ML20205J714

From kanterella
Jump to navigation Jump to search
Insp Rept 50-289/88-16 on 880829-0902.No Violations or Deviations Noted.Major Areas Inspected:Licensee Actions on Previously Identified Insp Findings.Deficiencies Noted Re Failure to Implement & Evaluate Emergency Feedwater Upgrade
ML20205J714
Person / Time
Site: Crane Constellation icon.png
Issue date: 10/18/1988
From: Anderson C, Thomas Koshy, Roy Mathew
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20205J706 List:
References
50-289-88-16, NUDOCS 8810310465
Download: ML20205J714 (10)


See also: IR 05000289/1988016

Text

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _

._.

_

_

- _ _

.-

,

,

\\

U.S. NUCLEAR REGULATORY COMMISSION

REGICN I

Report No.

50-289/89-16

Docket No.

50-289

License No.

OPR-50

Licensee: GPU Nuclear Corporation

i

PTBox 480

Riddletown, Pennsylvania

17057

Facility Name: Three Mile Island, Unit 1

Inspection At:

Parsippay _ New Jersey and Middletovn. Pennsylvania

Ins;>ection Conducted: August 29 - September .',1983

Inspectors:

/

/O'N'

Inomas Koshy, $ Piir~hractor Engineer

date

1

(

/O /7 N

/M.hoy K. Mathew,

actor Engineer

date

Approved by:

b'

~

/v/3' II

C. J. A.

erson, Thief 7PTir,J.,:t'<mssection

date

-

Inspection Summary:

Inspection on August 29-31,1988JCorporate_ Office)

}eptember 1-271983_(TNI-3 l' *j - Inspect 1on ReportTo. FO-2iW/88a15

Areas Inspected:

This was an announced inspection to review the licensee's

action on previously identified inspection findings.

Results: No violations or deviations were identifted.

Fiwe unresolved items

were closed. Two deficiencies were noted.

The licenre has not fully

implemented and evaluated the EFV system upgrade.

The adequacy of the diesel

generator capacity was not well supported in the licensee's plant loading

calculations.

4

88103 0465 891024

PDR

ADOCK 050002G9

0

FDC

-

_

,

. - _ -

-

- - - - - _ _ - - - - _ ,

,

.

,

1

DETAILS

1.0 Persons contacted

1.1 GPU Nuclear Corporation (GPUN)

  • A. Agarwal, Instrumentation Manager-
  • J. Anger, PWR Licensing Engineer
  • G. Braulke, TMI Project

-

T. G. Broughton, OTM Director, TMI-1

  • L. Cavaliere, Equipment Qualification Engineer
  • W. M. Drendall, Instrumentation & Controls Engineer
  • R. Ezzo, Electrical Engineer
  • B. Gan, Project Engineer

C. E. Hartman, Manager, Plant Engineering

  • J. Horton, Engineer-

H. J. Hukill, Director, TMI-1

  • D. Hull, Instrumentation & Controls Engineer

C. Incorvati, TMI Audit Manager

B. Knight, TMI-1, Licensing Engineer

  • S. Y. Ku, Engineer
  • J. Mancinelli, Manage'., Equipment Qualification

D. J. McGettrick, Technical Function, EP&I

R. J. McGoey, Licensing Manager

M. A. Nelson, Manager, Nuclear Safety

  • E. Pagan, Equipment Qualification Enginect
  • H. Robinson, Electrical Power Manager
  • J. Sadauskas, Manager, Electrical Power Instruments
  • R. W. Wulf, Manager, TMI Projects

1.2

U.S. Nuclear Regulatory Commission (NRC)

R. Conte, Senior Resident Inspector

  • D. Johnson, Resident Inspector

1.3 Pennsylvania State Representative.

A. K. Bhattacharyya, Nuclear Engineer

  • Not present at the exit meeting.

_

_

_,

.

-_ . _ , _ _ . - _ , - _ . _

-_,

- _ _ _ _ - _ , -

_ _ _________ _ ___________ _ __ __-__ ____ ______

_ - ___ _

..

.-

,

3

2.0 Purpose

The purpose of this inspection was to review and verify the licensee's

corrective actions for previously identified NRC findings.

'

3.0 Followup of Previous Inspection Findings

3.1 Closed (289/86-06-07. Item 2) Qualification of BIW Silicone Rubber

!

'

Cable.

