Text
, _ -
o 123 Main Street V!htte Plains, New York 10601 914 681.6240
- D NewVorkPbwer
=ta";";.,
e 1# Authonty
"-a-t-June 25, 1986 JPN-86-29 Director of Nuclear Reactor Regulation U.S.
Nuclear Regulatory Commission Washington, DC 20555 Attention:
Mr. Daniel R.
Muller, Director BWR Project Directorate No. 2 Division of BWR Licensing
Subject:
James A.
FitzPatrick Nuclear Power Plant Docket No. 50-333 Proposed Change to the Technical Specifications Regarding Water Level Setpoint for the Main Steam Isolation Valves (MSIVs), Main Steam Line Drain Valves (MSLDVs) and Reactor Water Sample Line Isolation Valves (RWSVs) (JPTS-85-08)
Dear Sir:
The Authority is requesting an amendment to the James A.
FitzPatrick Technical Specifications to change the water level setpoint for the MSIV, MSLDV and RWSV closure f rom reactor low-low water level (Level 2) [t l26.5 inches from top of active fuel (TAF)]
to reactor low-low-low water level (Level 1) (2 18 inches from TAF).
The proposed change in the water level setpoint for the MSIVs, would reduce the possibility of spurious MSIV closure due to variation of water level, which would result in an increase in plant availability.
This change would also reduce challenges to the Safety Relief Valves (SRVs), reduce suppression pool heatup and simplify operation of the FitzPatrick plant.
Since the set of water level instruments controlling the MSIVs also control the MSLDVs and RWSVs, the setpoint for these systems are also lowered in this proposed amendment.
Enclosed for filing are three (3) signed originals and nineteen (19) copies of a document titled " Application for Amendment to Operating License", together with forty (40) copies of Attachments I and II thereto, comprising a statement of the proposed change to the Technical Specifications and the associated Safety Evaluation.
General Electric Report NEDC-30838-1 Rev.
1, June 1985, " Safety Review of Safety Relief Valve Simmer Margin Analysis and Water Level Setpoint Change for the James A. FitzPatrick Nuclear Power Plant" is included as Attachment III.
The sections on Safety Relief Valve Simmer Margin Analysis which are also included in this report are not applicable to this amendment application.
ff 8607080175 860625 g[
g f fg PDR ADOCK 05000' 3 4 $lT
7' This GE report contains information which the General Electric Company customarily maintains in confidence and withholds from public disclosure.
This information has been handled and classified as proprietary to General Electric as indicated in the attached affidavit (Attachment IV), and the Authority hereby requests that this report be withheld from public disclosure in accordance with the provisions of 10 CFR 2.790.
In accordance with the requirements of 10 CFR 50.91, a copy of this application, with attachments, is being provided to the designated New York State official.
In accordance with the requirements of 10 CFR 170.12, the Authority has enclosed a check for $150.00 for the amendment application fee.
Should you or your staff have any questions regarding this proposed change, please contact Mr.
J.
A.
Gray, Jr. of my staff.
Very truly yours, bhn C.
Brons Senior Vice President Nuclear Generation Encs.
cc:
Office of the Resident Inspector U.S.
Nuclear Regulatory Commission Post Office Box 136 Lycoming, New York 13093 Mr.
J.'D.
Dunkleberger Division of Policy Analysis and Planning New Y rk State Energy Office o
Agency Building 2, Empire State Plaza Albany, New York 12223
.