c ns -o/ 6 June 13, 1986 Docket No. 50-302 Mr. Walter S. Wilgus-Vice President, Nuclear Operations Florida Power Corporation ATTN: Manager, Nuclear Licensing
& Fuel Management P. 0. Box 14042; M.A.C. H-3 St. Petersburg, Florida 33733
Dear Mr. Wilgus:
In the Safety Evaluation Report (SER) enclosed with our letter of October 24, 1985, we stated that your respor.se to Item 1.1 of Generic Letter 83-28 for Crystal River, Unit 3 (CR-3) did not meet the guidelines for post-trip review in the following areas:
(1). The criteria for the need of independent assessment of the event following a trip.
(2).
Incorporation of these criteria into the procedure for conducting restart evaluations.
By letter dated November 25, 1985, as revised by letter dated May 21, 1986, you responded to our concerns. You stated that all unscheduled reactor trips will be reviewed by the Shift Operations Technical Advisor and the Nuclear Plant Manager or Man on Call.
Upon completion of these reviews, the Plant Review Committee will be convened to perform an independent review of the restart evaluation. These actions have been incorporated into procedures describing your post-trip review program and are acceptable.
Based on our review of these submittals and on our previous review, we conclude that the guidelines of Item 1.1 of Generic Letter 83-28 have been met and that your Post-Trip Review Program and Procedures are acceptable for CR-3.
Sincerely, thecutseemd w John F. Stolz, Director PWR Project Directorate #6 Division of PWR Licensing-B cc: See next page D_ISTRIBUTION ACRS-10 BMozafari (DocketFilf BGrimes RWeller 8Io 02 NHL PUR JPartlow DShum e6o62I0048 Doc 6 PDR L POR HSilver WRegan 0
$UR PBD-6 Rdg RIngram FMiraglia Gray File OELD EBrach Edordan H0rnstein g
gg A
k PBD PBD-6 PBD-6 P (1z BWR:B 'F0 PW HSilver;jak BMozafari
.RWeller JS DShum WR 6/g86 6/T)/86 6//^'/86 6/?f86 6/p,/86 6//
6
Mr. W. S. Wilgus Crystal River Unit No. 3 Nuclear Florida Power Corporation Generating Plant cc:
Mr. R. W. Neiser State Planning and Development Senior Vice President Clearinghouse and General Counsel Office of Planning and Budget Florida Power Corporation Executive Office of the Governor P. O. Box 14042 The Capitol Building St. Petersburg, Florida 33733 Tallahassee, Florida 32301-Mr. P. McKee Mr. F. Alex Griffin, Chairman Nuclear Plant Manager Beard of County Commissioners Florida Power Corporation Citrus County P. O. Box 219 110 North Apopka Avenue Crystal River, Florida 32629 Inverness, Florida 36250 Mr. Robert B. Borsum Babcock & Wilcox Nuclear Power Generation Division Suite 220, 7910 Woodmont Avenue Bethesda, Maryland 20814 Resident Inspector U.S. Nuclear Regulatory Commission Route #3, Box 717 Crystal River, Florida 32629 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 Mr. Allan Schubert, Manager Public Health Physicist Department of Health and Rehabilitative Services 1323 Winewood Blvd.
Tallahassee, Fl'orida 32301 Administrator Department of Environmental Regulation Power Plant Siting Section State of Florida 2600 Blair Stone Road Tallahassee, Florida 32301 Attorney General Department of Legal Affairs The Capitol 4
Tallahassee, Florida 32304
.j