SHNPP) g L. Rubenstein (NRC) 3 MEM/HO-8703350/ PACE 1/OSI