Sid3M M Exuq'o, j)pg//J/[8 UNITED STATES
,{
g NUCLEAR REGULATORY COMMISSION ADVISORY COMMITTEE ON REACTOR SAFEGUARDS 3
- p g
WASHINGTON, D. C. 20555 August 22, 1985 Honorable Nunzio J. Palladino Chairman Nuclear Regulatory Comission Washington, D.C.
20555 i
Dear Dr. Palladino:
SUBJECT:
THREE HUNDRED FOURTH MEETING OF THE ADVISORY COMMITTEE ON REACTOR SAFEGUARDS, AUGUST 8-10, 1985 304th ACRS Meeting The Committee met with representatives of the NRC Staff and Georgia Power Company (the Applicant), acting on behalf of itself and as agent for the Municipal Electric Authority of Georgia, the Oglethorpe Power Corporation, and the l'ty of Dalton, Georgia to review the application for licenses to operate the Vogtle Electric Generating Plant, Units 1 and 2.
The Committee met with representatives of the Southern California Edison Company (Licensee) and the NRC Staff to review the results of Phase II of the Systematic Evaluation Program as it has been applied to the San Onofre Nuclear Generating Station, Unit 1.
The Committee met with representatives of the NRC Staff and the Seismic Qualification Utilization Group to review the status of the NRC Staff proposed resolution of USI A-46, Seismic Qualification of Equipment in Operating Plants.
The Committee discussed its role in advising the NRC on matters pertaining to the civilian high-level radioactive waste management program.
The Committee discussed the adequacy and success of the INP0 program to assist commercial nuclear power plant licensees in the implementation of improved radiation protection programs.
The Comittee discussed the status of ACRS activities on long range planning which have been in progress for the last several months to assist the Comission with its long range planning efforts.
Reports on the subjects noted above have been sent to you.
The Committee met with representatives of the NRC Staff to review the April 12, 1985 draft version of the NRC Maintenance and Surveillance Program Plan.
The Committee discussed a method being developed by IDCOR for systematic analysis of operating plants,
, 3 g a,L m.
Cortified D7 8511040027 R50022 PDR ACRS SL-0313 PDR
...- - -=
Honorable Nunzio J..Palladino.
i-
- The Consnittee's comments on the subjects noted above have been provided to.the Executive Director for Operations. A copy has been sent to you.
The -Committee met with representatives of the NRC Staff, the Brookhaven
~ National Laboratory, and the General Electric Company (GE) to continue review of the application of GE for a forward-looking Final Design Approval for the GESSAR II design.
Subcommittee Activities Since the last report of ACRS activities the following Subcommittee meetings have been held:
Scram System Reliability, in Washington, D.C. on July 17, 1985 to discuss reactor protection system and scram breaker reliability.
Vogtle Electric Generating Plant, Units 1 and 2, in Augusta, Georgia on July 18-19, 1985 to begin review of Georgia Power Company's application for an operating license for Vogtle, Units 1 and 2 Joint Waste Management and Procedures and Administration, in Washington, D.C. on July 30, 1985 to discuss the ACRS role in the Civilian High-Level Radioactive Waste Management Program Reactor Radiological Effects, in Washington, D.C. on July 31, 1985 to review INPO's Radiation Protection Program, particularly as it relates to a similar and related NRC program Emergency Core Cooling Systems, in Washington, D.C. on July 31, 1985 to continue the review of the proposed revision to Appendix K of the 10 CFR 50.46; review implementation of Appendix K analysis effort for GE BWR's; discuss RCP trip issue resolution; and discuss NRR's ECCS-related issues of ongoing concern Class '9 Accidents, in Washington, D.C.
on August 1,
1985 to continue discussion with the NRC Staff of draft NUREG-0956, " Source Term Reassessment" Class 9 Accidents, in Washington, D.C. on August 2, 1985 to discuss with the NRC Staff and IDCOR the status of programs related to extending the results of the reference plants and how this relates to the ACRS recommended search for outliers program Oualification Program for Safety-Related Equipment, in Washington, 0.C. on August 6, 1985 to discuss NRC Staff resolution of USI A-46,
" Seismic Qualification of Equipment in Operating Plants" Long Range Plan for NRC, in Washington, D.C. on August 7, 1985 to continue discussions of technical issues related to the regulation of nuclear power plant safety and safety regulation over the next 5 to 10 years as they relate to a long range plan for NRC-
' /1
Honorabic Nunzio J. Palladino,
GESSAR II, in Washington, D.C. on August 7, 1985 to continue review of GESSAR II for a Final Design Approval applicable to future plants Future Agenda The following items are tentatively scheduled for consideration during the 305th ACRS meeting, September 12-14, 1985:
t Report of Panel on ACRS Effectiveness -- Sumary/ discussion of report Briefing by NRC Staff on approach to proposed revisions to Regulatory Guide 1.82, Rev. 1, Sumps for Emergency Core Cooling and Containment Spray Systems Application of PRAs to Nuclear Power Stations -- Proposed ACRS coments on application of PRAs to Indian Point and other nuclear power plants 10 CFR 50, Appendix A General Design Criteria for Interim ACRS coments on proposed changes in Schedular Exemption criteria regarding failure of primary system piping General Electric Standard Safety Analysis Report (GESSAR II) --
Continue ACRS review of the FDA for this standardized NSSS Use of Natural Aptitude Testing of Nuclear Power Plant Operators --
Briefing / discussion regarding use of natural aptitude testing for selection of nuclear power plant operators Regulatory Guide 1.99, Rev.
2, Effects of Residual Elements on Predicted Radiation Damage to Reactor Vessel Materials -- ACRS coments River Bend Nuclear Plant -- OL open issues regarding H2 generation and control Briefing by NRC Staff of Recent Events at Operating Nuclear Power Plants Meeting with NRC Comissioners to discuss the ACRS report on ACRS participation in NRC regulation of the DOE program for high-level civilian radioactive wastes, implementation of the NRC Severe Accident Policy, and the need for human factors research Sincerely, W1 1
W,l d
i David A. War Chairman