This type of cable is used in specific instrument applications inside

containmont as follows:

-BIW 3/C #16AWG, 30 mils flame retardant Silicone Rubber (SR)

insulation, 45 mils flame retardant Silicone Rubber (SR) jacket

with overall shield.

This cable is used as an instrument cable

for:

RE-TE-1033 (Weed RTO with milli-volt and milli-amp

circuit).

-BIW 4/C #14AWG, 45 mils flame retardant Silicone Rubber (SR)

insulation, 45 mils flame retardant Silicone Rubber (SR) Jacket

with overall shield. This cable is used as an instrument cable

for: WEL-LT-804, WDL-LT-805, WOL-LT-806, and WDL-LT-807.

,

(Transamerica Delaval (Gem) Level Transmi6,ters with 115 VAC and

1/2 amp circuit).

No LOCA type test was conducted for this type cable.

However, the EQ

file did contain a BIW test report #B924 which included an oven

,

'

temperature test, a water immersion test, and a radiation test.

To

address the LOCA portion of the type test, the licensee used the LOCA

test reports of the following five cable types. all silicone rubber

insulated:

Test Report #

Manufacture

Cable Tested

L

i

1) Franklin F-C2946

Continental

7/C #12 AWG, 45 mil

2) Anaconda Report

Continental

1/C #12 AWG, 45 mil

No. 79118 on LOCA

3) Rockbestos A-708-86

Rockbestos

1/C #14 AWG, 30 mil

4) Anaconda-Ericson

Anaconda

1/C #14 AWG, 45 mil

report No. 80330-2

Ericson

MSLB test

5) Anaconda-Ericson

Anaconda -

2/C #16 AWG, 30 mil

report No. 81028-2

Ericson

SLB/LOCA test

The tested temperature / pressure profiles enveloped the TMI plant

,

profile.

The similarity between the installed cable and the tested

4

cables was discussed on page 3 of the EQ supplemental sheet in TMI EQ

file No. TI-163.

The lowest IR measured during the LOCA condition

,.

.-

,

4

7

was 1 X 10

chms for a length of 20 feet cable.

Based on test data

from the above test reports and the limited application of BIW cable

at TMI, the inspector concluoed that the BIW cable at TMI is

qualificd for its specific application. This item is considered

closed.

3.2 (Closed) Unresolved Item (50-289/87-09-03) Condensate Storage Tank

(CST) Level Oscillations

~

The licensee installed new safety grade level transmitters on the

condensate storage tank (CST) suction lines to supply the necessary

input signals for level indications and low-low level alarm as

specified by Regulatory Guide (RG) 1.97 and Restart License Condition

No. 3.a.

Following the installation, the licensee noted large

oscillations in level indications in the control room when the

Auxiliary / Emergency feedwater pump is running.

An initial engineering evaluation of this problem indicated that the

fluctuations in CST suction pressure were induced by fluid flow

dynamics which caused the level signal oscillations.

The licensee

briefed the NRC staff on the problem and committed to upgrade the CST

tank level indication / alarm by the cycle 7 start-up.

The non-safety

related CST level system was placed back in operation to complete the

study on the safety grade transmitters.

The licensee performed the following evaluation of the new safety-

grade level transmitted installation. GPUN Letter 5211-87-2128 dated

June 29, 1967 and the Licensee's Safety Evaluation Report SE

412024-004 Revision No. 4 provided the results of an evaluation of

the unstable CST level indications.

Findings reported that the

low-low level alarms on the condensate storage tanks which are set at

a tank level of 5 feet are connected to pressure transmitters that

are ,nounted in the condensate storage tank drain line.

This

configuration makes the transmitters sensitive to changes in flow

causing an oscillatory input to the indication / alarm circuits.

During the starting of the emergency fksdwater pump and the initation

of flow in the CST drain line, the output of the transmitters may dip

the equivalent of a 3 to 4 foot tank level drop for a very short

duration.

The flow indication later stabilizes at a value of approxi-

mately 0.75 feet below the actual CST tank level due to the Becrinol

effect at the detector.

The licensee concluded that they could reinstate the safety grade

transmitters based on the following reasons. Operations normally

maintains the CST Level at approximately 15-17 feet and the high

level (20 feet), low level (11-5 feet) and low low level approxi-

mately at 5 feet.

If the level droos below the low level alarm set

point which is the minimum technical specification level of 11.2 feet,

the operators must take corrective actions to restore the level within

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

The error in level signal caused by this oscillation and

the steady state error is acceptable due to the followir.g reasons.

,

.

.

