ML20204C873

From kanterella
Jump to navigation Jump to search
Ack Receipt of Re Need for Feedwater Pump Trip on Reactor High Water Level.Finds Proposed Sched for Installation Acceptable
ML20204C873
Person / Time
Site: Pilgrim
Issue date: 11/28/1978
From: Ippolito T
Office of Nuclear Reactor Regulation
To: Andognini G
BOSTON EDISON CO.
References
NUDOCS 7812050272
Download: ML20204C873 (2)


Text

. _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ _

j f r mog b UfdlVED STATES b

y* 7t NUCLEAR REGULATORY COMMISSION g - - ), j WASHINGTON, D. C. 20555 o.s

% N#[/

i

  • ..+, NOVEMBER 2 8 1978 l

Docket No. 50-293 Mr. G. Carl Andognini M/C NUCLEAR Boston Edison Company ,

800 Boylston Street Boston, Massachusetts 02199

Dear Mr. Andognini:

We have reviewed your response dated February 27, 1978, to our letter dated February 1,1978, regarding the need for a feedwater pump trip on reactor high water level. Based upon our review of your submittal we have determined that your proposed schedule for installing a feedwater pump trip by the next scheduled refueling outage is acceptable.

Sincerely, 1

l 106

Thomas Ippolito, Chief Operating Reactors Branch #3 Division of Operating Reectors cc: see next page l

78.1205og g l'

Boston Edison Company CC Mr. Paul J. McGuire Pilgrim Station Acting Manager Boston Edison Company RFD #1, Rocky Hill Road Plymouth, Massachusetts 02360 Anthony Z. Roisman Natural Resources Defense Council 917 15th Street, N. W. ~

Washington, D. C. 20005 Henry Hernnann, Esquire Massachusetts Wildlife Federation 151 Tremont Street Boston, Massachusetts 02111 Plymouth Public Library 1

North Street Plymouth, Massachusetts 02360 l