ML20205M210
| ML20205M210 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 08/08/1997 |
| From: | Burzynski M TENNESSEE VALLEY AUTHORITY |
| To: | Lieberman J NRC OFFICE OF ENFORCEMENT (OE) |
| Shared Package | |
| ML20205M044 | List: |
| References | |
| FOIA-99-76 EA-95-220, NUDOCS 9904150179 | |
| Download: ML20205M210 (2) | |
Text
.
6 i
RA Temessee Valley Authonty.1101 Market Street. Chattanooga. Temessee 37402 2801 August 6, 1997 Mr. James Lieberman Director, Office of Enforcement U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738
Dear Mr. Lieberman:
In the Matter of
)
Docket Nos. 50-259 Tennessee Valley Authority
)
50-260 50-296 BROWNS FERRY NUCLEAR PLANT - ENFORCEMENT ACTION 95-220 This letter is pursuant to your letter to Oliver D.
Kingsley, Jr., dated April 4, 1996, in which the NRC agreed it would be appropriate for TVA to defer payment of the proposed civil per.Olty in the U.S. Departmer.t of Labor case involving Dougins Harrison pending the outcome of an appeal of that case.
On July 2, 1997, the U.S.
Court of Appeals for the Eleventh Circuit issued a decision upholding the Secretary of Labor's decision.
We understand that counsel for Stone & Webster Engineering Corporation has sent you a copy of the decision.
We also understand that Stone & Webster has decided to petition the court for rehearing with a suggestion for a rehearing en banc and will make an appropriate filing within the 45-day period permitted by the court.
As in the past, Stone & Webster will provide you with a copy of all filings and keep you informed of any results.
Also, in accordance with your letter of April 4, 1996, TVA will continue to defer payment of the proposed civil penalty until 30 days after a final judicial ruling is rendered in the Harrison case.
I
(
GUNTER99-76 PDR v
994///cd /79
=
i
's Mr. James Lieberman Page 2 August 6, 1997 If you have any questions, please telephone me at (423) 751-2508.
Sincere y, Mark J. Burzynski Manager Nuclear Licensing cc:
U.Sv Nuclear Regulatory Commission A
Document Control Desk W shington, D.C.
20555-0001 Mr. J.
F. Williams, Project Manager U.S.
Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Mr. Luis Reyes, Regional Administrator U.S.
Nuclear Regulatory Commission Regiod LI Atlaul.s Feder>L Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611