5

a)

The oscillation is momentary and has not caused the alarm. The

level signal to the alarm is in the conservative direction causing,

at worst, an early low-low level alarm

b)

The level error would not normally activate the low-low level

alarm set point because the tank level must be maintained above

the Technical Specification level of 11.2 feet (150,000 gallons)

c)

If the actual tank level drops below 9 feet during abnormal

plant conditions and a premature low-level alarm occurs, the

operator would have sufficient time to switch to the secondary

source.

This early transfer to the secondary condensate source

is acceptable since it does not create an undue risk to safe

plant operation. Both of these transient and steady state

errors are in the conservative direction.

They would not cause

any substantial operational problems nor any safety concerns.

The inspectors verified the installation and concurs with the

licensee's justification for utilizing the safety grade level

transmitters.

This item is closed.

3.3 (Closed) Unresolved Item (289/86-12-17) Remote Shutdown Panel EFW

Instrumentation Electrical Isolation from Control Room panels and

Seismic Qualification of EFW Digital Indications

During NRC Inspection 86-12 the licensee committed to provide

electrical isolation between the power supplies to the EFW digital

indicators on the remote shutdown panel and the control room panels.

This isolation was considered essential to prevent the loss of both

indications in the event of a puwer supply problem in either of the

locations for any reason including a seismic event.

The inspector

confirmed by a review of Gilbert Orawing 5130-B-600-509, revision

10-0 dated October 27, 1986 that the power supply isolation design

modification provides the required isolation. A review of the

licensee installation confirmed that this modification has been

installed and is operational.

During the NRC Inspection 86-12, the inspector noted that the

electrical isolation would be of significant concern if the control

room indications were not seismically qualified. A failure of the

indicator due to a seismic event could affect the entire safety grade

instrument loop.

During the 86-12 inspection the licensee reported

that the Weston Series 2470 indicators are seismically qualified.

Their qualification was left as an unresolved item pending Region I

review of the licensee qualification data package for these

i n t,trument s .

The inspectors reviewed the Wyle Laboratories seismic qualifications

test report 47430-1 Revision A dated October 3, 1984 for the Weston

'

.-

.,

.

6

Series 2470 Digital Panel Meter.

This report concludes that "It was

demonstrated that the specimen possessed sufficient integrity to

withstand, without compromise of structure of electrical functions,

the prescribed simulated seismic environment." No discrepancies were

observed.

This item is closed.

3.4 (Closed) Unresolved Item (50-289/86-13-06) Seismic Qualification of

Breaker Modification

The licensee modified the electro mechanical tripping device of

Westinghouse 08-25 and 08-50 breakers with a Westinghouse Ampetector

1A solid state trip system.

During a previous NRC Inspection, the

inspector witnessed the breaker modification.

However, the seismic

qualification of the modification was not available for review.

During this inspection, the inspectors reviewed the seismic

qualification report WCAP 10449 dated January 1984.

This is a

generic qualification report applicable to the solid state

modification of the DB series of Westinghouse breakers. Westinghouse

letter dated September 5, 1985 states that the particular mounting

configuration utilized at TMI-1 is a modified version of the <>riginal

mounting and that Westinghouse has analyzed this configuration as

presented in drawing 4378596. They concluded that it is seismically

qualified for the specified application. This modification provides

better breaker coordination and repeatability of trip

characteristics.

The licensee modified 44 breakers in safety related

applications and 77 breakers in the balance of plant applications.

This item is closed.

3.5 (Closed) Unresolved item (50-289/87-23-01) Evaluation of the

Voltage Dip at the 4160 Volt Bus

-

On November 9, 1987, the output voltage of the "1B" auxiliary

transformer (AXT) momentarily dipped.

The "1B" AXT normally supplies

one-of-two vital 4160 kv buses in addition to other non-safety

buses / loads, The voltage dropped down to 2400 volts.

However, the

duration of the voltage drop was not long enough for the time delay

relay to cause the associated emergency diesel generator to start.

Various plant equipment responded to the voltage transient, such as

alternate d.c. powered equipment starting.

The main turbine

experiencert a runback of about 6MW (megawatts). As a result, reactor

power dropped from about 99 percent to abot.t 98 percent.

The plant

was restored to full power short'y thereaf ter.

The licensee review determined th t the voltage dip was a result of

one of the six circulating water pumps (CW-P-1F) for the secondary

plant condenser experiencing an overcurrent situation.

The

circulating water pump motor is protected by instantaneous and time

.

.

