OCf24 1985
Georgia Power Company
AN: Mr. R. J. Kelly
Executive Vice President
P. O. Box 4545
Atlanta, GA 30302
Gentlemen:
SUBJECT: REPORT-NOS. 50-424/85-47 AND 50-425/85-34
On September 30 - October 4,1985, NRC inspected activities authorized by NRC
Construction Permit Nos. CPPR-108 and CPPR-109 for your Vogtle facility. At the
conclusion of the inspection, the findings were discussed with those members of
your staff identified in the enclosed inspection report.
Areas examined during the inspection are identified in the report. Within these
areas, the inspection consisted of selective examinations of procedures and
representative records, interviews with personnel, and observation of activities
in progress.
Within the scope of the inspection, no violations or deviations were identified.
Should you have any questions concerning this letter, please contact us.
Sincerely,
S
J
Virgil L. Brownlee, Chief
Reactor Projects Branch 2
Division of Reactor Projects
Enclosure:
Inspection Report Nos. 50-424/85-47
and 50-425/85-34
cc w/ encl:
v R. E. Conway, Senior Vice President
Nuclear Power
g.O. Foster,VicePresident
and General Manager Vogtle Project
g)i. H. Gregory, III, General
Manager, Vogtle Nuclear Construction
f. Bockhold, Jr., Vogtle
Plant Manager
,t C. T. Gucwa, Chief.
Nuclear Engineer
s
cc w/ encl cont'd:
(See page 2)
8511130002 851024
DR
ADOCK O
4
,
i .
j
-
- I
-
OCT24 1985
..
s
.
,
Georgia Power Company
2
cc w/ encl:
A ble A. Thomas,
Vice President-Licensing Vogtle
Project
led Groover, Quality
Assurance Site Manager
@y&GeneralManager
W. Hayes, QA Manager
T. Beckham, Vice President
- Operations
LJ<A. Bailey,ProjectLicensing
Manager
. G orge F. Trowbridge, Esq.
A
V
Shaw, Pittman, Potts and Trowbridge
p ce W. Churchill, Esq.
Shaw, Pittman, Potts and Trowbridge
pnest L. Blake, Jr., Esq.
Shaw, Pittman, Potts and Trowbridge
(, James E. Joiner, Troutman, Sanders,
Lockerman and Ashmore
fames G.. Ledbetter, Comissioner
.
Department of Human Resources
parles H. Badger,- Office of
Planning and Budget, Management
Review Division
pOffice of the Consumer's Utility
ppish Kirkland, III, Counsel
Council
@ ouglas C. Teper, Georgians Against
Nuclear Energy
purieFowler,Esq.,LegalEnvironmental
Assistance Foundation
g. Tim Johnson, Executive Director
Educational Campaign for a Prosperous
. Georgia
frtonB.Margulies,Esq., Chairman
Administrative Judge, Atomic Safety
and Licensing Board Panel
fr. Oscar H. Paris, Administrative Judge
Atomic Safety and Licensing Board Panel
yJudge,AtomicSafetyandLicensingBoard
tave A. Linenberger, Jr., Administrative
Panel
fillie P. Garde, Citizens Clinic
Director, Government Accountability
Project
bec w/ encl: .(See page 3)
t
-.
.
..
.
. -
.
.. .--.
.
. _ .
. -
OCT 2 41985
. . -
8
,
.
i-
Georgia Power Company
3
'
bcc w/ encl:
< Reis, ELD.
l
. Sinkule, RII
-
kC Resident Inspector
State of Georgia
Document Control Desk
.
1
.
>
e
i
J
t
i
h
L
'RII-
RIw.
RII .
-
V,
-RNewsome:dr-
ake
'AHerdt
VBrownlee
10/10 /85
V4V85
-10/y85
10/p/85
\\0
.
!
.
-
,
.
.,. . . _ . -._ .._. _
.,
. . - . . . _ . . . _ . _ . , _ . . . . .
._ _,.
_ , . _ - . . _ , , - . . . . _ . ,