@rowsasus Consumers Power AIKNIEAN5 PRSENE55 General officos: 1945 West Parnall Road, Jackson, MI 49201 * (517) 788-0550 April 6, 1987 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT -
DOCKET 50-255 - LICENSE DPR PALISADES PLANT -
RESPONSE TO NRC REQUEST FOR COST ESTIMATES TO INSTALL COMMUNICATION CIRCUlTRY AND PERMISSION TO USE SITE PROPERTY FOR CONTINGENCY TELECOMMUNICATIONS NRC letters dated September 4 and September 8, 1986 requested cost estimates from Consumers Power Company to install additional communication circuitry at the Big Roca Point Nuclear Power Plant's Emergency Operations Facility (EOF) and the Palisades Nuclear Power Plant's EOF and also the permission to use site property for contingency telecommunications. The actual request for both Palisades and Big Rock Point and Consumers Power Company's responses are as follows:
Request We are seeking Consumers Power Company's estimate for labor and material to accomplish the following tasks:
1.
Install two WE-742 Terminal Blocks; one located in the NRC area of the EOF (manor home) and the other at the telephone cable junction box located at the rear of the Transmitter Building at the EOF. The outside terminal block should be enclosed in a weatherproof box to protect it from the elements and should be marked for NRC Emergency Use Only.
2.
Install two DC Control pairs (voice quality circuits) from the EOF terminal block to the telephone cable junction box at the rear of the Transmitter Building at the EOF.
3.
Agree to reserva an area at the 50 meter level of the Met Tower for use by the NRC as a repeater site.
8704130031 870406 PDR ADOCK 05000155
\\
P PDR 1
\\
)
OC0487-0033-NLO4
()
i
Nuclear Regulatory Commission 2
Big Rock Point and Palisades Plants Cost Estimate - Communicator Circuitry April 6, 1987 I
Palisades EOF Response
'l l
The cost for installing the two DC control pairs, the weatherproof I
termination enclosure (rear of transmitter building) and the two WE-742 (or equivalent) Terminal Blocks is estimated to be $600.
I Based on a conversation with Ruth LaFreniere (NRC contact) a ten foot area (centered at the 55 foot height) can and will be reserved for temporary use by the NRC. The same stipulation (as that for the Big Rock location) applies i
to this location with respect to frequency selection.
The frequencies in use by Consumers Power Company at this site are 47.98 MHz, 173.350 MHz and 456.100 MHz Tx/451.100 MHz Rx to communicate with the Met Tower Repeater.
Request k
We are seeking Consumers Power Company's estimate for labor and material to accomplish the following tasks:
1.
Install two WE-742 Terminal Blocks; one located in the NRC area in the EOF, the other at the base of the wooden pole that serves as an antenna tower at the EOF. The pole terminations should be enclosed in a weatherproof box to protect them from the elements and be marked for emergency use by the NRC (placement to be determined by i
Consumers Power Company).
2.
Install two DC control pairs (voice quality circuits) from the EOF terminal block to the base of the wooden pole antenna terminal j
block. These lines will allow installation of the base station equipment required to establish communications frem the EOF to the 4
NRC repeater system.
3.
Agree to reserve a 10 foot area at the 55 foot level of the EOF antenna pole for use an as emergency communications equipment site.
j i
1 Big Rock Point EOF Response
)
)
The cost for installing the two DC control pairs, the weatherproof, pole j
mounted, termination enclosure and the two WE-742 (or equivalent) Terminal Blocks is estimated to be $600.
The ten (10) foot area (centered at 55 foot height) requested by the NRC can 1
and will be reserved for their temporary use with the stipulation that Consumer Power Company reserves the right to participate in their frequency l
selection process.
i l
The frequency in use by Consumers Power Company at this site is 173.350 MHz.
i
}
i OC0487-0033-NLO4 i
Nuclear Regulatory Commission 3
Big Rock Point and Palisades Plants Cost Estimate - Communicator Circuitry April 6, 1987 In addition to the responses provided for Big Rock Point and Palisades, Consumers Power Company is providing the following additional comments:
1.
Careful selection of the frequencies to be used by the NRC will allow effective communications to occur both for Consumers Power Company and the NRC. Less than careful selection can create harmful interference. Also, the larger the number of frequencies in use, the higher the potential for harmful interference. Therefore, once preliminary selection of the frequencies that the NRC would prefer to use is made, our Communication Services Department will be included in the final selection process.
2.
Finally, the estimates provided cover only the circuits and termination equipment requested. For example, no provisions have been made to supply power to any NRC transceivers nor have any preparations been made for actually securing the NRC antennas to the respective structures. Therefore, any requirements not specified in the original requests (our discussions with the NRC contact lead us to believe that there are no unspecified requirements other than the reserved space on the South Haven wood pole) are not covered by the estimates and will require commensurate additional funds in order l
to be accomplished.
Brian D Johnso Staff Licensing Engineer CC Administrator, Region III, NRC NRC Resident Inspectors - Big Rock Point & Palisades OC0487-0033-NLO4