,

7

overcurrent relays in each phase.

The as found settings for the

instantaneous relays correspond to primary currents of 3024A, 2840A,

and 2992A.

If the actual fault currents were lower than these

values, the fault could exist for 4 1/2 seconds or more before the

i

relays pickup.

But since the loss of voltage relays (set at 2400V)

actuated, the fault currents had to exceed 10,500 amps prior to

flashing to ground. This is the minimum additional current necessary

to cause the voltage to dip this low. Therefore, the fault flashed

'

to ground almost immediately and the ground fault (50G) relay

,

responded faster.

Typical response times at the maximum fault

'

current would be approximately 1/2 cycle for the phase overcurrent

relays and less than 1/4 cycle for the ground relay (50G).

Electrical faults of this nature are rare where a high fault between

phases lowers the grid voltage substantially for a duration and then

flashe, over to the ground.

The licensee practices on the protection

system was in accordance with Westinghouse Applied Protective

Relaying handbook and 1EEE standard 242-1986 Recommended Practice For

Protection And Coordination For Industrial And Commercial Power

Systems.

The protection system responded as designed. Any prolonged

voltage degradation on the safety bus would have lead to the starting

of the Emergency Diesel generator and isolating the non-safety

related buses which caused the fault. Even though such faults can

influence plant operation, their effect will be limited to one safety

train.

This item is closed.

3.6 [Open) Unresolved Item (50-289/87-02-03) The Emergency Diesel

Generator Load Scheme and The,Use of "0APPER" Computer Program

In the course of respond.ng to action items in NUREG-0737, the

licensee added several loads to the emergency bus which are required

to be energized by the emergency diesel generator.

By letter dated

January 11, 1985 the licensee indicated that their review of the

emergency power bus loadings confirmed that adequate bus capacity was

available to accept the additional loads from the safety system

modification.

The inspectors reviewed Technical Data Report (TOR) 836 "Evaluation

of Loading for the Emergency Diesel Generator and Engineered

Safeguards Buses" dated March 12, 190,7.

The licensee evaluated the

loading under various modes of plant operation, including

simultaneous unlikely events such as loss of redundant power channel

concurrent with a degraded bus voltage and loss of off-site power

concurrent with loss of a redundant power channel.

In the loading calculation, the licensee relies on seasonal load

requirements such as winter emergency loads and summer emergency

loads on plant heating and cooling loads such as air conditioning,

heat tracing, etc. The inspectors questioned this approach as the

_

g-.

e

r

. .

-

.

.

.

,

8

TDR did not contain sufficient bases to support this approach.

There

was no verification data that these loads are prevented from starting

when there is no seasonal demand. The heating and cooling systems

could draw full power when abruptly called upon to operate.

The

licensee is taking actions to reduce the 1E Bus loads and has already

relocated 90 kilowatts of load to a non-safety bus.

The. licensee

stated that it is unlikely that the worst case heating and cooling

,

seasonal loads would occur.

They have concluded that their diesels

-

are operable.

Should the worst case seasonal loads occur, the diesels

could be loaded to about 3000 kw, the continuous : Jty rating of the

l

diesels.

This is below the maximum short term rating of the diesels

.

of 3300 kw.

In addition, plant procedures direct the operators to

monitor diesel loading when the diesels start to assure that the

dierels are not overloaded.

The licensee agreed to document their

estimate of the worst case loading within a month.

In addition, the

licensee committed to develop a detailed calculation with sufficient

'

bases to confirm the adequacy of the EDG loading oy June 1989.

This

item remains unresolved pending further NRC review.

3.7 (Closed) Unresolved Item (50-289/86-19-02) EFW Back-Up

I

Instrument Air Banks orotection from Seismic Missiles

,

r

During a previous inspection, the NRC staff expressed concern about

'

the scismic installation ef ducting, piping, and other components

installed above the redundant two-hour backup instrument air banks in

the "B" emergency diesel generator (EDG) room.

The licensee

respondad by indicating that the EDG air intake supply ducting was

!

upgraded to meet seismic criteria in accordance with the FSAR

commitments.

No piping is above the air bank.

The remaining cable

and conduit, although not seismically mounted, by engineering

judgement, would not fall and render the air banks inoperable.

The

i

licensee did not provide their basis for this engineering judgement.

A review was made of an engineering analysis conducted by the

i

,

1

licensee dated August 3, 1987 entitled Technical Assessment on

l

Scismicity of Deadweight Supported Domestic Water Piping in the TMI-1

'

DGB which is installed above the 2HBUIA.

