ML20205G385
| ML20205G385 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 10/24/1988 |
| From: | Warnick R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Counsil W TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| Shared Package | |
| ML20205G390 | List: |
| References | |
| NUDOCS 8810280254 | |
| Download: ML20205G385 (4) | |
See also: IR 05000445/1988062
Text
,
-,
.'
,
-
.
,
OCT 2 4 l988
In Reply Refer To:
Docket:
50-445/88-62
50-446/88-58
TU Electric
ATTN:
Mr. W. G. Counsil
Executive Vice President
400 North Olive Street, Lock Box 81
Dallas, Texas
75201
Gentlemen:
This refers to the inspection conducted by Messrs. S.
P. Burris and
S. D.
Bitter during the period September 9 through October 4,
1988,
of activities authorized by NRC Construction Fermits CPPR-126 and
CPPR-127 for the Comanche Peak Steam Electric Station, Units 1
and 2, and to the discussion of our findings with you tr.' other
members of your staff at the conclusion of the inspect. n.
The enclosed copy of our inspection report identifies areas
examined during the inspection.
Within these areas, the inspection
consisted of selective examination of procedures and representative
records, interviews with personnel, and observation by the
inspectors.
Within the scope of the inspection, no violations or deviations
were identified.
In accordance with 10 CFR 2.790 of the Commission's regulations, a
copy of this letter and the enclosed inspection report will be
placed in the NRC Public Document Room.
Should you have any questions concerning this inspection, we will
be pleased to discuss them with you.
Sincerely,
ORIGn!AL SIGNED BY R. P. WARNICK
R. F. Warnick, Assistant Director
for Inspection Programs
l
Comanche Peak Project Division
1
Office of Special Projects
Enclosure:
Inspection Report 50-445/88-62; 50-446/88-58
cc: w/ enclosure
See next page
RI:IP:CPPD:OSPs
'RI:IP:CPPD OSP
P:CPPD:OSP
AD I : PPD:OSP
SBitter
SBurris
h'Wiebe
RWarnick
f
10/J.1/88
10/AT/88
- 10///88
10 /2y/88
.
8810280254 891024
,
ADOCK 05000445
1 {
l
Q
_
i
,
_ -
._ _
. . . .
-
-
. _ .
- _
-
.
,
'
-
.
,
j[
,\\,
UNITED $TATES
NUCLEAR REGULATORY COMMISSION
%
WASHING 704. D. C. 2M55
s
,
.....
OCT 2 41988
In Reply Refer To:
!
l
Docket:
50-445/88-62
l
50-446/88-58
l
l
TU Electric
I
ATTN:
Mr. W. G. Counsil
i
Executive Vice President
j
400 North Olive Street, Lock Box 81
i
Dallas, Texas
75201
Gentlemen:
l
This refers to the inspection conducted by Messrs. S. P. Burris and
i
S. D. Bitter during the period September 9 through October 4,1988,
[
of activities authorized by NRC Construction Permits CPPR-126 and
!
CPPR-127 for the Comanche Peak Steam Electric Station, Units 1
'
and 2, and to the discussion of our findings with you and other
,
members of your staff at the conclusion of the inspection.
!
'
l
l
The enclosed copy of our inspection report identifies areas
a
examined during the inspection.
Within these areas, the inspection
!
consisted of selective examination of procedures and representative
!
records, interviews with personnel, and observation by the
l
inspectors.
i
!
Within the scope of the inspection, no violations or deviations
i
were identified.
!
!
In accordance with 10 CFR 2.790 of the commission's regulations, a
!
copy of this letter and the enclosed inspection report will be
'
placed in the NRC Public Document Room.
Should you have any questions concerning this inspection, we will
}
be pleased to discuss them with you.
Sincerely,
l
l
RFld M
l
R. F. Waraick, Assistant Director
for Inspection Programs
i
Comanche Peak Projer.t Division
l
Cfficts of Special Projects
(
i
Enclosures
l
Inspection Report 50-445/88-62; 50-446/88-53
l
l
cc: w/ enclosure
l
See next page
'
_ _ _ _ - _ _
-
(
..
.,
.
. - -
---
.
. ._
.
.
.
'
l
'
,.
TU ElGctric
j
-
cc w/ enclosure:
Roger D. Walker
Nancy H. Williams
Manager, Nuclear Licensing
CYGNA Energy Services
-
TU Electric
Suite 390
i
Sky.' .y Tower
2121 N. California Blvd
!
400 North Olive Street, L.B. 81
Walnut Creek, CA
94596
Dallas, TX
75201
Robert A. Wooldridge, Esq.
Juanita Ellis
Worsham, Forsythe, Sampels
!
President - CASE
and Wooldridge
!
i
1426 South Polk Street
2001 Bryan Tower
i
Dallas, TX
75224
Suite 2500
!
"
Dallas, TX
75201
>
?
Susan M. Theisen
!
j
Assistant Attorney General
Mr. Homer C. Schmidt
!
Environmental Protection Division
Director of Nuclear
'
!
P.O. Box 12548, capitol Station
Services
i
Austin, TX
78711-1548
TU Electric
i
Skyway Tower
!
Jack R. Newman, Esq.
400 N. Olive St., L.B. 81
!
i
Newman & Holtzinger, P.C.
Dallas, TX
75201
!
i
1615 L Street, NW, suite 1000
l
Washington, D.C.
20036
Mr. J. L. Vota
a
Westinghouse Electric
GDS Associates, Inc.
Corporation
(
1850 Parkway Place, Suite 720
Post Office Box 355
'
{
Marietta, GA
30067-8237
Pittsburgh, PA
15230
4
i
i
Mr. R. W. Ackley
Lanny A. Sinkin
Stone & Webster Engineering
Christic Institute
i
i
corporation Project Mgr.
1324 H. Capitol Street
i
20002
!
P. O. Box 1002
-
3
i
Glen Rose, Texas
76043
David R. Pigott, Esq.
,
Orrick, Herrington & Sutcliffe
'
l
Anthony Z. Roisman, Esq.
600 Montgomery Street
l
Suite 600
San Francisco, CA
94111
1401 New York Avenue, NW
20005
Robert Jablon
i
!
Bonnie S. Blair
'
Ms. Billie Pirner Garde, Esq.
Spiegel & McDiarmid
Government Accountability Project
1350 New York Avenue, NW
i
Midwest Office
20005-4798
]
104 East Wisconsin Avenue
,
I
Appleton, WI
54911
TU Electric
'
c/o Bethesda Licensing
!
Regional Administrator, Region IV
3 Metro Center, Suite 610
i
U.S. Nuclear Regulatory Commission
Bethesda, MD
20814
611 Ryan Plaza Drive, Suite 1000
3
Arlington, Texas
76011
,
i
,
l
}
4
,
i
.
- .
.
-
_.-
-
.
- - - - - - . .
- . - -
- .
'
.
',
-3
TU ElGctric
cc w/ enclosures
(continued)
,
George A. Parker, Chairman
,
'
Public Utility Committee
Senior citizens Alliance of
Tarrant County, Inc.
l
6048 Wonder Drive
l
Fort Worth, TX
76133
Joseph F. Fulbright
Fulbright & Jaworski
l
1301 McKinney Street
l
Houston, TX
77010
William A. Burchette, Esq.
Counsel for Tex-La Electric
Cooperative of Texas
Heron, Burchette, Ruckert &
Rothwell
Suite 700
1025 Thomas Jefferson St., NW
20007
!
l
l