Forwards Insp Repts 50-369/88-24 & 50-370/88-24 on 880801-0916.Violations Under Consideration for Escalated Enforcement Action.Enforcement Conference Scheduled for 881027.Unresolved Item Will Be Pursued During Future Insps
ML20204J220
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 10/11/1988
From: Ernst M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Tucker H
DUKE POWER CO.
Shared Package
ML20204J225 List:
References
NUDOCS 8810250042
Download: ML20204J220 (2)


See also: IR 05000369/1988024

Text

+ _ _ . _ -- -. _- -

  • - -

l .

.

,. 'o . ..

l l i

l ,

OCT I 1 1989

Docket Nos. 50-369, 50-370 l

License Nos. NPF-9, NPF-17

l  ?

1

l

i / Duke Power Company F

v ATTN: Mr. H. B. Tucker, Vice President i

Nuclear Production Department f

422 South Church Street ,

Charlotte, NC 28242

Gentlemen:

SUBJECT: NRC INSPECTION REPORT NOS. 50-369/88-24 AND 50-370/88-24 j

This refers to the Nuclear Regulatory Commission (NRC) special inspection  !

conducted by W. Orders, D. Nelson, and R. Croteau on August 1, 1988 -  !

September 16, 1988. The inspection included a review of activities authorized l

for your McGuire facility. At the conclusion of the inspection, the findings  !

were discussed with those members of your staff identified in the enclosed i

inspection report.  ;

Areas examined during the inspection are identified in the report. Within i

these areas, the inspection consisted of selective examinations of procedures t

and representative records, interviews with personnel, and observation of i

activities in progress. l

The inspection findings indicate that certain activities appeared to violate

NRC requirements. The violations descrined in the enclosed Inspection Report [

are under consideration for escalated enforcement action. Accordingly, no  ;

Notice of Violation is being issued at this time and no response to this letter [

is required. However, please be advised that the number and characterization  ;

of violations described in the enclosed Inspection Report may change as a  !

result of further NRC review. An Enforcement Conference to discuss these

violations has been scheduled for October 27, 1988. You will be advised by (

separate correspondence of the results of our deliberations on this matter.  ;

I

Your attention is invited to the unresolved item identified in the inspection (

report. This matter will be pursued during future inspections. l

!

In accordance with Section 2.790 of the NRC's "Rules of Practice " Part 2,  !

Title 10 Code of Federal Regulations, a copy of this letter and its enclosure i

will be placed in the NRC Public Document Roon. l

l

l

t

I

t

l

esto:50042 es1011

PDR ADOCK 05000369

( i

i

f

O FDC i

,rEcl

- . .

'

.

.

, . . . .

~

OCT 11 1968

Duke Power Company 2

Should you have any questions concerning this letter, please contact us.

Sine rel ,

T

c-

Malcolm L. Ernst

Deputy Regional Administrator

!

l Enclosure: i

NRC Inspection Report

cc w/ encl:

JT.L.McConnell,ScationManager

/ Senior Resident Inspector - Catawba

State of South Carolina

bec w/ encl:

Document Control Desk

sNRC Resident Inspector

l

I

&bob:a b d' d m. :,,pv

, ,.. c -,?, ,..r a

,,,,,,

-

"O b fup

,

l

1

I

L