This analysis is made to

evaluate whether a domestic 1/2 inch copper tubing water line

installed above the air banks represents a seismic hazard to the air

[

,

banks.

The analysis refers to NVREG.1061, Volume #2 Addendum Report

^

of the US Nuclear Regulatory Commission piping review committee,

!

'

summary and evaluation of historical strong motion sarthquake seismic

!

response and damage to above ground piping, dated April 1985.

t

Piping Seismic adequacy criteria recommendations based on performance

during earthquakes, by G. S. Hardy, P. D. Smith and Y. K. Tono,

presented at the symposium on current issues related to nuclear power

plant structure, equipment and piping, North Carolina State

University, December 12, 1986.

The analysis made by the licensee

discusses the various pipe f ailure and failure modes which were

!

reported in the two reference documents cited above and relates these

f

to the 1/2 inch copper tubing above the air banks.

4

,

5

1

--e

-~

c__

-_ ~ ~ , . ,

,_,,,_y_.--

,em.w-_.__r._,__-,m____._.,,~__,,,,..,___y

m_.m_.__..,__c_..m-

- - , _ ,


m,

, ,

  1. ---.-m

r

,o.

-

9

The analysis concludes that the domestic water line above the back-up

instrument air banks in the EDG building can withstand an SSE without

falling and damaging the back-up air supply. A review was made of

the licensees seismic evaluation analyses of the EDG air ducts and

air intake filter including its supports.

This seismic evaluation

was made by the licensee's engineering mechanics group under calcula-

tion numbers 1101 X dated May 22, 1980 and calculation number 1101 X

dated May 22, 1980 and calculation number 1101 X -322C-A27 dated

May 26, 1981. As a result this analysis additional supports and

bracing were added to the ducting and the air filter.

The licensee

evaluation concludes that with the additional support in place in

accordance with the details provided by the analyses, the EDG ducting

and air filter do not constitute a missile hazard to the air bands

during SSE. The inspector confirmed the additional support and

bracing t,y a visual inspection.

This item is closed.

4.0 Emergency Feedwater System Upgrades

Durtnc this intpection, the NRC inspectors reviewed certain areas of the

licensee's modification to upgrade the emergency feedwater system to a

safety grade system.

The EFW is designed to initiate on any of the

following signals.

1.

Low level in either OTSG

2.

High Containment pressure

3.

Main Feedwater Loss

4.

Loss of reactor coolant pumps

The inspectors verified the installation of instruments, cable

routing, trays, conduits for high containment pressure signal, a new

signal and main feedwater loss signal, a previously existing signal

to determine the adequacy of the cable routing and installation.

The high containment pressure signal instruments PT1186, 1187, 1188

and 1189 and its respective conduits, trays, cables up to heat sink

protection cabinets were verified and found to be color coded and

installed per GPUs 500 772-A electrical cable and raceway routing

criteria.

However, the existing main feed water loss signal

instruments OPS 829, 542, 543 and 830 sensing lines, trays, conduits

and cables were not upgraded.

TTe licensee considers this to be a

non safety related signal. At nstruments DPS 829 and 542 the

inspectors observed that one if the two mounting U bolts of the

instrument had missing nuts the tubing supports were missing, and

some loose tubing was tied with loose wire to a conduit.

The

-.

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

__ _ _

-

-

.

,

,

10

inspectors reviewed the surveillance record in Procedure 1302-06.17

dated June 19, 1988.

This record indicated a random drift of a

1

setpoint in the instruments.

The present condition of the instrument

'

mounting and the cable routing for the loss of main feed flow signal

i

for the emergency feedwater actuation system could lead to undue

challenges to the safety system.

The inspectors relayed these

concerns to the licensee management.

The licensee committed to

'

implement corrective action by October 30, 1988.

This is an

,

unresolved item pending NRC review of the licensee action to improve

l

the reliability of the loss of main feed flow signal

(50-289/88-16-01).

5.0 Unresolved Items

Unresolved items are matters for which more information is required in

order to ascertain whether they are acceptable, violations, or deviations.

One unresolved item is discussed in Section 4.0 of this report.

6.0 Exit Interview

At the conclusion of the inspection on September 2, 1988, the inspectors

met with the licensee representatives denoted in Section 1.0.

The

inspectors summarized the scope and findings of the inspection at that

time.

No written material was provided to the licensee by the inspectors.

j

I

t

I

i

,